CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
June 27, 2023
Mr. Robert Kuhns
Selge Construction Co., Inc.
2833 South 11TH St.
Niles, MI 49120
aswinehart@selgeconstruction.com
RE: Change Order No. 8 – Coal Line Trail, Phase I – (DES#1401810)
Project No. 115-063
Dear Mr. Kuhns:
At its June 27, 2023 meeting, the Board of Public Works approved the above referenced
Change Orders to be increased by four hundred & ten (410) days, with a new completion date of
September 29, 2022.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
Contract No:R -38064 Change Order No.: 008
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: R -38064 Letting Date:03/10/2021
District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Dietz, Don Status:Draft
Change Order Information Change Order No.: 008 EWA: N or Force Acct: N
Date Generated: 00/00/0000 Date Approved: 00/00/0000
Reason Code: CHANGED COND, Environmental Related
Description: Time Extension
Original Contract Amount $ 1,623,701.34
Current Change Order Amount $ 0.00 Percent: 0.000 %
Total Previous Approved Changes $ 247,561.45 Percent: 15.247 %
Total Change To-Date $ 247,561.45 Percent: 15.247 %
Modified Contract Amount $ 1,871,262.79
Time Extension Information
Date Initiated 00/00/0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 08/15/2021 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description: This contract was let on March 10, 2021 and the Notice to Proceed was issued on April
7, 2021. This did not allow the contractor time to clear the trees on the project prior to April 1, 2021in order to
comply with the bat nesting requirements. The work began on May 11, 2011 and the trees were realized in early
June. At that time the mitigation process was deemed to be impractical as there well over 10 trees larger than 4
inches in diameter and there was a good change the process would run past October 1, 2021. The contractor
determined that there was enough work that could be done prior the trees needing to be cleared if they started on
August 7, 2021. This would allow them to work up to October 1,2021 and then clear tress and proceed with the
project. It was also determined that with a Rule 5 Permit in place that project should be extended until May 1, 2022
to have time to establish trees and vegetation for the Notice of Termination. This change order is to extend the
contract completion date to September 29, 2022. No extra costs are added to this change order.
Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00
Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______
SS Days____________ SP Days Value $ _______________
Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
Contract No:R -38064 Change Order No.: 008
INDIANA Department of Transportation Page: 2
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______*
($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- )
(Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days)
Verbal Approval Required? Y / N If Y, by_____________ Date Issued___________
Total Change To-Date>5%? Y / N If Y , Copy to Program Budget Manager_________________
Scope/Design Recommendation
Required?
Y / N If Y, Referred to Project Manager(PM) __________________
Date to PM__________ Date Returned___________
Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________
If N,Resolution: Approved __________ Disapproved ___________
Resolved by_________________________ Date__________
LPA Signatures Required? Y / N If Y, Date to LPA _____________ Date Returned _________
FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer _________________________ Date _____________
Comments: ____________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
Contract No:R -38064 INDIANA Date:06/14/2023
Change Order No:008 Department of Transportation Page: 3
Contract:R -38064
Project:State:140181000LC4
Change Order Nbr: 008
Change Order Description: Time Extension
Reason Code:CHANGED COND, Environmental Related
CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change
Total Value for Change Order 008 = $ 0.00
Contract Completion Date Time Adjustment
Original Completion dt: 08/15/2021 Adj compl dt 09/29/2022 Adj No. of Days 410
Explanation: This contract was let on March 10, 2021 and the Notice to Proceed was issued on April 7, 2021. This did not allow the contractor
time to clear the trees on the project prior to April 1, 2021in order to comply with the bat nesting requirements. The work began on May 11, 2011
and the trees were realized in early June. At that time the mitigation process was deemed to be impractical as there well over 10 trees larger than
4 inches in diameter and there was a good change the process would run past October 1, 2021. The contractor determined that there was
enough work that could be done prior the trees needing to be cleared if they started on August 7, 2021. This would allow them to work up to
October 1,2021 and then clear tress and proceed with the project. It was also determined that with a Rule 5 Permit in place that project should be
extended until May 1, 2022 to have time to establish trees and vegetation for the Notice of Termination. This change order is to extend the
contract completion date to September 29, 2022. No extra costs are added to this change order.
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
Additional time is being added to the contract due to a delay in the manufacturing of the ornamental rail and the chain link fence. Materials were
ordered. No costs are added to this contract. See Time Adjustments for explanations.
Change Order Explanation for Specific Line Item
****************************************************************************************************************************
It is the intent of the parties that this change order is full and complete compensation for the work describe above.
Notification and consent to this change order is hereby acknowledged.
Contractor:____________________________________________Signed By:_____________________________________________
Date:__________________________________________________
***************************************************************************************************************************
NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system.
Contract No:R -38064 INDIANA Date:06/14/2023
Change Order No:008 Department of Transportation Page: 4
****************************************************************************************************************************
APPROVED FOR LOCAL PUBLIC AGENCY
SUBMITTED FOR CONSIDERATION
PE/S _________________________
****************************************************************************************************************************
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Approval Level Name of Approver Date Status
Don Dietz
June 27, 2023
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 6/22/23 Department Public Works
Name Rebecca Maenhout Division/Bureau Engineering
BPW Date 06/27/2023 Phone Extension 5996
Required Prior to Submittal to Board
Legal Attorney Name: Michael Schmidt
Controller Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing Michael Schmidt
Check the Appropriate Item Type – Required for All Submissions
Agreement Amendment Contract Proposal Addendum
Professional Services Resolution
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award
Change Order No. C/O & PCA No. PCA
Ease/Encroach. Traffic Control:
Other:
Required Information
Company or Vendor Name INDOT R-38064
New Vendor
Yes No If Yes, Approved by
Purchasing
MBE/WBE Contractor MBE WBE
MBE/WBE Contractor Requested No Yes Name of Company
Project Name R-38064 Coal Line Trail Phase I
Project Number 115-063
Funding Source PR specific to this change order was created 04/25/2023
Account No. PROJ00000018
Amount 0.00
Terms of Contract
Purpose/Description
Change Order 8 covers time extension 410 days to complete Project. Original
Completion date of 08/15/2021 to 09/29/2022
Required Contractor’s Certification Forms Attached (Non-
Collusion, Non-Discrimination, Non-Debarment, E-Verify, Iran, etc.)
Required For Change Orders Only
Amount of Increase
Decrease $
Previous Amount $ 1,871,262.79
Current Percent of Change: 0.00
New Amount $ 1,871,262.79
Total Percent of Change: 15.247%
Dispersal After Approval
Copy Original
8X
X 410 Days