INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Administrative Assistant
Board of Public Works
FROM: Scott Kreeger, Project Engineer
SUBJECT: Project No. 123-066
Michigan Street Paving from S. Ireland to Chippewa Ave
DATE: January 26, 2024
INDOT’s current US 31/20 Bridge Replacement project has allowed the City the opportunity to
extend the project limits from south of the Ireland and Ironwood intersection instead to
Chippewa Avenue. The City portion of the project was completed in November 2023, which
resulted in an underrun of milling and intermediate HMA quantities. The attached INDOT
change order document is listed as Change Order No. 27 as part of the overall INDOT project;
however, this is the first and final change order for the City portion of the project. The
over/underruns are included in the attached documents along with further justification for the
quantities.
Please call with your questions (9245).
Contract No:B -40600 Change Order No.: 027
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: B -40600 Letting Date:11/17/2021
District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Borggren, Kent Status:Draft
Change Order Information Change Order No.: 027 EWA: N or Force Acct: N
Date Generated: 01/09/2023 Date Approved: 00/00/0000
Reason Code: FINAL QUANTITY ADJUSTMENT
Description: Over/Under CO for the City of South Bend
Original Contract Amount $ 10,924,942.00
Current Change Order Amount $ -21,755.80 Percent: -0.199 %
Total Previous Approved Changes $ 1,942,581.97 Percent: 17.781 %
Total Change To-Date $ 1,920,826.17 Percent: 17.582 %
Modified Contract Amount $ 12,845,768.17
Time Extension Information
Date Initiated 00/00/0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description:
Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00
Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______
SS Days____________ SP Days Value $ _______________
Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
Contract No:B -40600 Change Order No.: 027
INDIANA Department of Transportation Page: 2
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______*
($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- )
(Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days)
Verbal Approval Required? Y / N If Y, by_____________ Date Issued___________
Total Change To-Date>5%? Y / N If Y , Copy to Program Budget Manager_________________
Scope/Design Recommendation
Required?
Y / N If Y, Referred to Project Manager(PM) __________________
Date to PM__________ Date Returned___________
Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________
If N,Resolution: Approved __________ Disapproved ___________
Resolved by_________________________ Date__________
LPA Signatures Required? Y / N If Y, Date to LPA _____________ Date Returned _________
FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer _________________________ Date _____________
Comments: ____________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
Contract No:B -40600 INDIANA Date:01/09/2024
Change Order No:027 Department of Transportation Page: 3
Contract: B -40600
Project: 1701538 - State:170153800ST4
Change Order Nbr: 027
Change Order Description: Over/Under CO for the City of South Bend
Reason Code: FINAL QUANTITY ADJUSTMENT
CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change
0209 1701538 0147 306-08038 SYS 8.300 -2576.000 C Amount:$ -21,380.80
Item Description:MILLING ASPHALT 4 IN
Supplemental Description1: City of South Bend
Supplemental Description2:
0210 1701538 0148 109-08440 DOL 1.000 25595.000 C Amount:$ 25,595.00
Item Description:QUALITY ADJUSTMENTS HMA
Supplemental Description1: City of South Bend
Supplemental Description2:
0212 1701538 0150 401-07404 TON 98.000 -265.000 C Amount:$ -25,970.00
Item Description:QC/QA-HMA 4 76 INTERMEDIATE 19.0 mm
Supplemental Description1: City of South Bend
Supplemental Description2:
Total Value for Change Order 027 = $ -21,755.80
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
The original calculations for the asphalt milling were rough calculations. When the milling was field measured it amounted to 2576 Syds less than
anticipated. Asphalt quantities were based on rough calculations and the amount of Intermediate was 265 Tons under the anticipated amount.
The original amount of Quality Adjustment was placed at $1.00 to have the item available without creating a new change order once all of the
testing was completed. After the testing was complete an additional $25,595.22 was due to the contractor based on results from INDOT Testing.
General or Standard Change Order Explanation
A contract time adjustment is not required for this change.
Change Order Explanation for Specific Line Item
****************************************************************************************************************************
It is the intent of the parties that this change order is full and complete compensation for the work describe above.
Notification and consent to this change order is hereby acknowledged.
Contractor:____________________________________________ Signed By:_____________________________________________
Date:__________________________________________________
***************************************************************************************************************************
NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system.
Contract No:B -40600 INDIANA Date:01/09/2024
Change Order No:027 Department of Transportation Page: 4
****************************************************************************************************************************
APPROVED FOR LOCAL PUBLIC AGENCY
SUBMITTED FOR CONSIDERATION
PE/S _________________________
****************************************************************************************************************************
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Approval Level Name of Approver Date Status
February 13, 2024
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 2/6/24
Name Scott Kreeger
Department Public
Works
BPW Date 2/13/24 Phone Extension 9245
Required Prior to Submittal to Board
BPW Attorney Attorney Name Michael Schmidt
Dept. Attorney Attorney Name
Purchasing Mickey Lovy
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 27 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Indiana Department of Transportation
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Michigan Street Repaving
Project Number 123-066 (DFO Proj 420) PO-26258
Funding Source Southside Development TIF
Account No. 430-10-102-121-442001
Amount
Terms of Contract
Purpose/Description _As part of the INDOT contract agreement for the mill & overlay of
Michigan, the final change order processed through INDOT includes a deduct
to the City’s portions.
For Change Orders Only
Amount of Increase
Decrease
$
($ 21,755.80)
Previous Amount $ 978,170.66
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $ 956,414.86
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: