HomeMy WebLinkAboutChange Order No 3 - North Water Treatment Plant Improvements Proj No. 119-011 - Bowen Engineering Corp.1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/235-9251
FAx 574/235-9171
CITY OF SOUTH BEND TAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
August 22, 2023
Mr. Mitchell Stull
Bowen Engineering Corporation
8802 N. Meridian St.
Indianapolis, IN 46260
mstullkbowenen ing eering com
RE: Change Order No. 3 — North Water Treatment Plant Improvements
Project No. 119-011
Dear Mr. Stull:
At its August 22, 2023 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $5,687 with an additional one hundred eighty-one
(181) days, bringing the revised contract amount to $3,557,327 with a new completion date of
November 30, 2023.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
Is/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT ALEXANDRA DOLZ-LANE MURRAY L. MILLER
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Becca Plantz, Project Engineer
SUBJECT: Change Order 3 Project No. 119-011
DATE: August 11, 2023
This contract was originally awarded as an open market contract after being opened first on
November 9, 2021. The open market contract was awarded on April 26, 2022, and owner
direction was provided to wait until after the summer season to shut the plant down. Additional
field orders from the owner and research for discussions to finalize requests for information
support the reason for extending the substantial completion to October 31, 2023, or scope
complete to the point that the plant can come back on in this time. Field orders and RFIs
resulting in delay include replacing manways on each vessel per R-Stamp standards, applying
to be removed from the state registered list of vessels prior to repairs, and filter clarifications on
pre -conditioned media. The final completion is being set for November 30, 2023, to encompass
discharge water head pipe replacement.
The increase of this change order in the amount of $5,687 is a net total of field orders and
savings found in the allowances and unit price items. Increased costs are associated with the
need to replace the hatches on each vessel, the testing required for this level of replacement,
repair and replacement of the degrading discharge head in the upper level, and a support gravel
size change during media placement. The physical rehabilitation of the vessels is nearing
completion with less structural concerns encountered than prepared for, resulting in savings
identified in the allowances and unit prices designed for this scope.
Please call with your questions (5998).
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO.
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
08/10/2023
North Water Treatment Plant Improvements
4/26/2022
3
SUBJECT OF CHANGE ORDER: Extending the completion date for field orders and time for research to
finalize responses to requests for information. Includes unit price
savings and the addition of the discharge water head replacement.
The original contract sum $ 3,582,800.00
Net change by previously authorized change orders $ (31,160.00)
The contract sum prior to this change order $ 3,551,640.00
By this Change Order, the project amount is ® Increased
❑ Decreased $ 5,687.00
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
CONTRACTOR
Contractor Signature
Mitchell Stull, Sr. Project Engineer
Printed Name and Title
Bowen Engineering
Company name
8802 N. Meridian St
Address
3,557,327.00
0.16 %
1.07) %
Substantial: 8/ 15/22, Final 9/ 15/2022
260 days
181 days
Substantial: 10/31/23, Final 11/30/2023
RECOMMENDED FOR APPROVAL
I- "
PROJECT MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Date:
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
Elizabeth A. Maradik, President
Gary A. Gilot, Member
Indianapolis, IN, 46260
City, State, Zip
Murray L. Miller, Member
Joseph R. Molnar, Vice President
Alexandra Dolz-Lane, Member
4
Attest: Theresa M. Heffner, Clerk
Date: August 22, 2023
July 6, 2022
City of South Bend
Attn: Rebecca Plantz
227 West Jefferson Boulevard
South Bend, IN 46601-1830
BdWiEN
Engineering Corporation
CONTRACTORS • ENGINEERS
RE: South Bend North Treatment Plant Improvements
Bowen Project Number: 15 — 22 — 042
PCO-02 Filter Vessel Spring Assisted Manways, Revision 2
Rebecca:
Bowen Engineering (BEC) is pleased to submit this proposal for the Owner's review of the
associated additional work.
Scope:
- Remove and replace ten (10) spring assisted manways on the five (5) filter vessels (two (2) per
vessel) of the North Station for the lump sum cost listed below.
- Revision No. 2 includes cost for 3rd party NDE Testing
Lump Sum Cost:
Clarifications:
- BEC Cost
o Labor & Equipment : $ 72,957.00
o Material $ 69,676.07
o Mark -Up $ 21,255.93
- Lump Sum Cost $ 163,889.00
- Existing hatches will be replaced in kind. (See attached marked -up catalog for
reference)
- Repairs will conform to the current edition of the National Board Inspection
Code (NBIC) and the American Society of Mechanical Engineers (ASME) Boiler
and Pressure Vessel Code (BPVC).
- Bowen Engineering/Locke AMI are authorized to complete R-stamp repairs.
- Manways will be cut at the existing tank nozzle / manway hub connection weld.
New manways will be welded at the same existing tank nozzle. (See attached
marked up drawing for reference)
- This proposal assumes no repairs or alterations to the tank shell will be required.
- No pressure testing has been included other than an in-service test.
- One mobilization has been included. Additional mobilization if required will
incur additional costs.
- No overtime has been included.
- Additional contract time will be required. A revised substantial completion date
will be mutually agreed to.
CONTRAETOR OF CHOICE
8802 North Meridian St. • Indianapolis, IN 46260
AYfY�
317.842.2616 phone • 317.841.4257 fax • BowenEngineering.com PAGE 1OF2
HdWEN
Engineering Corporation
CONTRACTORS • ENGINEERS
Please review, and if you have any questions, please do not hesitate to contact me.
Sincerely,
Mitchell Stull
Senior Project Engineer
Mobile: 317-650-8313 1 Email: mstull@bowenengineering.com
CC: Bradley VanOosterum — City of South Bend, Mark Rackow — Black & Veatch, Pat Stanford — BEC,
Tony Abitua — BEC, Margaret Burroughs — BEC
CONTRACTOR OF CHOICE
8802 North Meridian St. • Indianapolis, IN 46260 • 317.842.2616 phone • 317.841.4257 fax • www.BowenEngineering.com
PAGE 2OF2
August 9, 2023
City of South Bend
Attn: Rebecca Plantz
227 West Jefferson Boulevard
South Bend, IN 46601-1830
EldwiEN
• Engineering Corporation
CONTRACTORS • ENGINEERS
RE: South Bend North Treatment Plant Improvements
Bowen Project Number: 15 — 22 — 042
PCO-03 Pine Repair + Vessel #3 thru #5 FW Header Replacement — Revised Price No. 3
Rebecca:
Bowen Engineering (BEC) is pleased to submit this proposal for the Owner's review and approval for the
additional scope of work of replacing a portion of the 30" stainless steel fabricated pipe on the common
finish water header at the North Station.
Lump Sum Cost: $ 192,753.00
Scope:
- Remove existing stainless steel fabricated 30" 90' Bend, 30" x 18" reducing tee, and 30" x 24"
reducer and replace in kind with new and an additional 24" flange.
- Add 24" stub end and flange on existing pipe.
- Remove existing 30" and 18" stub ends and replace with new. Cut and prep pipe as required.
- Heli arc all welds, argon purge.
- Material of construction
0
1 EA
— 30" 316L stainless steel SCH 10 fabricated 30" 90° Bend, 30" x 18" reducing tee,
and 30" x 24" reducer.
0
1 EA
— 30" 316L stainless steel SCH 10 Type A stub end
0
1 EA
— 24" 316L stainless steel SCH 10 Type A stub end
0
1 EA
— 18" 316L stainless steel SCH 10 Type A stub end
0
1 EA
— 30" 150# galvanized back up flange.
0
1 EA
— 24" 150# galvanized back up flange.
0
1 EA
— 18" 150# galvanized back up flange.
0
1 EA
— 30" bolt back with gasket
0
1 EA
— 24" bolt back with gasket
0
1 EA
— 18" bolt back with gasket
Optional Credit-01
As an optional deduct, if the replacement of the 30" and 18" stub end is eliminated from the
scope of work, the credit value for this scope reduction would be $30,839.00 (Adjusted proposal
value with credit considered would be $161,914.00).
Attached is a one -line sketch of the proposed piping replacement associated with this proposal.
CONTRACTOR OF CHOICE
8802 North Meridian St. • Indianapolis, IN 46260
317.842.2616 phone • 317.841.4257 fax • BowenEngineering.com PAGE 1 OF 2
BOWEN
Engineering Corporation
CONTRACTORS • ENGINEERS
Clarifications:
- No pressure testing has been included other than an in-service test.
- No weld inspection / NDE Testing has been included.
- One mobilization has been included. Additional mobilization if required will incur additional costs.
- No overtime / premium time has been included.
- Pipeline can be isolated for the duration required to complete the scope of work.
- Plant personnel will be responsible for isolation of areas as required to complete the scope of work.
- Zimmerman is a trusted contractor of the City of South Bend. Therefore, to reduce the cost of the
proposal, BEC has eliminated supervision cost to oversee Zimmerman and will not be onsite.
- Additional contract time will be required. A revised substantial completion date will be mutually
agreed to.
Thank you for the opportunity,
Mitchell Stull, Senior Project Engineer
Mobile: 317-650-8313 1 Email: mstull@bowenengineering.com
CONTRACTOR OF CHOICE
8802 North Meridian St. • Indianapolis, IN 46260 • 317.842.2616 phone • 317.841.4257 fax • www.BowenEngineering.com
PAGE 2 OF 2
July 6, 2023
City of South Bend
Attn: Rebecca Plantz
227 West Jefferson Boulevard
South Bend, IN 46601-1830
BdWiEN
Engineering Corporation
C CONTRACTORS • ENGINEERS
RE: South Bend North Treatment Plant Improvements
Bowen Project Number: 15 — 22 — 042
PCO-06 Unused Allowance + Unit Price Budeet
Rebecca:
Please see the attached breakdown of the unused allowance and unit price budgets dollars that will
be coming back to the City of South Bend.
Total PCO Lump Sum Credit: $357,428.00
Please review, and if you have any questions, do not hesitate to contact me.
Sincerely,
Mitchell Stull
Senior Project Engineer
Mobile: 317-650-8313
Email: mstull@bowenengineering.com
EQNTRAETDR ❑F CHOICE I
01F
8802 North Meridian St. • Indianapolis, IN 46260
317.842.2616 phone • 317.841.4257 fax • Bowen Engineering.com PAGE 1 OF 1
119-011, (15-22-042) South Bend North Filter Project — PCO-06 Unused Allowance + Unit Price Budget
1 OF 1
Combined Filter Allowances
Unit Price Weld Work Total
Internal Components (Hungerford & Terry Material Cost)
Internal Components (Bowen Labor Complete)
Gravel Retaining Screen Angle Refurbishment
Plug Welds
Stud and Clip Repairs
Pipe Hanger / Manway Weld Outs
$ 500,000.00
$ 369,500.00
Notes
7/6/2023
$ (305,870.00)
Billed under Lump Sum tab. Allowances adjusted and billed out per each
filter
$ (54,970.00)
Billed under Lump Sum tab. Allowances adjusted and billed out per each
filter
$ (10,000.00)
Billed under Lump Sum tab. Allowances adjusted and billed out per each
filter
$ (51,985.00)
Billed under Unit Price tab of the Pay Application per each filter
$ (83,135.00)
Billed under ASI-2 under the Unit Price Tab of the Pay Application
$ (6,112.00)
Billed under ASI-3 under the Unit Price Tab of the Pay Application
PCO-06 Unused Allowance + Unit Price Budget $ 357,428.00
June 27, 2023
City of South Bend
Attn: Rebecca Plantz
227 West Jefferson Boulevard
South Bend, IN 46601-1830
BdWiEN
Engineering Corporation
CONTRACTORS • ENGINEERS
RE: South Bend North Treatment Plant Improvements
Bowen Project Number: 15 — 22 — 042
PCO-07 Red Flint Option #3— Suaaort Gravel
Rebecca:
Bowen Engineering (BEC) is submitting this proposal for alternate 5th layer support gravel. After
review by the City of South Bend and Black & Veatch, Bowen was released to order the material.
