HomeMy WebLinkAboutChange Order No 1 - LaSalle Park Improvements Proj No. 121-015 - HRP Construction1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/235-9251
FAx 574/235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
February 13, 2024
Mr. Matthew D. Cain
HRP Construction, Inc.
5777 Cleveland Road
South Bend, IN 46624
jeredb&hrpconstruction.com; cind vghrpconstruction.com
RE: Change Order No. 1 — LaSalle Park Improvements — Project No. 121-015
Dear Mr. Cain:
At its February 13, 2024 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $371,755.22 with an additional one hundred sixty-two
(162) days, bringing the revised contract amount to $2,475,839.62 with a new completion date
of June 7, 2024.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BRIANA N. MIcou
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Patrick Sherman
SUBJECT: LaSalle Park Improvements: Change Order #1
Project 121-015
DATE: 01 /08/2024
Greetings,
Attached is Change Order #1 for the LaSalle Park Improvements project. There are a variety of
improvements contained and detailed therein. The majority of the cost increase is due to EPA
mandated work associated with the Park's Soil Management Plan that were originally thought to
be not necessary. Following the award, Public Works was informed of the additional Soil
Management Plan requirements on the project. Public Works sought and received additional
funding through the RDC as well as VPA in order to cover the additional costs.
The total change order is for $371,755.22, which is 17.67% of the original contract. Some
additional costs were requested and rejected as not being approved by the inspection team.
Thank you for your consideration, and please call with any questions.
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE: 12/15/2023
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO:
SUBJECT OF CHANGE ORDER:
121-015
Lasalle Park Im
5/23/2023
1
PCR #2-Temp fencing per EPA PCR #3-Add geotextile fabric per
EPA PCR #4-Haul spoils per EPA PCR #5-Import topsoil due to
lead content in soil per EPA PCR #7-Hazwoper refresher training
per EPA PCR #8-Replace deteriorated Tesco cabinet PCR #9-Add
flagpole in front of Charles Black building PCR #10-Additional
Sand PCR #12-Additional Aggregate PCR #14-Additional Trash
Receptacles PCR #15-Asphalt Savings PCR #16-Court Refurbish
Extension 162 days 6/7/2024
The original contract sum
$
2,104,084.40
Net change by previously authorized change orders
$
0.00
The contract sum prior to this change order
$
2,104,084.40
By this Change Order, the project amount is
�X Increased
Decreased $
371,755.22
The new contract sum including this change order
$
2,475,839.62
This Change Order represents a total change of
17.67 %
Total change for entire project
17.67 %
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
Matthew D. Cain, President
Printed Name and Title
HRP Construction
Company Name
5777 Cleveland Road
Address
South Bend, IN 46628
City, State, Zip
12/28/2023
0 days
162 days
6/7/2024
RECOMMENDED FOR APPROVAL
CO RUCTION MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
=
Elizabeth A. Maradik, President
Gary A. Gilot, Member
Murray L. Miller, Member
Joseph R. Molnar, Vice President
Briana Micou, Member
4(//.
Attest: Theresa M. Heffner, Clerk
Date: February 13, 2024
Resolved
I
Resolved
Pending Pending
Days
Ori inal
C.O. Days
C.O. Date
Days Date
NTP
8/1 /2023
Substantial
Com letion 107
11/16/2023
162
4/26/2024
0 4/26/2024
Final
Completion 149
12/28/2023
162
6/7/2024
0 6/7/2024
Change Order Form
Time Added
Amount
Change
Order
Change
Order Subject of Change Order
View
Final ?
Resolved
Resolved Resolved
View -able
[Days]
Number
Date
Form?
Amount
Days Subjects
Subjects
Temp fencing per
PCR #2-Temp
$17,500.00
1
12/15/2023 Temp fencing per EPA
yes
$17,500.00
EPA
fencing per EPA
PCR #3-Add
Add geotextile
geotextile fabric
$28,000.00
1
12/15/2023 Add geotextile fabric per EPA
yes
$28,000.00
fabric per EPA
per EPA
Haul spoils per
PCR #4-Haul
$98,878.50
1
12/15/2023 Haul spoils per EPA
yes
$98,878.50
EPA
spoils per EPA
PCR #5-Import
Import topsoil due
topsoil due to lead
Import topsoil due to lead
to lead content in
content in soil per
$49,440.00
1
12/15/2023 content in soil per EPA
yes
$49,440.00
soil per EPA
EPA
Hazwoper
PCR #7-Hazwoper
Hazwoper refresher training
refresher training
refresher training
$21,500.00
1
12/15/2023 per EPA
yes
$21,500.00
per EPA
per EPA
Replace
PCR #8-Replace
Replace deteriorated Tesco
deteriorated Tesco
deteriorated Tesco
$16,782.00
1
12/15/2023 cabinet
yes
$16,782.00
cabinet
cabinet
PCR #9-Add
Add flagpole in
flagpole in front of
Add flagpole in front of
front of Charies
Charles Black
$6,820.00
1
12/15/2023 Charles Black building
yes
$6,820.00
Black building
building
PCR
#10-Additional
$52,952.72
1
12/15/2023 Additional Sand
yes
$52,952,72
Additional Sand
Sand
PCR
Additional
#12-Additional
$77,352.00
1
12/15/2023 Additional Aggregate
yes
$77,352.00
Aggregate
Aggregate
PCR
Additional Trash
#14-Additional
$7,530.00
1
12/15/2023 Additional Trash Receptacles
yes
$7,530.00
Receptacles
Trash Receptacles
PCR #15-Asphalt
-$5,000.00
1
12/15/2023 Asphalt Savings
yes
-$5,000.00
Asphalt Savings
Savings
PCR #16-Court
Court Refurbish
Refurbish
Court Refurbish Extension
Extension 162
Extension 162
162
1
12/15/2023 162 days 6/7/2024
yes
162 days 6/7/2024
days 6/7/2024
Final Type w/Resolved CO # w/Resloved
Unforeseen 1
Unforeseen 1
Unforeseen 1
Unforeseen 1
Unforeseen 1
Unforeseen 1
Unforeseen 1
Unforeseen 1
Unforeseen 1
Other 1
Other 1
Other 1
Lasalle Park Improvement Project
HRP Construction 12/19/2023
Change Order 1
CITY Unit
Unit Price
Ext Price
Sand
Full Unit Price
800 Tons
$ 42.30
$
337840.00
1 /2 of Unit Price
868.76 Tons
$ 22.00
$
19,112.72
Total Payment Proposed
$
52,952.72
#53 Aggregate
Full Unit Price
620 Tons
$ 120.00
$
74,400.00
1 /2 of Unit Price
641.2 Tons
$ 60.00
$
387472.00
Total Payment Proposed
$ 112,872.00
Fencing
1 LS
$ 17,500.00
$
17,500.00
Geotextile
7000 SY
$ 4.00
$
28,000.00
Haul off spoils
4515 CY
$ 21.90
$
98,878.50
Importing Topsoil
1200 CY
$ 41.20
$
49,440.00
Hazwoper Certification and Decontamination
1 LS
$ 21,500.00
$
21,500.00
New Load Center Cabinet
1 LS
$ 16,782.00
$
16,782.00
Flag Pole Base
1 LS
$ 6,820.00
$
6,820.00
Site Furnishing - Trash Receptacles
2 EA
$ 3,765.00
$
7,530.00
Deduct for Asphalt
1 LS
$ (51000.00)
$
(51000.00)
IDeduct for 296 TONS
Total Change Order 1
$ 407,275.22 1
296 Tons 120 $ 35,520.00 1
$ 371,755.22
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 02/06/2024
Name: Patrick Sherman Department of Public Works — Engineering Division
BPW Date: 02/13/2024 Phone Extension: 5601
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Michael Schmidt
Dept. Attorney ❑ Attorney Name Michael Schmidt
Purchasing ❑ Mickey Low
Check the Appropriate Item Type — Required. for All Submissions
❑ Professional Services Agreement ❑ Contract ❑ Proposal
❑ Open Market Contract ❑ Amendment/Addendum ❑ Special Purchase, QPA
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award ❑ Reject Bids/Quotes
❑ Proposal Opening ❑ C/O & PCA No. ❑ PCA
® Chg. Order, No. 1 ❑ Traffic Control ❑ Resolution
n Other: n Ease./Encroach
Company or Vendor Name
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Special Contract Provisions
Purpose/Description
Information
HRP Construction
❑ Yes[:] If Yes, Approved by Purchasing
® No
MBE ❑ WBE Completed E-Verify Form Attached Yes
❑ No
LaSalle Park Improvements
121-015
PO #24048
$371,755.22
Public Bid
N/A
Change order for multiple cost increases primarily because of EPA mandated
soil management plan on project site.
For Change Orders Only
Amount of ® Increase $ 371,755.22
❑ Decrease ($ )
Previous Amount $ 2,104,084.40
Current Percent of Change
New Amount
Total Percent of Change;
Time Extension Amount
New Completion Date:
Increase
Decrease
$ 2,475,839.62
Increase
Decrease
162 Days
06/07/2024
17.67%
17.67%