February 13, 2024
Mr. Jason DeMeyer
D.A. Dodd, LLC
14 E. Michigan St.
Rolling Prairie, IN 46371
jasondemeyer@dadodd.com
RE: Change Order No. 1 – Century Center Water Softener – Project No. 123-041
Dear Mr. DeMeyer:
At its February 13, 2024 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $10,900 with an additional twenty-eight (28) days,
bringing the revised contract amount to $80,600 with a new completion date of February 23,
2024.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE: 02/16/2024
PROJECT NO: 123-041
PROJECT NAME: Century Center Water Softener Replacement
CONTRACT DATE: 10/10/2023
CHANGE ORDER NO. 1
SUBJECT OF CHANGE ORDER: Need to repair existing sump pump in order to start up new
water softener system.
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns.
The original contract sum $ 69,700.00
Net change by previously authorized change orders $ 0.00
The contract sum prior to this change order $ 69,700.00
By this Change Order, the project amount is Increased
Decreased $ 10,900.00
The new contract sum including this change order $ 80,600.00
This Change Order represents a total change of 15.60 %
Total change for entire project 15.60 %
Original contracted completion date/time January 26th, 2024
Extension of date/time by previous change orders 0 Days
Date/time extension by this change order 28 Days
New completion date/time February 23rd, 2024
RECOMMENDED FOR APPROVAL
CONTRACTOR Construction Manager
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Date: Contractor Signature
Printed Name and Title Elizabeth A. Maradik, President
Company name Gary A. Gilot, Member
Address Murray L. Miller, Member
City, State, Zip Breana N. Micou, Member
Joseph R. Molnar, Member
February 13, 2024
Quote Number:Quote By:Garrett McBride
Quote Date:Contact Email:garrettmcbride@dadodd.com
Customer Name: Customer Site Address:
Customer Contact:
Customer Contact PH:
Customer E-mail:
Job Description:
Replace existing ejector pump control panel and float system with new Liberty AE34 Series panel
and 3 floats. Turn off power supply to exisiting panel. Install temporary disconnect and on/off
switch for intermittent use of pumps. Demo existing control panel and floats. Install new
control panel and floats. Disconnect temporary power supply and connect pumps to new
control panel. Check new control panel and pump operation.
Special Exceptions/Lead Times:
If quote is acceptable please sign and return to garrettmcbride@dadodd.com or fax to 574-968-0590.
Signature of Acceptance: Date of Acceptance:
Accepted By: Customer PO#:
Terms: Net thirty (30) days from invoice completion date. Accounts over thirty (30) days are subject to 1-1/2 % per month
finance charge, 18% APR. Accounts over sixty (60) days are subject to mechanics lien.
D.A. Dodd, LLC agrees to provide labor and materials in the most timely manner allowable based upon agreed time frame and
available materials with exceptions for occurences beyond the control of D.A. Dodd, LLC.
All work to be performed during normal business ours between 7am and 4pm unless otherwise agreed upon.
Quote is valid for 10 (ten) days from date of this quote.
Labor: $5,280.00
Materials: $3,320.00
Sub-Contractors: $2,300.00
scotth@southbendin.gov
DA Dodd proposes to provide labor and materials to perform the above described job.
DA Dodd proposes to perform the above described job at the quoted price of :
$10,900.00
(Ten Thousand Nine Hundred dollars)
GM24-020
1/26/2024
City of South Bend
Scott Herczeg Century Center###
Mechanical | Plumbing | Sheet Metal
14 E. Michigan Street, Rolling Prairie IN 46371
3416 Rascal Drive, Lafayette IN 47909 2516 N. Home Street, Mishawaka IN 46545
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 02/06/2024
Name: Patrick Sherman Department of Public Works – Engineering Division
BPW Date: 02/13/2024 Phone Extension: 5601
Required Prior to Submittal to Board BPW Attorney X Attorney Name Michael Schmidt
Dept. Attorney Attorney Name Michael Schmidt
Purchasing Mickey Lovy
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 1 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name D. A. Dodd, LLC
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Century Center Water Softener
Project Number 123-041
Funding Source PO# 26879
Account No. 671-11-230-297-445008--PROJ00000429
Amount $10,900.00
Terms of Contract Public Quote
Special Contract Provisions N/A
Purpose/Description Change order for additional repairs needed to make softener system work.
For Change Orders Only
Amount of
Increase
Decrease
$ 10,900.00
($ )
Previous Amount $ 69,700.00
Current Percent of Change:
Increase
Decrease
15.6%
( %)
New Amount $ 80,600.00
Total Percent of Change:
Increase
Decrease
3.51%
( %)
Time Extension Amount: 28 Days
New Completion Date: 02/23/2024