December 20, 2022
Mr. Brian Triska
Traffic Control Specialists, LLC
1810 W. Pacific Ave.
Knox, IN 46534
estimating@tcspecialists.net; rik@tcspecialists.net
RE: Quotation Award – Multi-Component Striping – Project No. 122-065
Dear Mr. Brian Triska:
At its December 20, 2022 meeting, the Board of Public Works awarded the above
referenced quotation to you in the amount of $17,838.94.
Please forward the following documents in one submittal by January 10, 2023 to my
attention for Board of Public Works approval at lhensley@southbendin.gov :
1) One (1) signed original of the Contract (enclosed); and
2) Certificate of Insurance naming the City of South Bend as an additional insured.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
December 20, 2022
Ms. Caroline Hughes
CE Hughes Milling, Inc. dba The Airmarking Company
1544 N. SR 25
Rochester, IN 46975
penny@airmarking.com; nick@airmarking.com
RE: Quotation Award – Multi-Component Striping – Project No. 122-065
Dear Ms. Hughes:
At its December 20, 2022 meeting, the Board of Public Works awarded the above
referenced quotation to Traffic Control Specialists, LLC in the amount of $17,838.94.
We thank you for quoting and hope you will quote with us again in the future.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Daniel Sexton, Project Engineer
SUBJECT: Award Project No. 122-065
Multi-Component Striping
DATE: December 20, 2022
On December 20, 2022, the Department of Public Works opened and read quotes for the above
project, using the quote process for projects less than $50,000. The request for quote was sent
to five (5) contractors, and only two (2) quotes were received.
The contractor quotes rank as follows:
Quoter Amount
1. Traffic Control Specialists, LLC $17,838.94
2.The Airmarking Company, Inc $20,303.00
I recommend award of a contract to Traffic Control Specialists, LLC who provided the
lowest responsible and responsive quote in the amount of $17,838.94.
Sufficient funds have been appropriated from Local Roads and Streets, 251-431000.
Please call with your questions.
Page 1 of 1
December 20, 2022
BOARD OF PUBLIC WORKS
CITY OF SOUTH BEND, INDIANA
PUBLIC WORKS CONTRACT
This Agreement is made and entered into this 20th Day of December, 2022, by and between Traffic
Control Specialists, LLC, 1810 W. Pacific Ave., Knox, IN 46534 (the “Contractor”), and the
Board of Public Works (the "Board”).
The Contractor covenants and agrees to make the following improvement, as fully set out in the
Request for Quotations, Standard Specifications, Special Provisions, Plans, and Bid Proposals, all
of which are set forth as a part of this Contract, for:
PROJECT NO. 122-065
DESCRIPTION: MULTI-COMPONENT STRIPING
COMPLETION DATE: SEE SPECIFICATIONS
AMOUNT: $17,838.94
FUNDING: PR-00021150
The unit prices for this improvement were those prices as received and accepted by the Board on
the 20th Day of December, 2022.
The Contractor further agrees to notify the assigned Engineer when this improvement is
completed. This notification shall be in the form of a Project Completion Affidavit, signed by the
Contractor. Upon final acceptance of the improvement by the Engineer, the Contractor’s final
estimate will be presented to the Board for final Payment with one (1) copy of the Project
Completion Affidavit and one (1) copy of a Waiver of Lien.
Each of the Parties, by signing below, represents and warrants to the other Party that he/she/it has
the authority to bind the named person or entity to this Agreement.
BOARD OF PUBLIC WORKS TRAFFIC CONTROL
SPECIALISTS, LLC
President Member Printed Name
Member Member Signature
Member Attest: Clerk
December 20, 2022
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 12/13/2022
Name: Daniel Sexton Department of Public Works – Engineering Division
BPW Date: 12/20/2022 Phone Extension: 5903
Required Prior to Submittal to Board
BPW Attorney X Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Traffic Control Specialists, LLC
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Multi-Component Striping
Project Number 122-065
Funding Source LR&S: 251-431000
Account No. PR/PO # PR-00021150
Amount $ 17,838.94
Terms of Contract Multi-component striping at Michigan/Chippewa roundabout.
Special Contract Provisions n/a
Purpose/Description Updating faded striping at the Michigan St and Chippewa Ave intersection
roundabout.
For Change Orders Only
Amount of Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: