HomeMy WebLinkAboutAward Bid - MarMain Apartments Roof Replacement Proj No. 122-061 - Slatile Roofing & Sheet Metal Co.1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/235-9251
FAx 574/235-9171
CITY OF SOUTH BEND TAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
February 14, 2023
Mr. Gerald Longerot
Slatile Roofing and Sheet Metal Co., Inc.
1703 S. Ironwood Dr.
South Bend, IN 46613
michael.albert&slatile.com; ebra.carothers(kslatile.com
RE: Award Bid — MarMain Apartments Roof Replacement - Project No. 122-061
Dear Mr. Longerot:
At its February 14, 2023 meeting, the Board of Public Works awarded the above
referenced bid to you in the amount of $436,012, Base Bid Plus Alternate. Enclosed please find
a signed Bid/Proposal form.
Please forward the following documents in one submittal by February 28, 2023 to my
attention for Board of Public Works approval at lhensleyksouthbendin.gov:
1) One (1) signed original of the Public Works Contract (enclosed)
2) Labor & Material Payment Bond
3) Performance Bond (125% of Bid Amount)
4) Certificate of Insurance naming the City of South Bend as an additional insured
5) Item #4 for all subcontractors that you use
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/235-9251
FAx 574/235-9171
CITY OF SOUTH BEND TAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
February 14, 2023
Mr. Michael W. Frahn
Midland Engineering Company, Inc.
52369 State Road 933 North
South Bend, IN 46637
zmahnesmithkmidlanden in�g com
RE: Bid Award — MarMain Apartments Roof Replacement — Project No. 122-061
Dear Mr. Frahn:
At its February 14, 2023, meeting, the Board of Public Works awarded the above
referenced bid to Slatile Roofing and Sheet Metal Co., Inc. in the amount of $436,012, Base Bid
Plus Alternate.
Thank you for bidding, and we hope you bid with us in the future.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
Is/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
uTH INTER -OFFICE MEMORANDUM
r
U\
DEPARTMENT OF PUBLIC WORKS
x �4i5 k DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Zach Hurst, Project Engineer
SUBJECT: Award Bid - Project No. 122-061
MarMain Apartments Roof Replacement
DATE: 02/01 /2023
On January 24, 2023, the Board of Public Works opened and read bids for the above project.
Two bids were received, from Slatile Roofing and Sheet Metal, and Midland Engineering. The
bids were reviewed and found complete and responsive. A breakdown of the bids is as follows:
Contractor:
Slatile Roofing and
Sheet Metal
Midland Engineering
Base Bid:
$434,812.00
$440,600.00
Alternate Item:
$1,200.00
$2,500.00
TOTAL:
$436,012.00
$443,100.00
UNIT PRICE: Roof Drain Replacement:
$3,200.00
$750.00
UNIT PRICE: '/2" Plywood Replacement:
$235.00
$225.00
UNIT PRICE: V Plywood Replacement:
$275.00
$250.00
During review of the bids, Midland Engineering noted that if three (3) or more roof drains
required replacement, they would become the low bid. However, upon consultation with Forum
Architects, the City's architect for this project, it was noted that roof drain replacement is an
unforeseen condition. It is not possible to determine if a roof drain requires full replacement until
the construction work has begun and the existing bolts are removed. A copy of that
correspondence is included in this bid award package.
MWBE Analysis:
MBE goal: 0.6%
• Met via JMH Roofing Company: $8,696.00 (2.0%)
WBE goal: 2.1 %
Met via JMH Roofing Company: $17,392.00 (4.0%)
I recommend award of the base bid and alternate item for MarMain Apartments Roof
Replacement to Slatile Roofing and Sheet Metal Co. Inc., in the amount of $436,012.00.
Funding is available through PR-00021364.
Page 1 of 1
Zach Hurst
From:
William Hentschel <whentschel@forumarchitectsllc.com>
Sent:
Thursday, January 26, 2023 2:57 PM
To:
Zach Hurst
Cc:
info
Subject:
RE: MarMain Roof - bids and award
Afternoon Zach:
The Mar -Main roof only has seven (7) roof drains.
Durning our roof inspections, all appeared to be in acceptable condition except one location.
But until they get into the roof replacement, it is unknow to what will be required at this one location.
At the other locations some of the strainers may need to be reattached or replaced — but nothing major.
The biggest issue come up when the roofing system replacement work is being done.
