HomeMy WebLinkAbout01092024 Board of Public Works MeetingAGENDA REVIEW SESSION JANUARY 4, 2024 1
The Agenda Review Session of the Board of Public Works was convened at 10:33 a.m. on
January 4, 2024, by Board President Elizabeth A. Maradik, Vice President Joseph Molnar, and
Board Members Gary Gilot, Murray Miller, Briana Micou, and Board Attorney Michael Schmidt
present. The Board of Public Works Clerk, Theresa Heffner, presented the Board with a
proposed agenda of items presented by the public and by City Staff.
Board members discussed the following item(s) from the agenda.
CHANGE ORDERS
Mr. Miller asked about the winter conditions that were added to the change order for item 3.A:
Fire Station No. 8 Replacement. Senior Engineer Zach Hurst explained that the winter conditions
were an omission on the designer's part. Given the schedule that they provided to use with work
starting in the fall and continuing through winter, winter conditions should have been present in
the bid documents. It was an oversight, and they were not included.
Mr. Gilot noted that the contractor should have reasonably assumed there would be winter
conditions based on the calendar days that went through winter months. Senior Engineer Hurst
stated that it is something that should have been addressed during the bid period, but it is also
something that needed to be in the contract and this change order adds it to the contract.
Mr. Miller asked about the gear washing in the change order. Senior Engineer Hurst noted that
the City is having R. Yoder Construction, inc. do some gear washer preparation installations at
three (3) fire stations, providing pumps, plumbing, and electrical hookups for new gear washers
to be installed at those locations.
Mr. Miller asked if it was being added to the contract. Senior Engineer Hurst answered yes
clarifying that this is something we previously tried to quote out with no success. It is similar to a
roadway project where some asphalt paving or something similar is done at a different location
than the street in question.
Mr. Miller asked about the error in the driveway thickness and the stone base. Senior Engineer
Hurst explained that the designer miscalculated the proper concrete depths to be able to handle
the fire apparatuses. He added that the stone base was also a designer error.
Mr. Miller asked if anything would be going back on the designer for those errors. Senior
Engineer Hurst advised that it is something that we are pondering right now, stating there are still
some invoices of theirs that have not been paid out yet based on their current performance.
Attorney Schmidt asked Senior Engineer Hurst if there are any additional scope changes to this
fire station on gear washing. Senior Engineer Hurst responded no.
Cynthia Simmons Officer of Diversity and Inclusion asked when the quote went out for the gear
washing and received no responses. Senior Engineer Hurst advised about a year and a half ago.
AGREEMENTS/CONTRACTS/PROPOSALS/ADDENDA
Mr. Gilot asked about the open market contract for item 6. E: Water Damage Repairs and
MarMain Apartments, noting it is a good size number and asked if it included mold remediation.
Senior Engineer Hurst advised that it is just dealing with the damaged drywall.
Mr. Gilot asked if there are nonresponsive quotes included. Senior Engineer Hurst noted that it is
all noted in the memo.
PROJECT COMPLETION AFFIDAVIT
Attorney Schmidt advised the Board of the MWBE goals for item 4. A.: MarMain Apartments
Roof Replacement. He advised that the goals were all met for this project.
AGREEMENTS/CONTRACTS/PROPOSALS/ADDENDA
Mr. Gilot asked about item 6.B: Utility Easement at Beacon Health System Memorial Hospital.
He noted that when we vacate a street, we vacate subject to utility easements. He asked why
there is an exclusive utility easement over and above what is in the normal statute.
REGULAR MEETING JANUARY 9, 2024 2
Senior Engineer Rebecca Plantz noted that this is Project Engineer Gemma Stanton’s project.
She explained that in the initial vacation it was overlooked so they have to do a double check at
the original documents to understand where the standard with each vacation that there is a utility
easement with it, they are saying that it was overlooked in this one, but perhaps it is not in that
document because they are outside of those limits working on the north side of the building.
There is a stretch between the north side of the building and the vacated Bartlett Street and if
there are any utilities in there, they could be extending that location too.
Senior Engineer Charlie Brach advised that if there are city utilities in a vacant right-of-way, we
are now requiring the recording of an actual easement because the language is very vague in the
vacation ordinance, and it does not actually record an easement on the plat.
Project Engineer Gemma Stanton confirmed that the vacation was approved by the Common
Council without waiting for the utility easements. She added they just recently realized the
process happened out of order and are now needing to get the easements in line even though the
right-of-way vacation was finalized before the easements were recorded.
AGREEMENTS/CONTRACTS/PROPOSALS/ADDENDA
Attorney Schmidt noted that item 6. A: is also part of the same project as 6. B.
