HomeMy WebLinkAboutChange Order No 5 - Coal Line Trail Phase IIB Proj. No 122-035 - INDOT, Milestone Contractors North Inc.1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/235-9251
FAx 574/235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
January 23, 2024
Mr. Mike McDonald
Milestone Contractors North, Inc.
24358 State Road 23
South Bend, IN 46614
akrueger&mile stonelp. com
RE: Change Order No. 5 — Coal Line Trail, Phase IIB — Project No. 122-035
Dear McDonald:
At its January 23, 2024 meeting, the Board of Public Works approved the above
referenced Change Order be extended by ninety-eight (98) days with a new completion date of
May 1, 2024.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BRIANA N. MIcou
Contract No:B -44292
Change Order No.: 005
INDIANA Department of Transportation
Page: 1
Construction Change Order and Time Extension
Summary
Contract Information Contract No.: B -44292
Letting Date:09/14/2022
District: LAPORTE DISTRICT AE:Hauersperger, Steven
PE/S:Holth, Chris Status:Draft
Change Order Information Change Order No.: 005
EWA: N or Force Acct: N
Date Generated: 00/00/0000 Date Approved: 00/00/0000
Reason Code: CHANGED COND, Materials Related
Description: Delay in materials due to shop drawing change
Original Contract Amount $ 3,450,217.13
Current Change Order Amount $ 0.00
Percent: 0.000 %
Total Previous Approved Changes $ 58,318.38
Percent: 1.690 %
Total Change To -Date $ 58,318.38
Percent: 1.690 %
Modified Contract Amount $ 3,508,535.51
Time Extension Information
Date Initiated 00/00/0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description
Current Time Extension
Previous Time Approved
SS Days 0 SP Days 98
SS Days by AE: DCE
SS Days
SP Days Value $ 0.00
SCE: DDCM:
SP Days Value $
Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
Contract No:B -44292
INDIANA Department of Transportation
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority
($ per Change Order)
(Days per Contract)
Verbal Approval Required?
Total Change To-Date>5%?
Scope/Design Recommendation
Required?
Change Order No.: 005
Page: 2
AE: DCE: ✓ SGE-: * DDCM
(-LE$250K-) (-LE$750K-) (--LE$2M--) (--GT$2M--)
( 50 SS days) ( 100 SS days) ( 200 SS Days ) ( GT 200 SS days)
ON If Y, by S.Hauersperger Date Issued 01/02/24
Y / N If Y, Copy to Program Budget Manager
-
Y / N If Y, Referred to Project Manager(PM) _
Date to PM Date Returned
Approval Authority Concurs with PM? 0 N If Y, Concurrence by .LKrueckeburg ^ Date 01/08/24
If N,Resolution: Approved _ Disapproved
Resolved by Date
LPA Signatures Required? CD N If Y, Date to LPA 01/08/24 Date Returned
FHWA Signatures Required? Y 0f Y, Date to FHWA Date Returned
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer Date
Comments:
Contract No:B -44292
Change Order No:005
Contract:
Project:
Change Order Nbr
101a]/_10/_1
Department of Transportation
B -44292
State:220019900LC4
005
Change Order Description: Delay in materials due to shop drawing change
Reason Code: CHANGED COND, Materials Related
CLN PCN PLN Item Code Unit Unit Price CO aty Comment
Milestone Time Adjustment
MileStone Nbr: 01
Date:01 /02/2024
Page: 3
Amount Change
Total Value for Change Order 005 = $ 0.00
Milestone Description: CSGP INTERMEDIATE COMPLETION DATE
Original Completion dt: 09/01/2023 Adj comp) dt 12/15/2023 Adj No. of Days 98
Explanation: Due to a delay in getting shop drawings approved because of a change in railing post size this caused a delay in getting
materials ordered for the railing to be installed.
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
The contract plans showed the conduit with a Tee fitting at the base of each railing post with a lighting fixture. The electrical wire has to be pulled
into the post. It is not constructable to pull wire through conduit with Tee fittings. There needed to be 90 degree elbows coming into the post
railing from both directions. To have two 90 degree conduit elbows to turn up into the post from the concrete deck, the railing post had to be
widened. The post got widened from 5 inches to 7 inches to accommodate the two elbow fittings. In addition, an access panel was needed to be
able to access the wires to install and for future maintenance of the light fixtures. These changes to the railing post took a long time to discuss
and get approved. The final shop drawings for the railing were approved on May 9, 2023. At this point, the materials could be ordered for
fabrication. Then the railing had to be fabricated, galvanized, and then powder coated. Specialties received the railing at the beginning of the
week of November 6th and started that week with the installation. After the installation was complete, Hawk had to come in behind them to install
all of the light fixtures. This was completed on November 17th, 2023. The railing needed some touch up painting and the temperatures were not
warm enough to paint it until December 8th, 2023. This was the last day of work. This is 98 days beyond the original intermediate completion
date.
Change Order Explanation for Specific Line Item
It is the intent of the parties that this change order is full and complete compensation for the work describe above.
Notification and consent
to this change order is hereby acknowledged.
Contractor: aI" ` tf /`y,:,^'-- �a'^' / � " Signed By:
Date:,�7 I ��
NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system.
Contract No:B -44292 INDIANA Date:01/02/2024
Change Order No:005
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
t1tLNk
Elizabeth A. Maradik, President
Gary A. Gilot, Member
7,4—r K m
Department of Transportation
/ i l
Joseph R. Molnar, Vice President
Briana Micou, Member
Cl-14
Murray L. Miller, Member Attest: Theresa M. Heffner, Clerk
Date: Tannaty 23 2024
PENS C //,"
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Page: 4
Approval Level r Name of Approver _ Date Status�� n
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date:
Name
01/16/2024
Gemma Stanton
Department of Public Works — Engineering Division
BPW Date: January 23rd, 2024 Phone Extension: 9083
Required Prior to Submittal to Board
BPW Attorney ❑ Attorney Name Michael Schmidt
Dept. Attorney ❑ Attorney Name
Purchasing ❑
I Check the Appropriate Item Tvne — Reauired for All Submissions I
U Professional Services Agreement U Contract
❑ Open Market Contract ❑ Amendment/Addendum
❑ Bid Opening ❑ Bid Award
❑ Quote Opening ❑ Quote Award
❑ Proposal Opening ❑ C/O & PCA No.
® Chg. Order, No. 5 ❑ Traffic Control
❑ Other: INDOT-LPA
Information
U Proposal
❑ Special Purchase, QPA
❑ Req. to Advertise ❑ Title Sheet
❑ Reject Bids/Quotes
❑ PCA
❑ Resolution
❑ Ease./Encroach
Company or Vendor Name
INDOT (Milestone Contractors performing work)
❑ Yes ❑ If Yes, Approved by Purchasing
New Vendor
® No
❑ MBE El Yes
MBE/WBE Contractor
Completed E-Verify Form Attached
❑ WBE ❑ No
Project Name
Coal Line Trail Phase IIB
Project Number
122-035 (INDOT DES #2200199)
Funding Source
PO-25244
Account No.
Amount
Terms of Contract
Purpose/Description
Change Order #5 to extend intermediate completion date. Final
completion date (5/l/2024) remains the same.
For Change Orders Only
Amount of ❑ Increase $
❑ Decrease ($ )
Previous Amount
$
Increase
Current Percent of Change:
Decrease
New Amount
$
Increase
Total Percent of Change:
Decrease
Time Extension Amount:
98 days
New Completion Date:
5/l/2024