HomeMy WebLinkAboutChange Order Nos 2-3 - Coal Line Trail, Phase IIA Proj No. 115-063 - INDOT Selge ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BRIANA N. MICOU 1316 COUNTY-CITY BUILDING 227 W. JEFFERSON BOULEVARD SOUTH BEND, INDIANA 46601-1830 PHONE 574/ 235-9251 FAX 574/ 235-9171 CITY OF SOUTH BEND JAMES MUELLER, MAYOR BOARD OF PUBLIC WORKS April 23, 2024 Mr. Robert Kuhns Selge Construction Co., Inc. 2833 South 11TH St. Niles, MI 49120 aswinehart@selgeconstruction.com RE: Change Order Nos. 2-3 – Coal Line Trail, Phase IIA – (DES#1401810) Project No. 115-063 Dear Mr. Kuhns: At its April 23, 2024 meeting, the Board of Public Works approved the above referenced Change Order to be increased $164,482.99 (City) with an additional one hundred & sixty-six (166) days, bringing the revised contract amount to $1,934,536.64 with a new completion date of December 31, 2021. Enclosed is a copy of the Change Order for your records. If you have any further questions, please call this office at (574) 235-9251. Sincerely, /s/ Theresa Heffner Theresa Heffner, Clerk Enclosures TH/lh INTER-OFFICE MEMORANDUM DEPARTMENT OF PUBLIC WORKS TO: Board of Public Works FROM: Gemma Stanton, Project Engineer SUBJECT: Change Order #2 and #3 Coal Line Trail Phase 2A DATE: 4/15/2024 Attached are Change Orders 2 and 3 for the Coal Line Trail Phase 2A project. Original Contract amount: $1,696,460.65 Previously approved change orders: $73,593.00 Percent Increase Including Requested: 13.5% New Contract Amount: $1,934,536.64 Change order #2 is for additional fill needed on the project. Increase Amount: Total Percent Increase: $50,821.12 Total (All Local Funds) 2.99% Revised Contract Amount $1,747,281.77 Change order #3 is for adding a section of guardrail to the project at the City’s request. Increase Amount: $113,661.87 Total (All Local funds) Total Percent Increase: 6.7% Revised Contract Amount: $1,934,536.64 As this is a federal aid project, INDOT is responsible for the construction contract with Selge. INDOT will invoice the City the amount of the local share once approved. As these changes are non- participating, the City will pay for 100% of each change order. It is requested the Board of Public Works approve Change Orders 2 and 3 the Coal Line Trail Phase 2A Project (115-064) for a total increase of $164,482.99 (Local share of 100%) which is a total increase of 13.5% to the contract price bringing the new contract price to $1,934,536,64. Thank you for your consideration of this request. Contract No:R -38065 Change Order No.: 002 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -38065 Letting Date:09/14/2022 District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Dietz, Don Status:Draft Change Order Information Change Order No.: 002 EWA: Y or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: CHANGED COND, Constructability Related Description: Borrow for new trail elevation Original Contract Amount $ 1,696,460.65 Current Change Order Amount $ 50,821.12 Percent: 2.996 % Total Previous Approved Changes $ 73,593.00 Percent: 4.338 % Total Change To-Date $ 124,414.12 Percent: 7.334 % Modified Contract Amount $ 1,820,874.77 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension SS Days 0 SP Days 7 SP Days Value $ 0.00 Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______ SS Days____________ SP Days Value $ _______________ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -38065 Change Order No.: 002 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______* ($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- ) (Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days) Verbal Approval Required? Y / N If Y, by_____________ Date Issued___________ Total Change To-Date>5%? Y / N If Y , Copy to Program Budget Manager_________________ Scope/Design Recommendation Required? Y / N If Y, Referred to Project Manager(PM) __________________ Date to PM__________ Date Returned___________ Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________ If N,Resolution: Approved __________ Disapproved ___________ Resolved by_________________________ Date__________ LPA Signatures Required? Y / N If Y, Date to LPA _____________ Date Returned _________ FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________ * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer _________________________ Date _____________ Comments: ____________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Contract No:R -38065 INDIANA Date:03/21/2024 Change Order No:002 Department of Transportation Page: 3 Contract:R -38065 Project:1401811 - State:140181100LC4 Change Order Nbr: 002 Change Order Description: Borrow for new trail elevation Reason Code:CHANGED COND, Constructability Related CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change 0090 1401811 0090 203-02070 CYS 28.850 1184.000 C Amount:$ 34,158.40 Item Description:BORROW Supplemental Description1: Indiana Earth Material Supplemental Description2: 0091 1401811 0091 203-02070 CYS 20.420 816.000 C Amount:$ 16,662.72 Item Description:BORROW Supplemental Description1: Notre Dame Supplied Material Supplemental Description2: Total Value for Change Order 002 = $ 50,821.12 Milestone Time Adjustment MileStone Nbr: 01 Milestone Description: CSGP INTERMEDIATE COMPLETION DATE Original Completion dt: 09/01/2023 Adj compl dt 09/08/2023 Adj No. of Days 7 Explanation:Time added for work added to contract to include the placement of borrow on the trail at the request of Notre Dame in agreement with the city of South Bend. Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation This Change Order was created to raise the elevation of the trail as requested by Notre Dame and agreed to by the City of South Bend. Notre Dame orignally offered material, but there was a miscommunication as to how the material would be delivered. During this time, Selge sought out another option thinking the cost of material plus trucking from Notre Dame would be more expensive. Selge began receiving material from Indiana Earth for what was thought to be cheaper. It was then discovered Notre Dame's price included delivery, therefore Selge switched and accepted the material from Notre Dame. Both items are nonparticipating. Change Order Explanation for Specific Line Item **************************************************************************************************************************** It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor:____________________________________________Signed By:_____________________________________________ Date:__________________________________________________ *************************************************************************************************************************** NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Contract No:R -38065 INDIANA Date:03/21/2024 Change Order No:002 Department of Transportation Page: 4 **************************************************************************************************************************** APPROVED FOR LOCAL PUBLIC AGENCY SUBMITTED FOR CONSIDERATION PE/S _________________________ **************************************************************************************************************************** APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION Approval Level Name of Approver Date Status April 23, 2024 Contract No:R -38065 Change Order No.: 003 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -38065 Letting Date:09/14/2022 District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Dietz, Don Status:Draft Change Order Information Change Order No.: 003 EWA: Y or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: SCOPE CHANGES, Added Quantities/Items Description: Guardrail Addition Original Contract Amount $ 1,696,460.65 Current Change Order Amount $ 113,661.87 Percent: 6.700 % Total Previous Approved Changes $ 73,593.00 Percent: 4.338 % Total Change To-Date $ 187,254.87 Percent: 11.038 % Modified Contract Amount $ 1,883,715.52 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension SS Days 0 SP Days 159 SP Days Value $ 0.00 Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______ SS Days____________ SP Days Value $ _______________ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -38065 Change Order No.: 003 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______* ($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- ) (Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days) Verbal Approval Required?Y / N If Y, by_____________ Date Issued___________ Total Change To-Date>5%?Y / N If Y , Copy to Program Budget Manager_________________ Scope/Design Recommendation Required? Y / N If Y, Referred to Project Manager(PM) __________________ Date to PM__________ Date Returned___________ Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________ If N,Resolution: Approved __________ Disapproved ___________ Resolved by_________________________ Date__________ LPA Signatures Required?Y / N If Y, Date to LPA _____________ Date Returned _________ FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________ * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer _________________________Date _____________ Comments: ____________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Contract No:R -38065 INDIANA Date:03/26/2024 Change Order No:003 Department of Transportation Page: 3 Contract:R -38065 Project:1401811 - State:140181100LC4 Change Order Nbr: 003 Change Order Description: Guardrail Addition Reason Code:SCOPE CHANGES, Added Quantities/Items CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change 0092 1401811 0092 110-01001 LS 15,800.000 1.000 C Amount:$ 15,800.00 Item Description:MOBILIZATION AND DEMOBILIZATION Supplemental Description1: Mobilization and demobilization for added guardrail work Supplemental Description2: 0093 1401811 0093 801-06775 LS 19,500.000 1.000 C Amount:$ 19,500.00 Item Description:MAINTAINING TRAFFIC Supplemental Description1: MOT for guardrail Supplemental Description2: 0094 1401811 0094 601-02241 LFT 21.000 455.000 C Amount:$ 9,555.00 Item Description:GUARDRAIL REMOVE Supplemental Description1: Supplemental Description2: 0095 1401811 0095 202-93615 SYS 54.000 70.000 C Amount:$ 3,780.00 Item Description:CONCRETE REMOVE Supplemental Description1: Concrete under existing guardrail Supplemental Description2: 0096 1401811 0096 601-99105 LFT 39.750 437.500 C Amount:$ 17,390.62 Item Description:GUARDRAIL W-BEAM 6 FT 3 IN SPACING Supplemental Description1: Supplemental Description2: 0097 1401811 0097 601-62110 LFT 30.000 437.500 C Amount:$ 13,125.00 Item Description:GUARDRAIL CHANNEL 6.7 LBS/FT INSTALL Supplemental Description1: Supplemental Description2: 0098 1401811 0098 601-61390 EACH 150.000 3.000 C Amount:$450.00 