To do the roof replacement, the clamp ring bolts need to be removed as part of the roofing system replacement.
With older roof drains there is the possible for the bolts to snap off — which then would require a replacement to the
roof drain.
That's why in most cases the problem is unseen or undetectable until you do the roof system replacement.
On the past 30 or 40 roof replacement projects we have encounter maybe one or two roof drains that needed
replacement.
But that is typically on a school roof project where we are doing multiple roofs areas for that school.
I think the biggest item that can possible show up maybe repairs to the masonry parapets.
You can't really see those areas except at the caps which some do appear to require some minor joint repair work.
Let me know if you need anything else.
Thanks
William
CITY OF SOUTH BEND, INDIANA
CONTRACTOR'S BID FOR PUBLIC WORK
Project Name Mar -Main Apartments Roof Replacement
Project No. 122-061
For Bids Due January 24, 2023 to bpwbids@southbendin.gov
PART I
(Must be completed for all bids. Please type or print)
Date: January 24, 2023 Bidder (Firm): Slatile Roofing & Sheet Metal Co., Inc.
Address: 1703 S. Ironwood Drive
City/State/Zip: South Bend, IN 46613 Telephone Number: (574 ) 233-7485
Agent of Bidder (if Applicable):
Pursuant to notices given, the undersigned offers to furnish labor and/or material necessary to complete the
public works project of.
MarMain Roof Replacement
the City of South Bend, Indiana, in accordance with plans and specifications prepared by:
Forum Architects
and dated 1/6/2023
for the sum of (enter the Total Bid as shown on the Proposal)
Four Hundred Thirty Four Thousand Eight Hundred Twelve Dollars
(Enter sum of Total Base Bid plus Alternates shown on Proposal)
($ 434,812.00 )
(Numerical)
The undersigned further agrees to furnish a bond or certified check with this bid for an amount specified in
the notice of the letting. If alternative bids apply, the undersigned submits a proposal for each in accordance
with the notice. Any addendums attached will be specifically referenced at the applicable page.
If additional units of material included in the contract are needed, the cost of units must be the same as that
shown in the original contract if accepted by the City of South Bend. If the bid is to be awarded on a unit
basis, the itemization of the units shall be shown�onaeparate �aftachm
By
(5ignatur�y
Gerald Longerot
(Printed Name of Person Signing)
The above bid is accepted this
Subject to the following conditions:
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
C'
Elizabeth A. Maradik, President
Gary A. Gilot, Member
4
Murray L. Miller, Member
ACCEPTANCE
day of
",�2_ 7Tt
Joseph R. Molnar, Vice President
Jordan V. Gathers, Member
6 , "
Attest: Theresa M. Heffner, Clerk
Date: February 14, 2023
W
BOARD OF PUBLIC WORKS
CITY OF SOUTH BEND, INDIANA
PUBLIC WORKS CONTRACT
This Agreement is made and entered into this 14th Day of February, 2023, by and between Slatile
Roofing & Sheet Metal Co., Inc, 1703 S. Ironwood Dr., South Bend, IN 46613 (the "Contractor"),
and the Board of Public Works (the "Board").
The Contractor covenants and agrees to make the following improvement, as fully set out in the
Request for Quotations, Standard Specifications, Special Provisions, Plans, and Bid Proposals, all
of which are set forth as a part of this Contract, for:
PROJECT NO. 122-061
DESCRIPTION: MARMAIN APARTMENTS ROOF REPLACEMENT
COMPLETION DATE: SEE SPECIFICATIONS
AMOUNT: $436,012; BASE BID PLUS ALTERNATE
FT TNT)TN(T- PR-000? 1364
The unit prices for this improvement were those prices as received and accepted by the Board on
the 24th Day of January, 2023.
The Contractor further agrees to notify the assigned Engineer when this improvement is
completed. This notification shall be in the form of a Project Completion Affidavit, signed by the
Contractor. Upon final acceptance of the improvement by the Engineer, the Contractor's final
estimate will be presented to the Board for final Payment with one (1) copy of the Project
Completion Affidavit and one (1) copy of a Waiver of Lien.
Each of the Parties, by signing below, represents and warrants to the other Party that he/she/it has
the authority to bind the named person or entity to this Agreement.
CITY OF SOUTH BEND, INDIANA SLATILE ROOFING & SHEET
BOARD OF PUBLIC WORKS METAL CO., INC.