Different pricing and material options were provided during the selection process of the alternate
5th layer material. Option #3, supplied by the manufacturer Red Flit, was selected on 06/13/2023 via
email.
Lump Sum: $6,473.00
Please review, and if you have any questions, please do not hesitate to contact me.
Sincerely,
Mitchell Stull
Senior Project Engineer
Mobile: 317-650-8313 1 Email: mstull@bowenengineering.com
CQNTR,4CTOR OF CHOICE ""`w
8802 North Meridian St. • Indianapolis, IN 46260
AYfA�
317.842.2616 phone • 317.841.4257 fax • BowenEngineering.com PAGE 1 OF 1
City of South Bend
Department of Administration & Finance
Change Order Request Form
Changing the line amount:
You can only change a line amount if it has NOT been invoiced against.
• If the line has NOT been invoiced — reduce the line amount to equal what it should be.
• If the line has been invoiced — cancel the delivery remainder and finalize the individual line, then add a new line for the
amount that should be remaining.
Multiple PO lines:
If you have changes to more than two lines on the same PO, fill out a separate section for each line affected by the change
order.
Project POs:
For change orders on project -related POs, this form must be approved by the Project Accounting Team as described in
Supplement 508.
PO Number
PO-0016353
Line Number
5
Original Dollar Amount
$0.00
New Dollar Amount
For liquidation request, enter $0
$5,687.00
Reason Code if changed)
na
Financial Dimensions (fund-dept-
division -subdivision -main account
622-06-604-620-442005
Project Code if applicable)
PROJ-56
Description of change (include
budget impact)
Decrease in the contract as a net total of field orders and savings under the
allowances and unit prices.
APPROVED BY PROJECT
ACCOUNTING TEAM (if applicable)
Ron O'Connor 08-14-2023
PO Number
Line Number
Original Dollar Amount
New Dollar Amount
For liquidation request, enter $0
Reason Code if changed)
Financial Dimensions (fund-dept-
division-subdivision-main account
Project Code if applicable)
Description of change (include
budget impact)
APPROVED BY PROJECT
ACCOUNTING TEAM (if applicable)
PO Number
Line Number
Original Dollar Amount
2023 08 August 14 PO-16353 Bowne Engineering PO Change Order Request Form - Increase Line #5 - RP 1 of 3
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 08/11 /2023
Name Becca Plantz Department Public Works
BPW Date 08/22/2023 Phone Extension 5998
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer ❑ Officer Name
BPW Attorney ❑ Attorney Name
Dept. Attorney ❑ Attorney Name
Purchasing ❑
Michael Schmidt
Check the Appropriate Item Type — Required. for All Submissions
❑ Professional Services Agreement ❑ Contract ❑ Proposal
❑ Open Market Contract ❑ Amendment/Addendum ❑ Special Purchase, QPA
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award ❑ Reject Bids/Quotes
❑ Proposal Opening ❑ C/O & PCA No. ❑ PCA
® Chg. Order, No. 3 ❑ Traffic Control ❑ Resolution
n Other: n Ease./Encroach
Information
Company or Vendor Name
Bowen Engineering Corporation
❑ Yes❑ If Yes, Approved by Purchasing
New Vendor
❑ No
❑
MBE/WBE Contractor
Completed E-Verify Form Attached
❑ WBE
❑ Nos
Project Name
North Water Treatment Plant Improvements
Project Number
119-011
Funding Source
River West TIF & Water Works Capital
Account No.
PO-16353
Amount
Terms of Contract
Purpose/Description
Extending the completion date in the contract to encompass
field orders and
time for research and discussions to finalize responses to requests for
information. Decreasing the contract amount according
to net savings.
For Change Orders Only
Amount of ®
Increase $5,687.00
❑
Decrease $
Previous Amount
$ 3,551,640.00
Current Percent of Change
New Amount
Total Percent of Change:
Time Extension Amount
New Completion Date:
Increase
Decrease
$ 3,557,327.00
Increase
Decrease
181 Days
Substantial: 10/3
%0.16
(1.07%)
)23. Final: 11/30/2023