HomeMy WebLinkAboutChange Order No 4 - North Water Treatment Plant Improvements Proj No. 119-011 - Bowen
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BRIANA N. MICOU
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
February 13, 2024
Mr. Mitchell Stull
Bowen Engineering Corporation
8802 N. Meridian St.
Indianapolis, IN 46260
mstull@bowenengineering.com
RE: Change Order No. 4 – North Water Treatment Plant Improvements
Project No. 119-011
Dear Mr. Stull:
At its February 13, 2024, meeting, the Board of Public Works approved the above
referenced Change Order be increased by $107,501 with an additional two hundred ten (210)
days, bringing the revised contract amount to $3,664,828 with a new completion date of April
12, 2024.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO.
SUBJECT OF CHANGE ORDER: Schedule 80 PVC Pipe and Coupling Adapter to replace failing
discharge head.
The original contract sum $
Net change by previously authorized change orders $
The contract sum prior to this change order $
By this Change Order, the project amount is Increased
Decreased $
The new contract sum including this change order $
This Change Order represents a total change of %
Total change for entire project %
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
RECOMMENDED FOR APPROVAL
CONTRACTOR
PROJECT MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Date:
Contractor Signature
Printed Name and Title Elizabeth A. Maradik, President
Company name Joseph R. Molnar, Vice President
Address Gary A. Gilot, Member
City, State, Zip Briana Micou, Member
Murray L. Miller, Member
01/02/2024
119-011
North Water Treatment Plant Improvements
04/26/2022
4
3,582,800.00
X
(25,473.00)
3,557,327.00
107,501.00
3,664,828.00
2.3
3.0
Substantial: 8/15/22, Final 9/15/2022
441 days
Final completion: 04/12/2024
Mitchell Stull, Senior Project Engineer
Bowen Engineering
8802 N Meridian St.
Indianapolis, IN, 46260
210 days
February 13, 2024
8802 North Meridian St. • Indianapolis, IN 46260 317.842.2616 phone • 317.841.4257 fax • BowenEngineering.com PAGE 1 OF 2 December 21, 2023 City of South Bend Attn: Rebecca Plantz 227 West Jefferson Boulevard South Bend, IN 46601-1830 RE: South Bend North Treatment Plant Improvements Bowen Project Number: 15 – 22 – 042 PCO-08 Vessel #3 thru #5 FW Header Replacement, Phase II Rebecca: Bowen Engineering (BEC) is pleased to submit this proposal for the Owner’s review and approval for the additional scope of work of replacing a portion of the 30” stainless steel fabricated pipe on the common finish water header at the North Station. Attached is a one-line sketch of the proposed piping replacement associated with this proposal. Pricing Option #1 — Schedule 80 PVC Pipe and JCM 303 Fabricated Flanged Coupling Adapter Lump Sum Cost: $ 107,501.00 Scope of Work: - Remove existing stainless steel fabricated pipe from 24” flange to 18” flanges on common finish water header on the second floor of the North Station. - Cut existing 18” vertical riser as needed to install new schedule 80 PVC piping. Use JCM Model #303 Fabricated Flange Coupling Adapter or equal to connect schedule 80 PVC piping to existing schedule 10 stainless steel piping. - Reuse existing hangers Clarifications: - No pressure testing has been included other than an in-service test. - No weld inspection / NDE Testing has been included. - One mobilization has been included. Additional mobilization if required will incur additional costs. - No overtime / premium time has been included. - Pipeline can be isolated for the duration required to complete the scope of work. - Plant personnel will be responsible for isolation of areas as required to complete the scope of work. - Additional contract time will be required. A revised completion date will be mutually agreed to.
8802 North Meridian St. • Indianapolis, IN 46260 • 317.842.2616 phone • 317.841.4257 fax • www.BowenEngineering.com PAGE 2 OF 2 Pricing Option #2 — Replace in kind stainless steel. Lump Sum Cost: $ 199,346.00 Scope of Work: - Remove existing stainless steel fabricated pipe from 24” flange to 18” flanges on common finish water header on the second floor of the North Station. - Cut existing 18” vertical riser as needed and install new 18” stub end. - Reuse existing hangers. - New piping to be 316L stainless steel, Heliarc welded, and argon purged. Clarifications: - No pressure testing has been included other than an in-service test. - No weld inspection / NDE Testing has been included. - One mobilization has been included. Additional mobilization if required will incur additional costs. - No overtime / premium time has been included. - Pipeline can be isolated for the duration required to complete the scope of work. - Plant personnel will be responsible for isolation of areas as required to complete the scope of work. - Zimmerman is a trusted contractor of the City of South Bend. Therefore, to reduce the cost of the proposal, BEC has eliminated supervision cost to oversee Zimmerman and will not be onsite. - Additional contract time will be required. A revised completion date will be mutually agreed to. Thank you for the opportunity, Mitchell Stull, Senior Project Engineer Mobile: 317-650-8313 | Email: mstull@bowenengineering.com
City of South Bend
Department of Administration & Finance
Change Order Request Form
Multiple PO lines:
Project POs:
PO Number PO-0016353
Line Number 5
Original Dollar Amount $0.00
New Dollar Amount
(For liquidation request, enter $0)$5,687.00
Reason Code (if changed)na
Financial Dimensions (fund-dept-
division-subdivision-main account)622-06-604-620-42005
Project Code (if applicable)PROJ-56
Description of change (include
budget impact)
Decrease in the contract as a net total of field orders and savings under the
allowances and unit prices.
APPROVED BY PROJECT
ACCOUNTING TEAM (if applicable)
PO Number
Line Number
Original Dollar Amount
New Dollar Amount
(For liquidation request, enter $0)
Reason Code (if changed)
Financial Dimensions (fund-dept-
division-subdivision-main account)
Project Code (if applicable)
Description of change (include
budget impact)
APPROVED BY PROJECT
ACCOUNTING TEAM (if applicable)
PO Number
Line Number
Original Dollar Amount
Changing the line amount:
You can only change a line amount if it has NOT been invoiced against.
• If the line has NOT been invoiced – reduce the line amount to equal what it should be.
• If the line has been invoiced – cancel the delivery remainder and finalize the individual line, then add a new line for the
amount that should be remaining.
If you have changes to more than two lines on the same PO, fill out a separate section for each line affected by the change
order.
For change orders on project-related POs, this form must be approved by the Project Accounting Team as described in
Supplement 508.
Change Order Request Form - North WTP CO4 1 of 3
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 02/02/2024
Name Becca Plantz Department Public Works
BPW Date 02/13/2024 Phone Extension 5998
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name BPW Attorney Attorney Name Michael Schmidt
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 4 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Bowen Engineering Corporation
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name North Water Treatment Plant Improvements
Project Number 119-011
Funding Source River West TIF & Water Works Capital
Account No. PO-16353
Amount
Terms of Contract
Purpose/Description Increasing the contract amount and extending the completion date in the
contract to encompass field orders on the failing discharge head pipe.
For Change Orders Only
Amount of
Increase
Decrease
$107,501.00
$
Previous Amount $ 3,557,327.00
Current Percent of Change:
Increase
Decrease
3.0%
(%)
New Amount $ 3,664,828.00
Total Percent of Change:
Increase
Decrease
2.3%
(%)
Time Extension Amount: 210 Days
New Completion Date: Final: 04/12/2024