Elizabeth A. Maradik, President
Gary A. Gilot, Member
Murray L. Miller, Member
Joseph R. Molnar, Vice President
Printed Name
Jordan V. Gathers, Member Signature
Attest: Theresa M. Heffner, Clerk
Date: February 14, 2023
BID/PROPOSAL -
CITY OF SOUTH BEND -
Project Name: Mar -Main Apartments TIF Project "
Project Number: 122-061
For Bids Due: January 24, 2023
Contractor Name: Slatile Roofing & Sheet Metal Co., Inc.
BASE BID
Item
No.
Description
Total Amount
1
Replacement of the existing roofing system with a new roofing system per
drawings andspecifications
$394,812.00
2
Utility Allowance for Unseen Conditions
$15,000.00
3
Parapet Repair Allowance
$25,000.00
BASE BID TOTAL $434,812.00
ALTERNATE
Item
No.
Description
Total Amount
State the ADD amount (labor and material) to the base bid to replace existing
$1,200.00
1
broken or missing glass in roof skylights with new matching glass. Include all
necessary glazing sealing material and accessories for weather tight
installation
ALTERNATE TOTAL $1,200.00
UNIT PRICE
Item
No.
Description
Unit Price
1
Provide unit cost (labor and material) to replace entirely an existing roof drain
with new roof drain bowl, clamps, strainer, and accessoriesper roof drain
$3,200.00
2
Provide unit cost (labor and material) to replace existing damaged 1/2"
plywood roof sheathing with new 1/2" plywood roof sheathing per 4' x 8' area
$ 235.00
Provide unit cost (labor and material to replace existing damaged 3/4" plywood
roof sheathing with new 3/4" plywood roof sheathing per 4'x8' area
$ 275.00
Bidder (Firm): Slatile Roofing & Sheet Metal Co., Inc.
Address: 1703 S. Ironwood Drive
City/State/Zip: South Bend, IN 46613 Telephone Number: 574) 233-7485
By / sy
(Signat )
Gerald Longerot - President
(Printed Name of Person Signing)
Version 09/29/2021 Contractor's Bid for Public Works - 7
When the prospective Contractor is unable to certify to any of the statements below, it shall attach an explanation to this Affidavit
CONTRACTOR'S NON -COLLUSION AND NON -DEBARMENT AFFIDAVIT, CERTIFICATION
REGARDING INVESTMENT WITH IRAN, EMPLOYMENT ELIGIBILITY VERIFICATION, NON-
DISCRIMINATION COMMITMENT AND CERTIFICATION OF USE OF UNITED STATES STEEL
PRODUCTS OR FOUNDRY PRODUCTS
(Must be completed for all quotes and bids. Please type or print)
STATE OF Indiana )
St. Joseph COUSS:NTY )
The undersigned Contractor, being duly sworn upon his/her/its oath, affirms under the penalties of perjury
that:
1. Contractor has not, nor has any other member, representative, or agent of the firm, company,
corporation or partnership represented by him, entered into any combination, collusion or agreement with
any person relative to the price to be bid by anyone at such letting nor to prevent any person from bidding
nor to induce anyone to refrain from bidding, and that this bid is made without reference to any other bid and
without any agreement, understanding or combination with any other person in reference to such bidding.
Contractor further says that no person or persons, firms, or corporation has, have or will receive directly or
indirectly, any rebate, fee, gift, commission or thing of value on account of such sale; and
2. Contractor certifies by submission of this proposal that neither contractor nor any of its principals
are presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from
participation in this transaction by any Federal department or agency; and
3. Contractor has not, nor has any successor to, nor an affiliate of, Contractor, engaged in
investment activities in Iran.
a. For purposes of this Certification, "Iran" means the government of Iran and any agency
or instrumentality of Iran, or as otherwise defined at Ind. Code § 5-22-16.5-5, as
amended from time -to -time.
b. As provided by Ind. Code § 5-22-16.5-8, as amended from time -to -time, a Contractor
is engaged in investment activities in Iran if either:
i. Contractor, its successor or its affiliate, provides goods or services of twenty
million dollars ($20,000,000) or more in value in the energy sector of Iran;
or
ii. Contractor, its successor or its affiliate, is a financial institution that extends
twenty million dollars ($20,000,000) or more in credit to another person for
forty-five (45) days or more, if that person will (i) use the credit to provides
goods and services in the energy sector in Iran; and (ii) at the time the
financial institution extends credit, is a person identified on list published by
the Indiana Department of Administration.