Item Description:GUARDRAIL TERMINAL END SECT CURVE SNG GV Supplemental Description1: Supplemental Description2: 0099 1401811 0099 601-06273 EACH 5,250.000 1.000 C Amount:$ 5,250.00 Item Description:GUARDRAIL END TREATMENT TYPE SKT-350 Supplemental Description1: Supplemental Description2: 0100 1401811 0100 602-06729 EACH 37.500 72.000 C Amount:$ 2,700.00 Item Description:BARRIER DELINEATOR Supplemental Description1: Supplemental Description2: 0101 1401811 0101 802-09840 SFT 29.000 64.000 C Amount:$ 1,856.00 Item Description:SIGN SHEET WITH LEGEND 0.100 IN Supplemental Description1: Contract No:R -38065 INDIANA Date:03/26/2024 Change Order No:003 Department of Transportation Page: 4 Supplemental Description2: 0102 1401811 0102 802-05704 LFT 30.000 90.000 C Amount:$ 2,700.00 Item Description:SIGN POST SQ 1 UNREINFORCED ANCHOR BASE Supplemental Description1: Supplemental Description2: 0103 1401811 0103 802-07057 SFT 50.000 64.000 C Amount:$ 3,200.00 Item Description:SIGN PANEL WITH LEGEND Supplemental Description1: Supplemental Description2: 0104 1401811 0104 621-06570 CYS 275.000 11.500 C Amount:$ 3,162.50 Item Description:TOPSOIL Supplemental Description1: Supplemental Description2: 0105 1401811 0105 621-06574 SYS 13.700 68.000 C Amount:$931.60 Item Description:SODDING Supplemental Description1: Supplemental Description2: 0106 1401811 0106 105-06807 LS 14,261.140 1.000 C Amount:$ 14,261.14 Item Description:ADDITIONAL Supplemental Description1: Added Labor and Material for Existing Utility Conflict for Supplemental Description2: Post Installation Total Value for Change Order 003 = $ 113,661.86 Milestone Time Adjustment MileStone Nbr: 01 Milestone Description: CSGP INTERMEDIATE COMPLETION DATE Original Completion dt: 09/01/2023 Adj compl dt 02/07/2024 Adj No. of Days 159 Explanation:City requested addition of guardrail as a non participating change order. Contract intermediate completion date was extended to complete all work provided. This was an unplanned addition and therefore took a longer amount of time to precure all materials needed. Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation This change order includes multiple items for the addition of guardrail added by the request of the city. The guardrail is being replaced on Angela Blvd adjacent to the trail. All items are non-participating. The item Additional LS was added in order to complete the guardrail installation on the north side of Angela Rd. due to a conflict with an exisitng gas line. All post holes had to be excavated with a vac truck. As the post holes were excavated, many locations had existing pavement in direct conflict with the post hole. The pavement located in conflict had to be jack hammered out and the vac truck then continued to excavate the hole to the proper depth. Flowable fill was requierd for backfill for the guardrail posts. There was Time is being added to milestone 1 to cover the additional work, and the PM has been notified. Change Order Explanation for Specific Line Item **************************************************************************************************************************** It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor:____________________________________________Signed By:_____________________________________________ Date:__________________________________________________ *************************************************************************************************************************** Contract No:R -38065 INDIANA Date:03/26/2024 Change Order No:003 Department of Transportation Page: 5 NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Contract No:R -38065 INDIANA Date:03/26/2024 Change Order No:003 Department of Transportation Page: 6 **************************************************************************************************************************** APPROVED FOR LOCAL PUBLIC AGENCY SUBMITTED FOR CONSIDERATION PE/S _________________________ **************************************************************************************************************************** APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION Approval Level Name of Approver Date Status April 23, 2024 BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date 4/15/2024 Name Gemma Stanton Department PW BPW Date 4/23/2024 Phone Extension 9083 Review and Approval Required Prior to Submittal to Board Diversity Compliance and Inclusion Officer Officer Name BPW Attorney Attorney Name Dept. Attorney Attorney Name Purchasing Ron O'Connor Check the Appropriate Item Type – Required for All Submissions Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA Chg. Order, No. 2-3 Traffic Control Resolution Other: Ease./Encroach Required Information Company or Vendor Name INDOT (Contractor is Selge) New Vendor Yes If Yes, Approved by Purchasing No MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name Coal Line Trail Phase 2A Project Number 115-064 DES1401811 Funding Source Account No. PO-0025244 Amount $1,934,536.64 Total Terms of Contract Purpose/Description See attached memo. For Change Orders Only Amount of Increase Decrease $164,482.99 Total ($ ) Previous Amount $ 1,770,053.65 Current Percent of Change: Increase Decrease 9.29% ( %) New Amount $1,934,536.64 Total Percent of Change: Increase Decrease 13.5% ( %) Time Extension Amount: 166 Days New Completion Date: 12/31/2021