HomeMy WebLinkAboutIndustrial Wastewater Discharge Permit Renewal - South Bend Ethanol, LLCSouth Bend Ethanol LLC Industrial Discharge Permit 5
City of South Bend
Department of Public Works
Industrial Pretreatment Program
Significant Industrial User – Permit No. 014-1257.300
In accordance with all the terms of Chapter 17 of the City of South Bend’s Municipal Code, and with any
applicable provisions of federal or state law and regulations, permission is hereby granted to:
South Bend Ethanol, LLC
3201 West Calvert Street
South Bend IN 46613
for the contribution of wastewater into the City of South Bend Publicly Owned Treatment Works.
This permit is granted in accordance with the application filed on 21 October 2022.
Effective on: 23 January, 2023
Expires on the: 22 January, 2028
Any violation of the terms and conditions of this permit shall be deemed a violation of the City of South
Bend Municipal Code and will subject the permittee to the sanctions set out in section 17-11 through 17-
13 of the Municipal Code.
The permittee shall file an application for a renewal permit, a minimum of 90 days prior to the expiration
date.
Approved By:
January 10, 2023
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
DEPARTMENT OF PUBLIC WORKS
ERIC HORVATH, DIRECTOR
January 3, 2023
Board of Public Works
City of South Bend
1316 County City Building
227 West Jefferson Boulevard
South Bend IN 46601
RE: Renewal of Industrial Wastewater Discharge Permit
Dear Board Members:
The Division of Environmental Services recommends approving the renewal of the Industrial Discharge Permit for South
Bend Ethanol at the January 10, 2023, Board of Public Works Meeting.
South Bend Ethanol, LLC is a is classified as a Significant Industrial User (SIU) as defined in the South Bend Municipal
Code. South Bend Ethanol’s requirements were reviewed for necessary changes to ensure the industrial permit remains
legally substantiated. After review of requirements and historical data, some monitoring frequencies were changed.
Ammonia, Nitrogen and Phosphorus monitoring frequency has been upgraded from a semiannual basis to a monthly
basis. No other significant changes were made.
If you should have any questions, please do not hesitate to contact me (574) 235-5798 or at sshane@southbendin.gov.
Sincerely,
Serena Shane
Pretreatment Manager
City of South Bend
Division of Environmental Services, Department of Utilities
3113 Riverside Drive
South Bend, IN 46628
(574) 235-5798
sshane@southbendin.gov
Enclosure(s)
- Industrial Discharge Permit Board of Public Works Signature Page, Part II- Monitoring Frequency, -Agenda Request
Form
South Bend Ethanol, LLC Industrial Wastewater Discharge Permit page 10 of 42
PART II - MONITORING REQUIRMENTS
A. Monitoring Frequency
1.The following parameters shall be monitored at the frequency and with the sampling
type stated below. All measurements, tests, and analyses of the characteristics of
water and wastes to which reference is made in this permit shall be conducted using
the methods and procedures approved in 40 CFR 136 and amendments thereto,
unless otherwise specified in an applicable Categorical Pretreatment Standard.
The following parameters shall be monitored at Sample Site Outfall #3201 with the methods and at the
frequency stated below:
Parameter Sample Frequency Sampling Type
Flow, Total (gpd) Daily Continuously
Flow Monthly (gal) Monthly Continuously
BOD (mg/L) Daily Composite
FeCl or H2S chemical Addition Daily Continuously
pH (S.U.) Daily Grab
pH DAF (S.U.) Daily Grab
TSS (mg/L) Daily Composite
Ammonia, Nitrogen (mg/L) Monthly Composite
Phosphorus (mg/L) Monthly Composite
Arsenic (mg/L) Semiannual Composite
Cadmium (mg/L) Semiannual Composite
Chromium (mg/L) Semiannual Composite
Copper (mg/L) Semiannual Composite
Lead (mg/L) Semiannual Composite
Mercury (mg/L) Semiannual Grab
Nickel (mg/L) Semiannual Composite
Oil & Grease (mg/L) Semiannual Grab
Oil & Grease, TPH (mg/L) Semiannual Grab
Silver (mg/L) Semiannual Composite
Zinc (mg/L) Semiannual Composite
See Flow Measurement Requirements referenced in Part III - Reporting Requirements.
South Bend Ethanol LLC Industrial Discharge Permit 3
PERMIT BRIEFING MEMO
1. Facility Description
South Bend Ethanol, LLC engages in the conversion of corn to denatured, fuel-grade
ethanol by processes of fermentation, distillation, and drying. As a by-product of ethanol
production, SB Ethanol will also produce Distiller’s Dried Grain & Solubles (DDGS) and
corn oil which will be sold for livestock feed.
South Bend Ethanol’s facility is designed to operate 24 hours per day, seven days per week,
with two twelve-hour shifts. SB Ethanol currently has 50 employees. Seasonal variation in
production is not anticipated.
2. Discharge Description:
Wastewater streams discharged at Sample Site Outfall # 3201 originate from three (3)
locations. They are:
Source of Wastewater
Average
Discharge
(gpd)
Maximum
Discharge
(gpd)
1
Process Water – Combined in the Neutralization
Holding Tanks, includes wastewater from
fermentation and water pumped from containment
dikes following precipitation
300,000 750,000
2 Equipment/Facility Wash-down 110,000 200,000
3 Reverse Osmosis reject wastewater 10,000 20,000
Total average discharge flow 420,000 970,000
All of the wastewater is combined, treated, and discharged at the main lift station which is
located at the southeast corner of the property along Calvert Street, and is the location for
compliance monitoring.
3. Sample Site Description
Sample Site Outfall # 3201 is located inside South Bend Ethanol’s lift station on the far
southeast corner of SB Ethanol’s facility. The discharge is metered by South Bend
Ethanol’s Doppler System. As the lift station fills up there are two pumps set at different
levels in the pit to pump the discharge into the City of South Bend Sewer System. Inside
the lift station there is a T-line for the collection of compliance samples. South Bend
Ethanol’s sampler is connected to one end of the T-line and the Pretreatment staff
attaches the Pretreatment Program sampling tubing to the other end of the T-Line. Both
composite and grab samples are collected through the T-Line tubing using the pump in
the auto-sampler to draw the sample into the bottles. The sampler flow monitor is
connected to South Bend Ethanol’s flow meter in order to collect a flow proportioned
sample.
South Bend Ethanol LLC Industrial Discharge Permit 4
4. Wastewater Treatment
Wastewater Treatment consists of a surge pond, DAF system, dewatering system, Ferrous
Chloride addition or other Control Authority approved chemical addition and pH
neutralization.
5. Classification
South Bend Ethanol is classified as a Significant Industrial User (SIU) as defined in the
South Bend Municipal Code due to its wastewater flow in excess of 25,000 gpd. South
Bend Ethanol is a Category “A” industry, due to its process flow over 100,000 gpd.
South Bend Ethanol is not a Federal Categorical User. Although they plan to engage in
organic chemical production, South Bend Ethanol is not covered by 40 CFR 414 because
ethanol is produced using fermentation. According to 414.11 (e) “The provisions of [40
CFR 414] do not apply to any process wastewater discharges from the manufacture of
organic chemical compounds solely by fermentation processes.”
6. Calculation of Limits
South Bend Ethanol must meet Local Limits at their discharge location. Local Limits from
the South Bend Municipal Code are applied without modification to South Bend Ethanol’s
total facility effluent, with one exception: South Bend Ethanol was granted a specific
variance setting the upper pH limit to 12.0 S.U. in a 1995 amendment to Chapter 17 of the
South Bend Municipal Code. The upper pH limit of 12.0 was granted in order to assist in
keeping pH high in an additional effort to control hydrogen sulfide. This variance applies
to South Bend Ethanol as well because the industrial process, as described in South Bend
Ethanol’s permit application, and the surrounding situation is identical to the conditions
that gave rise to this variance.
7. Monitoring Frequency
Monitoring frequencies are based on South Bend’s US EPA approved Industrial
Pretreatment Program monitoring plan.
8. Industrial Operator Certification Requirement
Operator Certification Requirement: D
Industrial operator certification requirements are based on the criteria listed in Indiana
Administrative Code, Title 327, 5-22-5.
Permit Drafted by:
City of South Bend
Industrial Pretreatment Group
November 2022
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 1/3/2023
Name Serena Lozano-Shane Department UTILITIES
BPW Date 1/10/2023 Phone Extension 5798
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
x Other: South Bend Ethanol Industrial Discharge Permit Renewal
Required Information
Company or Vendor Name
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description _______________________________________________________________
_______________________________________________________________
___________________________________________________
For Change Orders Only
Amount of
Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: