Morris Performing Arts Center
South Bend Common Council
April 8, 2024
1
2
Community Wide Free Events
Fridays by the Fountain – 13 Free Concerts with over 4,000 attendees
Symphony Under the Stars – 1,030 attendees
Dia de los Muertos – 1,200 attendees
Morris Performing Arts Center 2023
3
Theater Improvements
MORRIS PERFORMING ARTS CENTER
PHASE I IMPROVEMENTS - $10M
Removed and replaced the concrete, steel, and utilities within the main floor of the theater
Removed and replaced all seats
Repainted handrails
Removed and replaced all carpet within the theater, lobbies, and Palais Royale
4
MORRIS PERFORMING ARTS CENTER
PHASE I IMPROVEMENTS - $10M
Guaranteed Energy Savings
Boiler & pump replacement
Air handling unit replacement
Rooftop unit and mechanical air unit replacement
Heat pump controls upgrades
New building automation system
Plumbing fixture replacement
Roofing replacement
Fire alarm system replacement
LED lighting upgrades
5
Morris Performing Arts Center
Phase I Improvements
6
RACLIN MURPHY ENCORE CENTER AT THE MPAC
Phase II - $16.5M
Dynamic building addition to the Morris Performing Arts Center (MPAC)
Provides an extra 20,000 sq/ft of floor space for special events of all kinds, circulation, additional restrooms, storage and theater support
Additional space and access to existing building facilitates support for the Equity in the Arts Program
7
RACLIN MURPHY ENCORE CENTER AT THE MPAC
Public bidding process begins in Spring
Construction starts late Summer 2024
Construction expected to take 16 months
8
RACLIN MURPHY ENCORE CENTER AT THE MPAC
9
Raclin Murphy Encore Center Funding
No local tax dollars for Phase II
$9 million general fund appropriation reimbursed by PSCDA
$6 million private donations
$1.5 million READI Grant
10
RACLIN MURPHY ENCORE CENTER AT THE MPAC
11
MPAC Garage Development – Phase III
$12+ million estimated budget – depends on number of parking spaces required
Driven by development opportunity and MPAC need
Anticipated construction start 2026
$9 million currently pledged in private donations for Phase III
12
Finance Summary of MPAC Phases I, II and III
$10 million Hotel-Motel Tax/Energy Savings
$16.5+ million of private donations
$9 million PSCDA
TBD additional development and private investment for Phase III