HomeMy WebLinkAbout5E1 Budget Request (High Street Improvements)
Redevelopment Commission Agenda Item
DATE: February 6, 2023
FROM: Chris Dressel, Staff
SUBJECT: Budget Request: High Street Improvements
Funding Source* (circle one) River West; River East; South Side; Douglas Road; West Washington; RDC General
*Funds are subject to the City Controller's determination of availability; if funds are unavailable, as solely determined by the City Controller,
then the authorization of the expenditure of such funds shall be void and of no effect.
Purpose of Request:
Staff requests the Redevelopment Commission's approval of $200,000 from the South Side
Redevelopment Area TIF to be budgeted for improvements to the west side of High Street from
Donmoyer Avenue to Ridgedale Road in the form of new curbs and sidewalks. Project
construction should commence this year and be completed no later than spring 2023.
The request for funds is consistent with the Miami Hills Neighborhood Plan (2020) that identified
upgrading infrastructure conditions and improve connections for non-motorized travel within
the neighborhood and to surroundings. The project area is of highest priority as it currently has
no proper sidewalks.
If you should have any questions or need more information, please feel free to contact me at
either cdressel@southbendin.gov or 235-5847.
INTERNAL USE ONLY: Project ID: PROJ ;
Total Amount – New Project Budget Appropriation $_______________;
Total Amount – Existing Project Budget Change (increase or decrease) $_______________;
Funding Limits: Engineering: $_____________________; Other Prof Serv Amt $_______________;
Acquisition of Land/Bldg (circle one) Amt: $___________; Street Const Amt $________________;
Building Imp Amt $_________; Sewers Amt $_________; Other (specify) Amt $ ________________
_________________________Pres/V-Pres
ATTEST: __________________Secretary
Date: ____________________
APPROVED Not Approved