Project Engineer Gemma Stanton explained that this is related to the same project. They are
wanting to install some temporary asphalt drives to do the construction of the Beacon tower and
when they do that, they will be destroying the curb and sidewalks and tree lawn as they drive
over it. This agreement holds them to replacing those streetscape elements and when they finish
the project, they will be restoring all those things and not leaving the asphalt drive approaches
that they will be using during construction.
PRIVILEGE OF THE FLOOR
ADJOURNMENT
There being no further business to come before the Board, President Maradik adjourned the
meeting at 10:46 a.m.
REGULAR MEETING JANUARY 9, 2024
The Regular Meeting of the Board of Public Works was convened at 9:30 a.m. on Tuesday,
January 9, 2024, by Board President Elizabeth A. Maradik in the 13th Floor Conference Room of
the County-City Building, 227 W. Jefferson Blvd., South Bend, Indiana. The meeting was also
streamed live to the public via Microsoft Teams. Board Clerk Theresa Heffner confirmed
the presence of Board President Elizabeth A. Maradik, Vice President Joseph Molnar, and
Board Members Gary Gilot, Murray Miller, Briana Micou, and Board Attorney Michael
Schmidt, with a roll call. President Maradik reminded virtual attendees to mute their
microphones and turn off
January 23, 2024
REGULAR MEETING JANUARY 9, 2024 3
their cameras when not speaking, and to save their questions and comments for the Privilege of
the Floor.
APPROVE MINUTES OF PREVIOUS MEETING
Upon a motion made by VP Molnar, seconded by Mr. Miller and carried by roll call, the minutes
for the Regular Meeting of the Board held on December 19, 2024, were approved.
AWARD BID AND APPROVE CONTRACT – 2023 GUARDRAIL & HANDRAIL
INSTALLATION & REPLACEMENT – PROJECT NO. 122-043R (PR-00022501)
Ms. Leslie Biek, Engineering, advised the Board that on December 12, 2023, bids were received
and opened for the above referenced project. After reviewing those bids, Ms. Biek recommended
that the Board award the contract to the lowest responsive and responsible bidder, LaPorte
Construction Co., Inc., in the amount of $334,670. Therefore, VP Molnar made a motion that the
recommendation be accepted, and the bid be awarded, and the contract approved as outlined
above. Mr. Miller seconded the motion, which carried by roll call.
AWARD BID AND APPROVE CONTRACT – CITY OF SB WAYFINDING SIGNAGE
PROGRAM, PHASE III – PROJECT NO. 123-013 (PR-00028908)
Ms. Leslie Biek, Engineering, advised the Board that on December 12, 2023, bids were received
and opened for the above referenced project. After reviewing those bids, Ms. Biek recommended
that the Board award the contract to the lowest responsive and responsible bidder, Geograph
Industries, Inc., in the amount of $186,035; Base Bid Plus Alternates 1 & 2. Therefore, VP
Molnar made a motion that the recommendation be accepted, and the bid be awarded, and the
contract approved as outlined above. Mr. Miller seconded the motion, which carried by roll call.
APPROVE CHANGE ORDER NO. 1 – FIRE STATION NO. 8 REPLACEMENT – PROJECT
NO. 122-034 (PO-0026318)
President Maradik advised that Mr. Zach Hurst, Engineering, has submitted change order
number 1 on behalf of R. Yoder Construction Co., Inc., indicating the contract amount be
increased by $76,757.37 for a new contract sum, including this change order, in the amount of
$3,780,607.37. Upon a motion made by VP Molnar, seconded by Mr. Gilot and carried by roll
call, the change order was approved. Mr. Miller voted no.
APPROVE PROJECT COMPLETION AFFIDAVIT – MARMAIN APARTMENTS ROOF
REPLACEMENT – PROJECT NO. 122-061 (PO-0021898)
President Maradik advised that Mr. Kyle Ludlow, Engineering, has submitted the project
completion affidavit on behalf of Slatile Roofing and Sheet Metal Co., Inc., for the above
referenced project, indicating a final cost of $484,062. Upon a motion made by VP Molnar,
seconded by Mr. Miller and carried by roll call, the project completion affidavit was approved.
ADOPT RESOLUTION NO. 01-2024 – A RESOLUTION OF THE CITY OF SOUTH BEND,
INDIANA BOARD OF PUBLIC WORKS FOR THE DISPOSAL OF SURPLUS PROPERTY
Upon a motion made by VP Molnar, seconded by Mr. Miller and carried by roll call, the
following resolution was adopted by the Board of Public Works:
RESOLUTION NO. 01-2024
A RESOLUTION OF THE CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS FOR THE
DISPOSAL OF SURPLUS PROPERTY
WHEREAS, I.C. 36-9-6-1 gives the Board of Public Works of the City of South Bend the
right and duty to have custody of, control of, use of, and dispose of in accordance with Indiana
statutes, all real and personal property owned by the City of South Bend; and
WHEREAS, the Common Council of the City of South Bend passed as amended on
January 11, 1988, Ordinance No. 7847-88 which mandates the Board of Public Works of the
City of South Bend to determine that the sidearm of a police officer who retires in go od standing
is surplus property and no longer useful to the City of South Bend; and
WHEREAS, PATROLMAN FIRST CLASS JAMES WOLFF retired effective
January 6th, 2024 from the South Bend Police Department after thirty-one (31) years of service,
and the Board of Public Safety of the City of South Bend has determined that he retired in good
standing; and
REGULAR MEETING JANUARY 9, 2024 4
WHEREAS, I.C. 5-22-22-1 permits and establishes procedure for disposal of personal
property which is no longer needed by the City and which is unfit for the purpose for which it
was intended;
NOW, THEREFORE, BE IT RESOLVED by the Board of Public Works of the City of
South Bend that handgun Serial No. NDT6962, a Smith and Wesson M&P Handgun, is no
longer needed by the City and is unfit for the purpose for which it was intended and has an
estimated fair market value of less than Five Hundred Dollars ($500.00).
BE IT FURTHER RESOLVED that said property be disposed of and removed from the
City inventory.
ADOPTED this 9th day of January 2024.
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
s/ Elizabeth A. Maradik
s/ Joseph R. Molnar
s/ Gary A. Gilot
s/ Murray L. Miller
s/ Brena N. Micou
ATTEST:
s/ Theresa Heffner, Clerk
APPROVAL OF AGREEMENTS/CONTRACTS/PROPOSALS/ADDENDA
The following agreements/contracts/proposals/addenda were submitted to the Board for
approval:
Type Business Description Amount/
Funding
Motion/
Second
Dedicated
Improvements
Agreement
Beacon Health
System
Memorial
Hospital
Install Temporary Asphalt
Drive Approaches at
Beacon Tower and
Replace Sidewalk, Curb,
and Landscaping when
Project is Finished
N/A VP Molnar /
Mr. Miller
Utility
Easement
Beacon Health
System
Memorial
Hospital
Exclusive Municipal
Storm Sewer, Sanitary
Sewer, and Water Main
Easement in Vacated
Bartlett St. Right-of-Way
N/A VP Molnar /
Mr. Miller
*Subject to final
legal approval
Real Property
Transfer
Agreement
Near Northwest
Neighborhood
Inc.
Transfer City Property at
912 and 914 Harrison for
Affordable Housing
N/A VP Molnar /
Mr. Miller
Local Public
Agency
Contract
Indiana
Department of
Transportation
Preliminary Engineering
Services for Coal Line
Trail, Phase III DES
#2201235 Project No.
123-007
$349,710;
INDOT to
Cover
$248,160
(PR-00029060)
VP Molnar /
Mr. Miller
Open Market
Contract
Herb’s Drywall
Service, Inc.
Water Damage Repairs at
MarMain Apartments
Project No. 122-061A
$16,680
(PR-00028875)
VP Molnar /
Mr. Miller
*Attorney Schmidt noted that this item would need additional legal review before final approval.
RATIFY APPROVAL AND/OR RELEASE CONTRACTOR, EXCAVATION, AND
OCCUPANCY BONDS
The Division of Engineering Permit Department recommended that the following bonds be
ratified pursuant to Resolution 100-2000 and/or released as follows:
Business Bond Type Approved/
Released Effective Date
Advanced Excavating LLC Excavation Released 02/08/2024
VP Molnar made a motion that the bond’s approval and/or release as outlined above be ratified.
Mr. Miller seconded the motion, which carried by roll call.
REGULAR MEETING JANUARY 9, 2024 5
RATIFY PREAPPROVED CLAIMS PAYMENTS
VP Molnar stated the Board received notices of the following preapproved claim payments from
the City’s Department of Administration and Finance:
Name Date Amount of Claim
City of South Bend Claims GBLN-69297 12/12/2023 $1,353,343.50
City of South Bend Claims GBLN-69800, GBLN-
69805, GBLN-70099
12/18/2023 $1,332,052.30
City of South Bend Claims GBLN-70010 12/19/2023 $2,726,916.19
City of South Bend Claims GBLN-70436, GBLN-
70452, GBLN-70458
12/29/2023 $2,387,366.98
City of South Bend Claims GBLN-70420 12/29/2023 $3,004,530.18
Each claim is fully supported by an invoice; the person receiving the goods or services has
approved the claims; and the claims have been filed with the City Fiscal Officer and certified for
accuracy. Therefore, upon a motion by VP Molnar, seconded by Mr. Miller, and carried by roll
call, the Board ratified the preapproved claims payments.
PRIVILEGE OF THE FLOOR
ADJOURNMENT
There being no further business to come before the Board, President Maradik adjourned the
meeting at 9:40 a.m.
January 23, 2024