HomeMy WebLinkAboutAward Bid - WWTP Masonry Improvements at Building 5 Proj No. 121-046R - Slatile Roofing & Sheet Metal
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
December 20, 2022
Mr. Gerald Longerot
Slatile Roofing and Sheet Metal Co., Inc.
1703 S. Ironwood Dr.
South Bend, IN 46613
michael.albert@slatile.com
RE: Award Bid – Wastewater Treatment Plant Masonry Improvements at Building 5
Project No. 121-046R
Dear Mr. Longerot:
At its December 20, 2022 meeting, the Board of Public Works awarded the above
referenced bid to you in the amount of $455,600; Base Bid Plus Alternates 1, 3, & 4. Enclosed
please find a signed Bid/Proposal form.
Please forward the following documents in one submittal by January 10, 2023 to my
attention for Board of Public Works approval at lhensley@southbendin.gov:
1) One (1) signed original of the Public Works Contract (enclosed)
2) Labor & Material Payment Bond
3) Performance Bond (125% of Bid Amount)
4) Certificate of Insurance naming the City of South Bend as an additional insured
5) Item #4 for all subcontractors that you use
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
December 20, 2022
Mr. Jason Watts
Ziolkowski Construction, Inc.
4050 Ralph Jones Dr.
South Bend, IN 46628
lmarker@zbuild.com
RE: Bid Award – Wastewater Treatment Plant Masonry Improvements at Building 5
Project No. 121-046R
Dear Mr. Watts:
At its December 20, 2022, meeting, the Board of Public Works awarded the above
referenced bid to Slatile Roofing and Sheet Metal Co., Inc. in the amount of $455,600; Base Bid
Plus Alternates 1, 3, & 4.
Thank you for bidding, and we hope you bid with us in the future.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENVIRONMENTAL SERVICES
TO: Members of the Board of Public Works
Michael Schmidt, Assistant City Attorney Public Works
Theresa Heffner, Board of Public Works Clerk
FROM: Jacob M. Klosinski, P.E., Assistant City Engineer
SUBJECT: 121-046R WWTP Masonry Improvements Compressor Building #5
(PROJ00000289; PR-00018587)
Agenda Request - Bid Award
DATE: December 12. 2022
On November 22, 2022, the Board of Public Works opened and read bids for the subject project.
Division of Engineering and Division of Utilities reviewed the documents and finds the information
correct and complete. Attached is a full bid tabulation which includes alternate and unit pricing.
Base Bid(s) ranked as follows based on price:
BID SUMMARY (Bold text represents low price for Base or Alternate Item for comparison)
Contractor Base Bid
Total
Alternate
#1
Alternate
#2
Alternate
#3
Alternate
#4
TOTAL BID
Base +
Alternates
#1,#2,#3,#4
Slatile
Roofing and
Sheet Metal,
Inc.
$410,000.00 $3,800.00 $12,000.00 $6,800.00 $35,000.00 $467,600.00
Ziolkowski
Construction,
Inc.
$434,437.00 $9,850.00 $13,500.00 $20,250.00 $14,500.00 $492,537.00
Bold text represents low bid for Base or Alternate Item for comparison
BID UNIT PRICE SUMMARIES (Bold text represents low unit price (Add), high unit price (Deduct) values)
Contractor Brick Masonry
Repointing (Per
SF)
Brick
Replacement
(Per Unit)
Glass Block
Replacement
(Per Unit)
Limestone
Replacement
(Per SF)
22’-0” Steel Lintel
Replacement (Per
EACH)
Add Deduct Add Deduct Add Deduct Add Deduct Add Deduct
Slatile
Roofing and
Sheet Metal
$25.00 $25.00 $35.00 $20.00 $80.00 $80.00 $45.00 $30.00 $3,800.00 $3,800.00
Ziolkowski
Construction,
Inc.
$21.00 $20.00 $30.00 $28.00 $40.00 $37.00 $50.00 $46.00 $3,960.00 $3,910.00
Bid Assessment
Both Bids were submitted with the complete bid packages. However, each had minor
discrepancies that required supplemental information requests from each contractor.
Slatile Roofing and Sheet Metal Co., Inc.
At the time of Bid Opening, a scrivener’s error was acknowledged in the Based Bid Total on
Slatile Roofing and Sheet Metal Co,, Inc.’s pricing. Pricing was identified to be an addition error.
Slatile’s Base Bid for Items 1, 2, and 3 was $410,000.00.
Supplementary Information was requested for Part II Section I and Part II Section II of the
Experience, Plan and Equipment Questionnaires. Slatile submitted supplementary information
to assess the questionnaire section.
Slatile listed D.A. Dodd as an WBE Certified Contractor. This was identified as a scrivener’s
error. D.A. Dodd is an MBE Certified Contractor and supplementary information was supplier by
Slatile identifying the correct certification from the State of Indiana certified MBE list. JMH
Roofing Company Inc. is both a certified WBE and a certified MBE. Based on review of the
anticipated MBE and WBE Utilization percentages, the scrivener’s error will have a minor impact
to the WBE and MBE Utilization percentages but does not impact the total spend for MBE and
WBE subcontractors. Slatile was identified to have a larger percentage of MBE and WBE
utilization.
Slatile Roofing and Sheet Metal was identified as the lowest, responsive, responsible bidder and
provided all supplementary information requested by City Engineering and Public Works.
Ziolkowski Construction, Inc.
