HomeMy WebLinkAboutPCA - Grandview Ave & RR Qwick Kurb Installation Proj No. 117-114 - Selge Construction Co., Inc.1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/235-9251
FAx 574/235-9171
CITY OF SOUTH BEND TAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
April 25, 2023
Mr. Robert Kuhns
Selge Construction Co., Inc.
2833 South I ITH St.
Niles, MI 49120
aswinehart&selgeconstruction. com
RE: Project Completion Affidavit — Grandview Ave. & RR Qwick Kurb Installation
Project No. 117-114
Dear Mr. Kuhns:
At its April 25, 2023 meeting, the Board of Public Works approved the Project
Completion Affidavit for this project in the amount of $17,785.
A copy of the Project Completion Affidavit is enclosed for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Hefner
Theresa Heffner, Clerk
Enclosures
TH/lh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
PROJECT COMPLETION AFFIDAVIT -.--
PROJECT NAME Grandview Ave and RR Qwick Kurb Installation
PROJECT NO 117-114 FINAL COST $17.785.00
CONTRACT SIGNED December 13, 2022 MAINTENANCE AGREEMENT ENDS
PROJECT DESCRIPTION -Install Qwick Kurb, provided by the City, on Grandview Ave at the railroad Mdi
WITNESSETH: crossing.
The work under the above contract between the City of South Bend and the undersigned contractor having been completed,
the City of South Bend, its officials and agents are hereby released from all claims and demands whatsoever arising under or
by such contract, and that the contractor performed the work within the scope of the Specifications and Standards of the City
of South Bend which were a part of the above Contract.
Execu d this 7th d y f April gft 2023
Signature
Justin Butler, Vice President
Printed Name
Selge Construction Co., Inc.
Company Name
2833 South 11 th Street
Company Address
Niles, MI 49120
City, State, Zip
WITNESSESS:
Before me, the undersigned Notary Public in and for said country and state, personally appeared
Justin Butler , and acknowledged his/her signature to the above Project Completion Affidavit on
the 7th dl_of April it Rak 0023.
� s y
~ otary Signature VMy Commission Expires 10/27/2027
Allison Swinehart
Printed Name
County of Residence
Berrien
If the Contractor is a corporation, the following certificate will be executed.
I, Allison Swinehart certify that I am Secretary of the Corporation executing
Justln Butler who signed this release on behalf of the contract
Vice President of said Corporation; that said release was duly signed for ar
jC pore#ion by Auth". of its governin body, and is within the scope of corporate powers:
Secretary's Signature
Allison Swinehart
Printed Name
`y��Ca� [•4 J V'pl���� r�i
a
COuNl YRELIC`• y
its lel"eA-g
was themb'B127� 2U7
be or 1p
Id
Corporate Seal
DEPARTMENT OF PUBLIC WORKS APPROVAL
This project is acceptable for final approval and we recommend to the Board of Public Works that it be ordained so.
Date:
Construction Manager
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
V'a(
Elizabeth A. Maradik, President
Gary A. Gilot, Member
Joseph R. Molnar, Vice President
�181
Jordan V. Gathers, Member
611 X.
Murray L. Miller, Member Attest: Theresa M. Heffner, Clerk
Date: Anril25.2023
Final Waiver of Lien
State of Indiana, County of Berrien SS:
Justin Butler being duly sworn that he/she is the Vice President
(Name of Officer) (Title)
of Selge Construction Co., Inc. having contracted with City of South Bend
(Contractor) (Owner)
to furnish certain materials and/or labor as follows; Install Qwick Ku rb
(Description)
for a project known as Grandview Ave and RR Qwick Kurb Installation
(Name of Project)
located at Grandview Ave at the NICTD and Norfolk Southern crossings '
and owned by City of South Bend
(Owner)
and does hereby further state on the behalf ofthe aforementioned subcontractor/supplier:
(PARTIAL WAIVER) that there is due from the Contractor the sum of
Dollars
❑ receipt of which is hereby aclmowledged; or
❑ the payment of which has been promised as the sole consideration for this Affidavit and Final Waiver of Lien -which is given
solely with respect to said amount, and which waiver shall be effective only upon receipt of payment thereof by the
undersigned;
(FINAL WAIVER) that the final balance due from the contractor is the sum of
Seventeen Thousal2d Seven Hundred Eighty Five Dollars and Zero Cents L$17,785.00) _
❑ receipt ofwhich is hereby acknowledged; or
i
❑ the payment of which has been promised as the sole consideration forthis Affidavit and Final Waiver of Lieu which shall
become effective only upon receipt of such payment. !!!
TBEREFORE, the undersigned waives and releases unto the Owner of said premises, any and all liens or claims whatsoever
on the above -described property and improvements thereon au account of labor or material or both, furnished b the undersigned
thereto, subject to limitations or conditions expressed herein, if any; and farther certified that no other party has any claim or right to a
lien on account of any work performed or material furnished to the undersigned for said project, and within the scope of this Affidavit
and Waiver of Lien. ,
Selge Construction Co., Inc. B c
y r '-'' i President
Michigan (Fim) (AuthmizedRepresentative)
STATE OF� 1
)
Berrien ) SS: ;
31x 19EM COUNTY )
Before me, the undersigned, a Notary Public, in and for said County and State, personally appeared Justin Butler
and acknowledged the execution of the foregoing Affidavit and Waiver of Lien.
IN WITNESS WHEREOF, Ihave hereunto subscribed my name and affixed my o alai seal on the 7th day of
- - April BIEI%,20
yL���� r i
C.O. rb;-, � ".��1 otsiy Public Signature
My Commission Expires: 10/27/2027
' q`
' --1 =Allison Swinehart !
Residingin Michigan County, Berrien; �'�, y��r'°8r' �FllotarypublicName
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 04/07/2023
Name Becca Plantz Department Public Works
BPW Date 04/25/2023 Phone Extension 5998
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer ❑ Officer Name Michael Patton
BPW Attorney
❑ Attorney Name
Dept. Attorney ❑ Attorney Name
Purchasing ❑
Check the Appropriate Item Tvne —
Michael Schmidt
All Submissions
❑ Professional Services Agreement ❑ Contract ❑ Proposal
❑ Open Market Contract ❑ Amendment/Addendum ❑ Special Purchase, QPA
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award ❑ Reject Bids/Quotes
❑ Proposal Opening ❑ C/O & PCA No. ® PCA
❑ Chg. Order, No. ❑ Traffic Control ❑ Resolution
n Other: n Ease./Encroach
Company or Vendor Name
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Information
Construction Co., Inc.
YesU If Yes, Approved by Purchasing
❑ No
❑ WBE Completed E-Verify Form Attached ❑❑ Nos
Grandview Ave and RR Qwick Kurb Installation
117-114
Local Roads & Streets — Streets & Alleys
PO-20695
$17,785.00
Lump Sum
Install Qwick Kurb provided by the City on Grandview Ave at the NICTD
and Norfolk Southern grade crossings as a supplemental safety measure for
the quiet zone.
For Change Orders Only
Amount of ❑ Increase $
❑ Decrease ($ )
Previous Amount
Current Percent of Change
New Amount
Total Percent of Change:
Time Extension Amount:
Increase
Decrease
Increase
Decrease
New Completion Date: