HomeMy WebLinkAbout5B1 Change Order (Seitz Park Phase 1)
Redevelopment Commission Agenda Item
DATE: October 25, 2022
FROM: Kara Boyles, City Engineer
SUBJECT: Seitz Park, Phase I
Funding Source* (circle one) River West; River East; South Side; West Washington; Douglas Road; RDC General
*Funds are subject to the City Controller's determination of availability; if funds are unavailable, as solely determined by the City Controller,
then the authorization of the expenditure of such funds shall be void and of no effect.
Purpose of Request: $1M from River East Residential TIF
This request will provide funding for a change order (#7) for the Seitz Park, Phase I project. The
general contractor, Ziolkowski Construction, has requested a change order for $990K due to
escalation and delay costs related to access to the Seitz Park project area. As a result of ND
Hydro project delays, Ziolkowski was not able to access the site to begin work on Divisions C, D
and E until June of this year, a date and time that exceeded their final completion date of
5/26/2022.
INTERNAL USE ONLY: Project ID: PROJ 117-093A ;
Total Amount – New Project Budget Appropriation $1,000,000____;
Total Amount – Existing Project Budget Change (increase or decrease) $__________;
Funding Limits: Engineering: $_____________________; Other Prof Serv Amt $_______________;
Acquisition of Land/Bldg (circle one) Amt: $___________; Street Const Amt $________________;
Building Imp Amt $_________; Sewers Amt $_________; Other (specify) Amt $ ________________
_________________________Pres/V-Pres
ATTEST: __________________Secretary
Date: ____________________
APPROVED Not Approved
SOUTH BEND REDEVELOPMENT COMMISSION