At the time of the Bid Opening, all documentation submitted by Ziolkowski Construction, Inc.
appeared to be submitted as complete. Further analysis of the Bid Questionnaire section
indicated that supplementary information was needed to review the Experience, Plan, and
Equipment Questionnaires. Ziolkowski Construction provided supplemental information for Part
II Section II as requested.
Ziolkowski Construction was identified as the second lowest responsive, responsible bidder and
provided all supplementaryu information requested by City Engineering and Public Works.
Both Bidders submitted Base Bid pricing within Public Works’ budget for the project. Unit pricing
was competitive and similar with the exception of the glass block replacement unit pricing.
Bid Award Recommendation
The Division of Engineering recommends the award of the Total Base Bid (Items 1, 2, and 3)
and Alternates #1 (Item 4), #3 (Item 6), and #4 (Item 7) for Project No. 121-046R WWTP
Masonry Improvements Compressor Building #5 to Slatile Roofing and Sheet Metal Co.,
Inc. for the Total of $455,600.00. Unit pricing as described in the Contractor’s Bid Proposal
shall be considered for additional work in the event of unforeseen conditions are encountered
during the repair and restoration work. Allowances for the project shall be directed by the City as
needed.
Funding: Sewage Works Building Repair and Maintenance Account 641-06-605-514-436001.
For questions regarding the subject agenda request, contact Jacob M. Klosinski (Ext. 9496) at
the Division of Engineering.
December 20, 2022
BOARD OF PUBLIC WORKS
CITY OF SOUTH BEND, INDIANA
PUBLIC WORKS CONTRACT
This Agreement is made and entered into this 20th Day of December, 2022, by and between Slatile
Roofing & Sheet Metal Co., Inc., 1703 S. Ironwood Dr., South Bend, IN 46613 (the “Contractor”),
and the Board of Public Works (the "Board”).
The Contractor covenants and agrees to make the following improvement, as fully set out in the
Request for Quotations, Standard Specifications, Special Provisions, Plans, and Bid Proposals, all
of which are set forth as a part of this Contract, for:
PROJECT NO. 121-046R
DESCRIPTION: WASTEWATER TREATMENT PLANT MASONRY
IMPROVEMENTS AT BUILDING 5
COMPLETION DATE: SEE SPECIFICATIONS
AMOUNT: $455,600; BASE BID PLUS ALTERNATES 1, 3, & 4
FUNDING: PR-00018587
The unit prices for this improvement were those prices as received and accepted by the Board on
the 22nd Day of November, 2022.
The Contractor further agrees to notify the assigned Engineer when this improvement is
completed. This notification shall be in the form of a Project Completion Affidavit, signed by the
Contractor. Upon final acceptance of the improvement by the Engineer, the Contractor’s final
estimate will be presented to the Board for final Payment with one (1) copy of the Project
Completion Affidavit and one (1) copy of a Waiver of Lien.
Each of the Parties, by signing below, represents and warrants to the other Party that he/she/it has
the authority to bind the named person or entity to this Agreement.
BOARD OF PUBLIC WORKS SLATILE ROOFING & SHEET
METAL CO., INC.
President Member Printed Name
Member Member Signature
Member Attest: Clerk
December 20, 2022
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 11-14-2022
Name: Jacob M. Klosinski Department of Public Works – Engineering Division
BPW Date: 11-22-2022 Phone Extension:9496
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Michael Schmidt
Dept. Attorney Attorney Name Michael Schmidt
Purchasing Mickey Lovy / Ron O'Connor
Check the Appropriate Item Type –Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name WWTP Compressor Building Masonry Improvements
Project Number 121-046R / PROJ# 00000289
Funding Source 641-06-605-514-436001 Wastewater Operations and Maintenance
Account No. PR # 00018587
Amount
Terms of Contract
Special Contract Provisions
Purpose/Description The Division of Engineering and Division of Utilities requests the Board of
Public Works receive and open public bids for the subject project at its
meeting on 11/22/2022. The Wastewater Treatment Plant Compressor
Building is scheduled for general building maintenance, masonry
tuckpointing, lintel restoration, select window & door replacements, and
minor electrical and plumbing improvements.
For Change Orders Only
Amount of
Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
(%)
New Amount $
Total Percent of Change:
Increase
Decrease
%
(%)
Time Extension Amount:
New Completion Date:
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 12-12-2022
Name: Jacob M. Klosinski Department of Public Works – Engineering Division
BPW Date: 12-20-2022 Phone Extension:9496
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Michael Schmidt
Dept. Attorney Attorney Name Michael Schmidt
Purchasing Kim Thompson / Mickey Lovy / Ron O'Connor
Check the Appropriate Item Type –Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Slatile Roofing and Sheet Metal (V-00001513)
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Lafayette Falls Phase IV, Section One – Sidewalk Installation
Project Number 121-046R (PROJ00000289; PR-00018587)
Funding Source Sewage Works Operations – Building Repairs and Maintenance
Account No. 641-06-605-514-436001
Amount $455,600.00
Terms of Contract Lump Sum (Base Bid plus Alternate #1, Alternate #3, & Alternate #4)
Special Contract Provisions Unit Prices and Allowances shall be Owner directed
Purpose/Description The Division of Engineering and Division of Utilities recommends the Board
of Public Works award the subject project to Slatile Roofing and Sheet Metal
as the lowest, responsive, responsible bidder. Upon execution of contract,
Notice to Proceed for this project will be issued in Dec 2022/Jan 2023.
For Change Orders Only
Amount of
Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
(%)
New Amount $
Total Percent of Change:
Increase
Decrease
%
(%)
Time Extension Amount:
New Completion Date: