CSO 045 and WWTP Improvements
Preliminary Engineering Report Public Hearing
May 23, 2023
Public Hearing General Information:
• There is a meeting attendance sheet. All present should sign -in so that we can include the
information in the final document
• There is also a speaker sheet. If anyone desires to speak, it will be appreciated if you will sign -in
on the speaker sheet so that we will have that information.
■ The Preliminary Engineering Report is available for review at the office of the South Bend Public
Works at 227 West Jefferson Blvd. Suite 1300 N South Bend, Indiana from May 12, 2023 through
May 22, 2023.
• This meeting may be recorded. Minutes of this meeting will be made a part of the final
Preliminary Engineering Report submittal to the Indiana Finance Authority.
o There is a written comment or question form attached to this handout. Please feel free to use
this. All written questions or comments with contact information included will receive a written
response. Written comments are preferred so that answers can be documented and made a
part of the final document.
• If responses to questions can be readily answered by the engineer or staff today, we will provide
answers. If the response will require a more detailed effort or research, the response may be
deferred to a written response provided to the speaker. In either case, an answer will be
provided to all questions.
i Please feel free to ask questions or provide comments. The City of South Bend respects public
input regarding this effort.
Project Need and General Summary:
This Preliminary Engineering Report (PER) is for engineering design, bidding, construction, and start-up
for the City of South Bend's Combined Sewer Overflow (CSO) System CSO 045 2.0 MG Equalization Basin
and for improvements to the current Wastewater Treatment Plant (WWTP).
The City of South Bend, Indiana is currently under a 2021 Consent Decree with the United States EPA, US
Department of Justice, and the State of Indiana Department of Environmental Management. The
purpose of the Consent Decree is to require the City of South Bend to comply with the Clean Water Act
as it relates to combined sewer discharges to the ground or to Waters of the United States. As part of the
Consent Decree, the City of South Bend completed a Long Term Control Plan (LTCP) for addressing these
issues. The Consent Decree establishes a specific timeline for compliance and establishes a schedule for
initiating and completing each project in the plan.
The two projects discussed in this report, the WWTP CSO 045 Equalization Basin Project and the WWTP
Hydraulic Improvements Project, are part of the work required for the purpose of reducing the volume
and/or frequency of CSO events from the City's collection system and increasing the capacity of the
WWTR This project involves the first of four CSO tanks installed as part of the Long Term Control Plan.
4) Allows for beneficial reuse of land above the basin
Once the initial configuration, elevation, materials, and construction were selected from the
alternatives, the City of South Bend requested a review of the cost differential of installing a
larger tank on site to make the best use of the available land. The updated design will now include
a 3.0 million gallon equalization basin.
Schedule:
PER Submittal to IDEM................ ..................................... ................................................ April, 2023
SRF Approval of PER............................................................................................................ July, 2023
Submit Plans and Specs to IDEM.........................................................................................
August, 2023
IDEM Issue Construction Permit..............................................................................
October, 2023
Advertise for Bids for Construction.............................................................................. October, 2023
Construction Bid Opening........................................................................................
November, 2023
Contract Award Approval..........................................................................................
December, 2023
Close on Loan................................................................................ .....
..........................
January, 2024
Commence Construction............................................................................................
February, 2024
Substantial Completion.......................................................................................................
July, 2025
Final Completion..........................................................................................................
October, 2025
Initiation of Operation..............................................................................................
December, 2025
Questions/Comments:
A question/comment sheet is attached following this page for formal written questions.
Questions/Comments may be submitted at this public hearing or anytime through May 281h 2023. If
questions or comments are provided after this meeting, please forward to:
Kieran Fahey
Director of Long Term Control Plan
Department of Public Works
3113 Riverside Drive,
South Bend, IN 46628
(574) 235-5993
kfahey@southbendin.gov
Written responses will be provide for all questions and will be included in the final submittal.
Circular
or EQB (2 MG)
_ r p
Legend
0. Proposed Sewer
■ Proposed Manhole
• Combined Wastewater
■ Sanitary
40- Gravity Mein
Circular EQ Basin
s i
�) 51 100 200
Feel
Proposed
Discharge
to WWTP
Proposed Diversion
Structure with
Electrically -actuated
�A,;Z11 Sluice Gate(s)
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 5/16/2023
Department Public
Name Kieran Fahey Works
BPW Date 5/23/2021 Phone Extension 5993
Review and Approval Required Prior to Submittal to Board
Diversity Compliance ❑
Officer Name
and Inclusion Officer
BPW Attorney
❑ Attorney Name
Dept. Attorney ❑ Attorney Name
Purchasing ❑
Check the Appropriate Item I
Professional Services Agreement ❑ Contract
❑ Open Market Contract
❑ Bid Opening
❑ Quote Opening
❑ Proposal Opening
❑ Chg. Order, No.
® Other: Preliminary
engineering report Public
M Schmidt
M Schmidt
❑ Amendment/Addendum
❑ Bid Award
❑ Quote Award
❑ C/O & PCA No.
❑ Traffic Control
Information
All Submissions
U Proposal
❑ Special Purchase, QPA
❑ Req. to Advertise ❑ Title Sheet
❑ Reject Bids/Quotes
❑ PCA
❑ Resolution
❑ Ease./Encroach
Company or Vendor Name
Indiana Finance Authority/American Structurepoint/The Public
❑ Yes❑ If Yes, Approved by Purchasing
New Vendor
® No
❑
MBE
MBE/WBE Contractor
Completed E-Verify Form Attached ❑ Nos
❑
Project Name
WWTP CSO tank
Project Number
121-071
Funding Source
No dollars
Account No.
NA
Amount
NA
Terms of Contract
To hold a public meeting at the 5/23/2023 BPWs for public/interested
parties regarding the WWTP CSO tank funding request to Indiana
Finance Authority
Purpose/Description
As above
For Change Orders Only
Amount of ❑ Increase $
❑ Decrease ($ )
Previous Amount
Current Percent of Change
New Amount
Total Percent of Change:
Increase %
Decrease ( %
Increase %
LEGAL NOTICE * South Bend Tribune * PUBLIC HEARING MAY 23, 2023
Notice of Public Hearing
City of South Bend, Indiana
Wastewater Preliminary Engineering Report (PER)
The City of South Bend (IN) Wastewater Utility, acting through the City of South Bend Board of Public
Works will hold a public hearing, at its regular meeting, at 9:30 AM on May 23, 2023, at the Board of
Public Works on the 131h floor, 227 W. Jefferson Blvd., South Bend, IN 46601.
The City of South Bend's engineering consultant, American Structurepoint, will present the
recommended project, which will include capacity upgrades to the wastewater treatment plant and
other associated improvements to comply with the terms of a regulatory agency consent decree.
The project will be funded through a Wastewater State Revolving Fund (WWSRF) loan.
Copies of the required Preliminary Engineering Report (PER) are available for public viewing starting on
May 12, 2023 through May 22, 2023 at the office of the South Bend's Department of Public Works, 227
W. Jefferson Blvd., Suite 1300 South Bend, IN 46601.
There will be the opportunity for questions and comments from the public at this meeting. Written
comments from the public will be accepted through May 31, 2023. Your participation is welcomed and
encouraged. If you will require special assistance at the meeting, please contact Kieran Fahey (574) 235-
5993 or by email at kfahey@south bend in.gov
Written comments regarding this project should be sent to Kieran Fahey at South Bend Department of
Public Works, 227 W. Jefferson Blvd., South Bend, IN 46601.