HomeMy WebLinkAboutChange Order No 2 - MPAC Carpet Replacement Project No. 121-029 - Carpet Service Outlet1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/235-9251
FAx 574/235-9171
CITY OF SOUTH BEND TAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
August 8, 2023
Ms. Vicki Shepard
Carpet Service Outlet, Inc.
1514 Mishawaka Ave.
South Bend, IN 46615
cgMetservice04kyahoo.com
RE: Change Order No. 2 — Morris Performing Arts Center Carpet Replacement
Project No. 121-029B
Dear Ms. Shepard:
At its August 8, 2023 meeting, the Board of Public Works approved the above referenced
Change Order be increased by $19,040 with an additional two hundred eighty (280) days,
bringing the revised contract amount to $216,774.50 with a new completion date of August 4,
2023.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
Is/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT ALEXANDRA DOLZ-LANE MURRAY L. MILLER
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Rebecca Plantz, Project Engineer
SUBJECT: Change Order 2, Project No. 121-029B
Morris Performing Arts Center Carpet Replacement
DATE: July 27, 2023
Change Order 2 to the Morris Performing Arts Center Carpet Replacement is to increase the
contract amount by $19,040.00. This increase is to cover increased labor for patching concrete
in the upper level that came loose during carpet removal, carpeting the trough lids as a design
change after the carpet was already awarded, removing a double layer of glue in the sound
booth, and additional cleaning around shows. Increased material costs are also included to
cover the patch material and tap downs at exposed edges not originally called out for edging.
This final change order will bring the total increase to the contract to 25.3% due to unforeseen
conditions attributed to the manufacturing delays and surface conditions under the existing
carpet.
The additional days and cleaning around shows were a result of manufacturing delays that
pushed the carpet installation out beyond the window of when the Morris Theater was not
scheduled for two months. The carpet crew had to bring in material and have it back out within
the same week for several months in order to finish the carpet around shows. This will be the
final change order as the project is in its punch list phase.
Please call with your questions (5998).
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO.
SUBJECT OF CHANGE ORDER:
07/13/2023
121-029B
Morris Performing Arts Center Carpet Replacement
05/24/2022
2
Inv #8527 — Increased labor for patching, carpeting trough lids,
double layer of glue in sound booth and cleaning around
shows. Increase material cost for additional tap downs at
exposed edges and concrete patch for upper level.
See attached Comparison of Estimate for overruns and underruns.
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
CONT CTOR
Contractor Si atur
Vicki Shepard
Printed Name and Title
Carpet Service Outlet Inc.
Company name
1514 Mishawaka Ave
Address
South Bend, IN, 46615
City, State, Zip
® Increased
❑ Decreased
$ 173,000.00
$ 24,734.50
$ 197,734.50
$ 19,040,00
$ $216,774.50
11 %
2'5.3 %
September 28, 2022
30 days
280 days
August 4, 2023
RECOMMENDED FOR APPROVAL
d4i, �- "
PROJECT MANAGER
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
Elizabeth A. Maradik, President
�_
Gary A. Gilot, Member
Murray L. Miller, Member
I-0
Joseph R. Molnar, Vice President
Alexandra Dolz-Lane, Member
Attest: Theresa M. Heffner, Clerk
Date: August 8, 2023
Carpet Service Outlet Inc.
Invoice
1514 Mishawaka Ave.
South Bend, In 46615
(574)-287-7148
Bill To
Morris Performing Arts Center
Ship To
CIO
Date
Invoice #
5/8/2023
8527
P.O. No.
Terms
Due Date
Rep
Order Date
Installer
Phone #
5/8/2023
5/8/2023
Style
Description
Qty
Rate
Amount
LABOR
Cover Metal Plates
1,800.00
1,800.00
LABOR
Install Reducer Cap Upper Aisles Inc. Material
1,700.00
1,700.00
LABOR
Move Railings,Balcany Seats, Furniture and Replace
3,600.00
3,600.00
IvMisc
Ardex Feather Finish Patch/ Material
58
30,00
1,740.00
LABOR
Main Lobby and Sound Booth Removal / Double Glue
1,200.00
1,200.00
Pad Addtional Removal Labor
LABOR
Patch all areas as needed 260 total man hours
260
30.00
7,800.00
LABOR
Addtional Cleanup
1,200.00
1,200.00
`Perms: We Require 50% Down Upon Order & Balance Upon Completion / One Year Labor
Warranty
Sales Tax (0.0%) $000
Total $19.040.00
Phone # Fax #
574-287-7148 574-287-7184
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 07/21 /2023
Name Becca Plantz Department Public Works
BPW Date 08/08/2023 Phone Extension 5998
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer ❑ Officer Name Cynthia Simmons
BPW Attorney
❑ Attorney Name
Dept. Attorney ❑ Attorney Name
Purchasing ❑
Michael Schmidt
Check the Appropriate
Item Type — Required. for All Submissions
❑ Professional Services Agreement
❑ Contract
❑ Proposal
❑ Open Market Contract
❑ Amendment/Addendum
❑ Special Purchase, QPA
❑ Bid Opening
❑ Bid Award
❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening
❑ Quote Award
❑ Reject Bids/Quotes
❑ Proposal Opening
❑ C/O & PCA No.
❑ PCA
® Chg. Order, No. 2
❑ Traffic Control
❑ Resolution
n Other:
n Ease./Encroach
Company or Vendor Name
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Amount of
Previous Amount
Information
Service Outlet, Inc.
LJ YesU If Yes, Approved by Purchasing
❑ No
❑❑ WBE Completed E-Verify Form Attached ❑❑ Nos
Morris Performing Arts Center Carpet Replacement
121-029B
Morris Ca
PO-16843
Lump Sum
Increased labor and material through change order 2 for unforeseen conditions
or out of scope needs when carpeting the Morris Performing Arts Center.
® Increase $ 19,040.00
❑ Decrease ($ )
$ 197,734.50
Increase
Current Percent of Change: Decrease
New Amount $ 216,774.50
11%
Increase 25.3%
Total Percent of Change: Decrease ( %)
Time Extension Amount: 280 days
New Completion Date: August 4, 2023