4. Contractor does not knowingly employ or contract with an unauthorized alien, nor retain any
employee or contract with a person that the Contractor subsequently learns is an unauthorized alien.
Version 09/29/2021 Contractor's Bid for Public Works - 4
Contractor agrees that he/she/it shall enroll in and verify the work eligibility status of all of Contractor's
newly hired employees through the E-Verify Program as defined by I.C. 22-5-1.7-3. Contractor's
documentation of enrollment and participation in the E-Verify Program is included and attached as part of
this bid/quote; and
5. Contractor shall require his/her/its subcontractors performing work under this public contract to
certify that the subcontractors do not knowingly employ or contract with an unauthorized alien, nor retain
any employee or contract with a person that the subcontractor subsequently teams is an unauthorized alien,
and that the subcontractor has enrolled in and is participating in the E-Verify Program. The Contractor agrees
to maintain this certification throughout the term of the contract with the City of South Bend, and understands
that the City may terminate the contract for default if the Contractor fails to cure a breach of this provision
no later than thirty (30) days after being notified by the City.
6. Persons, firms, partnerships, corporations, associations, or joint venturers awarded a contract by the
City of South Bend through its agencies, boards, or commissions shall not discriminate against any employee
or applicant for employment in the performance of a City contract with respect to hire, tenure, terms,
conditions, or privileges of contract or employment, or any matter directly or indirectly related to contracting
or employment because of race, sex, religion, color, national origin, ancestry, gender expression, gender
identity, sexual orientation, or due to age or disability that does not affect that persons ability to perform the
work.
In awarding contracts for the purchase of work, labor, services, supplies, equipment, materials, or any
combination of the foregoing including, but not limited to, public works contracts awarded under public
bidding laws or other contracts in which public bids are not required by law, the City, its agencies, boards,
or commissions will consider the Contractor's good faith efforts to obtain participation by those
subcontractors certified by the State of Indiana as a Minority Business ("MBE") or as a Women's Business
Enterprise ("WBE") as a factor in determining the lowest, responsible, responsive bidder.
Contractors seeking the award of a City contract cannot be required to award a subcontract to an MWBE;
however, they may not unlawfully discriminate against said MBE/WBE. On goal -eligible contracts,
Contractors are required to either meet both MBE and WBE utilization goals or demonstrate that the
Contractor has made good faith efforts to obtain participation from MBE and WBE subcontractors. A finding
of noncompliance or a discriminatory practice shall prohibit that Contractor from being awarded a City
contract for a period of one (1) year from the date of such determination, and such determination may also
be grounds for terminating the contact to which the discriminatory practice or noncompliance pertains.
7. The undersigned Contractor agrees that the following nondiscrimination commitment shall be made
a part of any contract which it may henceforth enter into with the City of South Bend, Indiana or any of its
agencies, boards or commissions.
Contractor agrees not to discriminate against or intimidate any employee or applicant for employment in the
performance of this contract with privileges of employment, or any matter directly or indirectly related to
employment, because of race, religion, color, sex, gender expression, gender identity, sexual orientation,
handicap, national origin or ancestry. Breach of this provision may be regarded as material breach of
contract.
I, the undersigned bidder or agent as contractor on a public works project, understand my statutory
obligations to the use of steel products or foundry products made in the United States (I.C. 5-16-8-1). I hereby
certify that I and all subcontractors employed by me for this project will use steel products or foundry
products made in the United States on this project if awarded. I understand I have an affirmative duty to
notify the City in my bid that my proposal does not include the use of steel products or foundry products
made in the United States. I understand it is my sole obligation and responsibility to provide a justification
to the City, subject to review and approval, why the cost of United States made steel or foundry products is
unreasonable. Prior to award and upon submission of bid which does not use steel products or foundry
products made in the United States, the City, through its director of public works, shall make a determination
if the price of United States made steel or foundry is unreasonable. I understand that violations hereunder
Version 09/29/2021 Contractor's Bid for Public Works - 5
may result in forfeiture of contractual payments.
I hereby affirm under the penalties of perjury that the facts and information contained in the foregoing bid
for public works are true and correct.
Dated this 24th day of January , 2023
Subscribed and sworn to before me this 24th
My Commission Expires /-/) /AS �30
County of Residence
Slatile Roofing & Sheet Metal Co., Inc.
ontractoFBidder (Firm)
S` ignature of Cgntract id or Its Agent
Gerald Longerot - President
Printed Name and Title
day of January , 20 23
- .r 2
Notary P h
Version 09/29/2021 Contractor's Bid for Public Works - 6
�1'I11 R
C,
CITY OF SOUTH BEND "`\ `.
MINORITY AND WOMEN BUSINESS ENTERPRISE INCLUSION PROGRAM PLAN
FORM MBE-1.0
MBE UTILIZATION PLAN
This completed form should be supplied with Bids that pertain to City of South Bend Public Works Projects involving MBE participation. It is
the bidder's sole responsibility to verify whether any listed minority -owned business meets the MBE qualifications.
Project Number: 122-061 Project Name: Mar -Main Apartments Roof Replacement
Bidder: Slatile Roofing & Sheet Metal Co., Inc. Total Bid Amount: 434,812.00 MBE Goal: 0.6%
Page of
Name 8 Address of MBE
Primary Contact Person
(Name/Telephone)
Scope of Work to be Performed
(Attach scope/schedule if you need additional space)
Dollar Amount of MBE
Component
Percentage
ofTolal
Bid/Proposal
JMH Roofing Company, Inc.
1219 E. 9th Street
Indianapolis, IN 46202
Jerilyn Huntington
317-605-2789
Materials Supplied
$8,696.00
2%
Submitted by: Gerald Longerot January 24, 2023
Print Name S—ig—rolrure I Date
Version 09/29/2021 Contractor's Bid for Public Works - 8
CITY OF SOUTH BEND '!
MINORITY AND WOMEN BUSINESS ENTERPRISE INCLUSION PROGRAM PLAN _
FORM WBE-1.0
WBE UTILIZATION PLAN -"
This completed form should be supplied with Bids that pertain to City of South Bend Public Works Projects involving WBE participation. It is
the bidder's sole responsibility to verify whether any listed woman -owned business meets the WBE qualifications.
Project Number: 122-061 Project Name: Mar -Main Apartments Roof Replacement
Bidder: Slatile Roofing & Sheet Metal Co., Inc. Total Bid Amount: 434,812.00 WBE Goal: 2.1%
Page of
Name 8 Address of WBE
Primary Contact Person
(Name/Telephone)
Scope of Work to be Performed
(Attach scope/schedule if you need additional space)
Dollar Amount of WBE
Component
Percentage
of Total
Bid/Proposal
JMH Roofing Company, Inc.
1219 E. 9th Street
Indianapolis, IN 46202
Jerilyn Huntington
317-605-2789
Materials Supplied
$17,392.00
4%
Submitted by: Gerald Longerot p� January 24, 2023
Print Name gigna ure Date
—7
Version 09/29/2021 Contractor's Bid for Public Works - 9
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 02/01/2023
Name Zach Hurst Department DPW
BPW Date 02/14/2023 Phone Extension 3057
Review and Approval Required Prior to Submittal to Board
Diversity Compliance ❑
Officer Name
and Inclusion Officer
BPW Attorney
❑ Attorney Name
Dept. Attorney ❑ Attorney Name
Purchasing ❑
Check the Appropriate Item I
Professional Services Agreement ❑ Contract
❑ Open Market Contract
❑ Bid Opening
❑ Quote Opening
❑ Proposal Opening
❑ Chg. Order, No.
I-1 Other:
Company or Vendor Name
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
— Reauired for All Submissions
Proposal
❑ Amendment/Addendum ❑ Special Purchase, QPA
® Bid Award
❑ Req. to Advertise ❑ Title Sheet
❑ Quote Award
❑ Reject Bids/Quotes
❑ C/O & PCA No.
❑ PCA
❑ Traffic Control
❑ Resolution
❑ Ease./Encroach
Reauired Information
Slatile Roofing and Sheet Metal
Yes U If Yes, Approved by Purchasing
® No
❑ MBE Completed E-Verify Form Attached ❑ Yes
No
MarMain Apartments Roof Replacement
122-061
River West DA TIF
PR-00021364
$436,012.00
Base bid plus alternate item for glazing repair
Request to award bid to replace the roof at MarMain Apartments
For Change Orders Only
Amount of ❑ Increase $
❑ Decrease ($ )
Previous Amount
Current Percent of Change
New Amount
Total Percent of Change:
Time Extension Amount:
Increase
Decrease
Increase
Decrease
New Completion Date: