HomeMy WebLinkAboutChange Order No 3 - Morris Performing Arts Center-Main Level Slab Replacement Proj No. 121-029A - Larson Danielson Construction
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
December 20, 2022
Mr. Timothy F. Larson
Larson Danielson Construction Co., Inc.
302 Tyler St.
LaPorte, IN 46350
mcd@ldconstruction.com
RE: Change Order No. 3 – Morris Performing Arts Center-Main Level Slab Replacement
Project No. 121-029A
Dear Mr. Larson:
At its December 20, 2022 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $9,028.38, bringing the revised contract amount to
$975,535.70.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:
PROJECT NO:121-029A
PROJECT NAME:Morris Performing Arts Center Main Level Slab Replacement
CONTRACT DATE:
CHANGE ORDER NO.
SUBJECT OF CHANGE ORDER:Increase in
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns.
The original contract sum $ 876,374.83
Net change by previously authorized change orders $,
The contract sum prior to this change order $.
By this Change Order, the project amount is Increased
Decreased $ 9 28 8
The new contract sum including this change order $ 975,5 70
This Change Order represents a total change of 9 %
Total change for entire project 1.1 %
Original contracted completion date/time 09/23/2022
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
RECOMMENDED FOR APPROVAL
CONTRACTOR Construction Manager
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Date:Contractor Signature
Printed Name and Title Elizabeth A. Maradik, President
Company name Joseph R. Molnar, Vice-President
Address Gary A. Gilot, Member
City, State, Zip Jordan V. Gathers, Member
Murray L. Miller, Member
December 20, 2022
LaPorte, IN 46350
302 Tyler Street
Ph : 219-362-2127
Change Request
Phone:
Job:56-606 SB,CTYOF-MORRIS PER ARTS CNTR
Number:
Date:
10
10/18/22
To:Rebecca Plantz
SOUTH BEND, CITY OF
227 W. JEFFERSON BLVD
SOUTH BEND, IN 46601
Ph: (574)235-5998
Description:Final Cleaning
We are pleased to offer the following specifications and pricing to make the following changes:
All labor, material and equipment cleaning costs beyond the reported $20,000 MBE participation included in our contract
agreement. Additional cleaning costs were incurred for cleaning carpets that would have otherwise been new if not for material
delays and cleaning additional spaces beyond the construction areas. Additional cleaning costs partially offset by T&M costs for
handrail removal and replacement coming in less than estimated costs included in CO #2.
Description Material Subcontract Other PriceLaborEquipment
Masters Construction MBE Final Cleaning $27,376.00$27,376.00
K&S Engineering MBE Testing $3,622.00$3,622.00
Original Contract MBE Participation $-20,000.00$-20,000.00
Remove & Reinstall Handrails $-2,823.00$-2,823.00
$8,175.00Subtotal:
$-423.45OH & P 15.00%-$2,823.00
$1,099.80OH & P 10.00%$10,998.00
$177.03Bond Markup 2.00%$8,851.35
$9,028.38Total:
If you have any questions, please contact me at (219)575-6085.
Date:
Approved by:Submitted by:
Cc: Sexton; Daniel (SOUTH BEND, CITY OF)
Darin Meyer
LARSON-DANIELSON CONST. CO INC
Page 1 of 1
City of South Bend
Department of Administration & Finance
Change Order Request Form
Multiple PO lines:
Project POs:
PO Number PO-14138
Line Number 3
Original Dollar Amount $0.00
New Dollar Amount
(For liquidation request, enter $0)$9,028.38
Reason Code (if changed)na
Financial Dimensions (fund-dept-
division-subdivision-main account)Morris Capital
Project Code (if applicable)PROJ-281
Description of change (include
budget impact)
Increase in cleaning service scope of work to accommodate additional cleaning
request outside of original plans.
APPROVED BY PROJECT
ACCOUNTING TEAM (if applicable)
PO Number
Line Number outside
Original Dollar Amount
New Dollar Amount
(For liquidation request, enter $0)
Reason Code (if changed)
Financial Dimensions (fund-dept-
division-subdivision-main account)
Project Code (if applicable)
Description of change (include
budget impact)
APPROVED BY PROJECT
ACCOUNTING TEAM (if applicable)
PO Number
Line Number
Original Dollar Amount
Changing the line amount:
You can only change a line amount if it has NOT been invoiced against.
• If the line has NOT been invoiced – reduce the line amount to equal what it should be.
• If the line has been invoiced – cancel the delivery remainder and finalize the individual line, then add a new line for the
amount that should be remaining.
If you have changes to more than two lines on the same PO, fill out a separate section for each line affected by the change
order.
For change orders on project-related POs, this form must be approved by the Project Accounting Team as described in
Supplement 508.
PO-14138 Change Order Request Form #3 1 of 3
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 12/14/2022
Name: Becca Plantz Department of Public Works – Engineering Division
BPW Date: 12/20/2022 Phone Extension: 5998
Required Prior to Submittal to Board
BPW Attorney X Michael Schmidt
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 3 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Larson-Danielson
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Morris Performing Arts Center – Main Level Slab Replacement
Project Number 121-029A
Funding Source Morris Capital
Account No. PROJ-281
Amount Original = $876,374.83, New Amount CO3 = $975,535.70
Terms of Contract
Special Contract Provisions
Purpose/Description
For Change Orders Only
Amount of Increase
Decrease
$ 9,028.38
($ )
Previous Amount $ 966,507.32
Current Percent of Change:
Increase 0.9%
( %)
New Amount
Decrease $
$975,535.70
Total Percent of Change:
Increase
Decrease
11.1%
( %)
Time Extension Amount:
New Completion Date: