BOARD OF PUBLIC WORKS
September 26, 2023
Mr. Jason Bennett
Green Demolition Contractors, Inc.
315 Brighton Street, Suite 1
LaPorte, IN 46350
jason@greendemolitioninc.com
RE: Change Order No. 1 – Monroe Circle Demolition – Project No. 123-048
Dear Mr. Bennett:
At its September 26, 2023 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $455,000, bringing the revised contract amount to
$1,306,600.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
Page 1 of 1
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Zach Hurst, PE, Sr. Project Engineer
SUBJECT: Change Order No. 1 - Project No. 123-048
Monroe Circle Demolition
DATE: 09/15/2023
During demolition of the existing townhomes at Monroe Circle, it was discovered that the
concrete foundation slabs were cast on top of transite pipe, which is an asbestos containing
material. The bid specifications noted that this was a possibility, but no removal quantity was
included, nor any contingency added to the contract.
The transite pipe acted as air ducts, traveling in all directions underneath the slab, and was also
cast monolithically with the foundation slab, meaning that separating the pipe from the slab was
not possible. To this end, the entire foundation slabs needed to be treated as hazardous
material and disposed of accordingly.
It was not possible to determine the extent of the transite pipe until the buildings were removed
and the foundation slabs uncovered. This was an unforeseen circumstance. The cost for
removal is $450,000: 90,000 cubic feet of foundation slab, removed at $5 per cubic foot.
The percentage change to the contract for unforeseen conditions is 52.8%. The added tree
removal, which is a $5,000 scope addition, is a 0.6% change to the contract.
September 26, 2023
City of South Bend Project No. 123-048 9/26/2023
Monroe Circle Demolition
Line Item Qty Unit Price Total
Remove Hazardous Foundation Slabs 1 LS $450,000.00 $450,000.00
Remove 3 Trees 1 LS $5,000.00 $5,000.00
CO Total =$455,000.00
Change Order #1
Notes
Unforeseen: Existing slabs contain conduit with asbestos; cannot be
separated. Entire slab needs to be treated as hazardous. 90,000 cubic
feet at $5 per cubic foot.
Scope: Existing trees in poor condition; require removal.
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 09/15/2023
Name Zach Hurst Department DPW
BPW Date 09/26/2023 Phone Extension 3057
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer Officer Name
BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 1 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Green Demolition Contractors
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Monroe Circle Demolition
Project Number 123-048
Funding Source River West DA TIF
Account No. PO-0024348
Amount Change: $455,000; Revised Amount: $1,306,600
Terms of Contract
Purpose/Description Change Order No. 1 addresses unforeseen asbestos removal and added tree
removal.
For Change Orders Only
Amount of Increase
Decrease
$ 455,000
($ )
Previous Amount $ 851,600
Current Percent of Change:
Increase
Decrease
53.43%
( %)
New Amount $ 1,306,600
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: