HomeMy WebLinkAboutChange Order No 2 - Installation of School Zone Flashing Beacons Proj No. 117-075 - Michiana Contracting, Inc.
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
September 27, 2022
Mr. Scott Kirkpatrick
Michiana Contracting, Inc.
7843 Lilac Rd.
Plymouth, IN 46563
skirkpatrick@michianacontracting.com
RE: Change Order No. 2 – School Zone Flashing Beacons Installation
Project No. 117-075
Dear Mr. Kirkpatrick:
At its September 27, 2022 meeting, the Board of Public Works approved the above
referenced Change Order be increase by $30,017.45, bringing the revised contract amount to
$1,038,566.36.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Scott Kreeger, Project Engineer
SUBJECT: Change Order No. 2 - Project No. 117-075
School Zone Flashing Beacons
DATE: September 26, 2022
As part of the current INDOT contract for the School Zone Flashing Beacons (DES#1801240),
the City of South Bend Division of Engineering has requested an additional 5 flashing beacons
with the intention of replacement parts for potential knockdowns and unforeseen damages.
These 5 beacons will be a non-participating item as it is outside the original scope of the project
and will be funded by the City. INDOT has approved the change order within the project for
$30,017.45 and will adjust the contract PO with Michiana Contracting to allow for the additional
flashing beacons. This acquisition is for supplies only.
Contract No:T -41189 Change Order No.: 002
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: T -41189 Letting Date:12/08/2021
District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Kreeger, Scott Status:Pending
Change Order Information Change Order No.: 002 EWA: Y or Force Acct: N
Date Generated: 09/20/2022 Date Approved: 00/00/0000
Reason Code: SCOPE CHANGES, Added Quantities/Items
Description: Additional Flashing Beacons for stock
Original Contract Amount $ 739,628.00
Current Change Order Amount $ 30,017.45 Percent: 4.059 %
Total Previous Approved Changes $ 268,920.91 Percent: 36.359 %
Total Change To-Date $ 298,938.36 Percent: 40.418 %
Modified Contract Amount $ 1,038,566.36
Time Extension Information
Date Initiated 00/00/0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description:
Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00
Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______
SS Days____________ SP Days Value $ _______________
Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
Contract No:T -41189 Change Order No.: 002
INDIANA Department of Transportation Page: 2
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______*
($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- )
(Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days)
Verbal Approval Required? Y / N If Y, by_____________ Date Issued___________
Total Change To-Date>5%? Y / N If Y , Copy to Program Budget Manager_________________
Scope/Design Recommendation
Required?
Y / N If Y, Referred to Project Manager(PM) __________________
Date to PM__________ Date Returned___________
Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________
If N,Resolution: Approved __________ Disapproved ___________
Resolved by_________________________ Date__________
LPA Signatures Required? Y / N If Y, Date to LPA _____________ Date Returned _________
FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer _________________________ Date _____________
Comments: ____________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
Contract No:T -41189 INDIANA Date:09/20/2022
Change Order No:002 Department of Transportation Page: 3
Contract: T -41189
Project: 1801240 - State:180124000LC4
Change Order Nbr: 002
Change Order Description: Additional Flashing Beacons for stock
Reason Code: SCOPE CHANGES, Added Quantities/Items
CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change
0022 1801240 0022 805-06742 EACH 4,727.490 5.000 C Amount:$ 23,637.45
Item Description:SOLAR POWERED FLASHING BEACON ASSEMBLY
Supplemental Description1: School zone flashing beacon with applied time & monitoring
Supplemental Description2:
0023 1801240 0023 805-11771 EACH 1,276.000 5.000 C Amount:$ 6,380.00
Item Description:SIGNAL POLE PEDESTAL 16 FT
Supplemental Description1: Pedestal base cap
Supplemental Description2:
Total Value for Change Order 002 = $ 30,017.45
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
The City of South Bend has requested an additional 5 flashing beacons with the intention of replacement parts for potential knockdowns and
unforeseen damages. These 5 beacons will be a non-participating item as it is outside the original scope of the project and will be funded by the
City. The INDOT PM is aware of the change and has given concurrence
Change Order Explanation for Specific Line Item
****************************************************************************************************************************
It is the intent of the parties that this change order is full and complete compensation for the work describe above.
Notification and consent to this change order is hereby acknowledged.
Contractor:____________________________________________ Signed By:_____________________________________________
Date:__________________________________________________
***************************************************************************************************************************
NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system.
Contract No:T -41189 INDIANA Date:09/20/2022
Change Order No:002 Department of Transportation Page: 4
****************************************************************************************************************************
APPROVED FOR LOCAL PUBLIC AGENCY
PE/S _________________________
****************************************************************************************************************************
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Approval Level Name of Approver Date Status
Project Engineer/Supervisor Project Engineer/Supervisor 00/00/0000 Action Pending
September 27, 2022
EWA 003 Added Beacons for Stock (Revised)PAGE 1 OF 5
DATE :
CONTRACT:T-41189 DESCRIPTION :
FORCE ACCOUNT / EXTRA WORK
INDOT
LABOR : 109.05 ( a )WEEK ENDING :
EMPLOYEE RATE TOTAL
FOREMAN 30.00 $0.00
ELECTRICIAN 32.43 $0.00
OPERATOR 27.53 $0.00
LINEMAN 35.76 $0.00
GROUNDMAN TRUCK DRIVER 22.16 $0.00
GROUNDMAN/LABORER 19.73 $0.00
$0.00
$0.00
$0.00
$0.00
TOTAL LABOR $0.00 ( 1 )
---------------------
FICA 7.65% X LINE ( 1 ) $0.00 ( 2 )
---------------------
FRINGES :
---------------
FOREMAN HRS X $15.50 =
ELECTRICIAN HRS X $12.33 =
OPERATOR HRS X $13.13 =
LINEMAN HRS X $15.52 =
GROUNDMAN HRS X $10.70 =
LABORER HRS X $9.89 =
TOTAL FRINGES $0.00 ( 3 )
-------------------
WORKMEN'S COMPENSATION 7.1% X LINE ( 1 ) $0.00 ( 4 )
-------------------
BODILY INJURY INSURANCE 2.1% X LINE ( 1 ) $0.00 ( 5 )
-------------------
PROPERTY DAMAGE INSURANCE 0.0% X LINE ( 1 ) $0.00 ( 6 )
-------------------
STATE UNEMPLOYMENT 4.3% X LINE ( 1 ) $0.00 ( 7 )
-------------------
FEDERAL UNEMPLOYMENT 0.8% X LINE ( 1 ) $0.00 ( 8 )
-------------------
TRAVEL ALLOWANCE OR SUBSISTENCE $0.00 ( 9 )
-------------------
TOTAL : LINES ( 1 ) + ( 2 ) + ( 3 ) + ( 4 ) + ( 5 ) + ( 6 ) + ( 7 ) + ( 8 ) + ( 9 ) $0.00 ( 10 )
-------------------
20% X LINE ( 10 ) $0.00 ( 11 )
-------------------
GRAND TOTAL LABOR : LINES ( 10 ) + ( 11 ) $0.00 ( 12 )
-------------------
July 25, 2022
$0.00
$0.00
$0.00
$0.00
$0.00
PAY HOURSDOUBLETIMEOVERTIMEREGULAR
$0.00
MICHIANA CONTRACTING, INC
FORCE ACCOUNT/EXTRA WORK AGREEMENT
Additional Beacons For Stock
Added by City of South Bend
EWA 003 Added Beacons for Stock (Revised)PAGE 2 OF 5
INSURANCE, TAXES : 109.05 ( b )
INSURANCE : [ 1.80 % X LINES ( 12 ) + ( 20 ) + ( 26 ) ] $524.06 ( 13 )
-------------------
TAXES $0.00 ( 14 )
-------------------
TOTAL : LINES ( 13 ) + ( 14 ) $524.06 ( 15 )
-------------------
10% X LINE ( 15 ) $52.41 ( 16 )
-------------------
GRAND TOTAL FOR INSURANCE, TAXES : LINES ( 15 ) + ( 16 ) $576.47 ( 17 )
-------------------
MATERIALS : 109.05 ( c )
TOTAL MATERIALS $25,995.00 ( 18 )
-------------------
12% X LINE ( 18 ) $3,119.40 ( 19 )
-------------------
GRAND TOTAL MATERIALS : LINES ( 18 ) + ( 19 ) $29,114.40 ( 20 )
-------------------
EQUIPMENT : 109.05 ( d )
CONTRACTOR OWNED EQUIPMENT : NO. OF
MACHINERY OR SPECIAL EQUIPMENT HOURS EXTENSION
SERVICE TRUCK $0.00
BUCKET TRUCK $0.00
LINE TRUCK $0.00
DUMP TRUCK $0.00
PICKUP TRUCK $0.00
SIGN INSTALLATION TRUCK $0.00
LOOP INSTALLATION TRUCK $0.00
TRUCK CRANE - 15 TON 65 FT., 6X4, DSL $0.00
BACKHOE - CASE # 580E $0.00
TRENCHER - D/W # 6510, W / BACKHOE $0.00
TRENCHER - D/W # 4010, W / BACKHOE $0.00
TRENCHER - D/W # 3700 $0.00
BORING MACHINE - VERMEER D24X40 $0.00
FIBER OPTIC FUSION SPLICER (LESS TRUCK) $0.00
HYDRAULIC EXCAVATOR - MINI - CAT 304/305 $0.00
HYDRAULIC EXCAVATOR - KOMATSU PC270 $0.00
LOADER - SKID STEER B/C # 843 $0.00
ROCK BREAKER - Z-96, FOR SKID STEER $0.00
TRACTOR ON HIGHWAY - 6X4, 275 HP, DSL. $0.00
EQUIPMENT TRAILER - 3 AXLE - 20 FT $0.00
EQUIPMENT TRIALER - 2 AXLE - 6 TON $0.00
AIR COMPRESSOR - ROTARY SCREW, 185 CFM $0.00
PAVEMENT BREAKER - 90 LB. $0.00
ROCK DRILL / CORE MACHINE $0.00
CHIPPING HAMMER $0.00
SMALL GENERATOR - 4KW $0.00
VIBRATORY PLATE COMPACTOR $0.00
CUT-OFF SAW $0.00
MAGNETIC DRILL $0.00
CONCRETE SAW - 35 HP $0.00
TRAFFIC LINE REMOVER $0.00
HYDRAULIC BENDER $0.00
ARROW BOARD - DIESEL $0.00
CRASH ATTENUATOR FOR TRUCK MOUNTING $0.00
TRASH PUMP W/ HOSE & GENERATOR $0.00
TOTAL CONTRACTOR OWNED EQUIPMENT $0.00 ( 21 )
---------------------
RENTED EQUIPMENT $0.00 ( 22 )
-------------------
FUEL, LUBRICANTS, & TRANSPORTATION COSTS $0.00 ( 23 )
-------------------
TOTAL : LINES ( 21 ) + ( 22 ) + ( 23 ) $0.00 ( 24 )
-------------------
12% X LINE ( 24 ) $0.00 ( 25 )
-------------------
GRAND TOTAL EQUIPMENT : LINES ( 24 ) + ( 25 ) $0.00 ( 26 )
-------------------
$17.55$7.22$10.33
ADJ. MO. RATE
BLUE BOOK BLUE BOOKBLUE BOOK
OPERATING TOTAL COST
$10.25 $36.01 $46.26
/ 176 HRS. RATE / HR PER HOUR
$28.34 $36.21 $64.55
$51.45 $54.39 $105.84
$16.40 $32.81 $49.21
$6.78 $17.72 $24.50
$56.10 $83.57 $139.67
$24.65 $76.82 $101.47
$19.78 $18.00 $37.78
$21.34 $22.91 $44.25
$103.05$54.36$48.69
$18.63 $14.41 $33.04
$12.34 $10.22 $22.56
$126.34 $210.73 $337.07
$62.14 $69.31 $131.45
$13.77 $14.66 $28.43
$10.23 $2.10 $12.33
$17.83 $44.07 $61.90
$10.62 $7.15 $17.77
$6.32 $1.45 $7.77
$5.85 $14.72 $20.57
$1.23 $0.45 $1.68
$3.24 $0.56 $3.80
$5.56 $0.45 $6.01
$1.23 $4.98 $6.21
$2.79 $4.18 $6.97
$10.39 $14.69
$4.30 $4.17 $8.47
$1.63 $22.45 $24.08
$1.05 $0.70 $1.75
$38.96 $30.17 $69.13
$89.60 $43.48 $133.08
$3.97 $0.60 $4.57
$4.30
$7.96 $18.82 $26.78
$2.19 $2.27 $4.46
EWA 003 Added Beacons for Stock (Revised)PAGE 3 OF 5
EWA 003 Added Beacons for Stock (Revised)PAGE 4 OF 5
SUBCONTRACTS : 109.05 ( f )
SUBCONTRACTS WEEK ENDING :
DESCRIPTION : AMOUNT
TOTAL SUBCONTRACTS WEEK ENDING $0.00 ( 27 )
-------------------
TOTAL SUBCONTRACTS TO DATE $0.00 ( 28 )
-------------------
10% X LINE ( 28 ), FOR FIRST $3,000.00 $0.00 ( 29 )
-------------------
7% X BALANCE OF LINE ( 28 ) , IF LINE ( 28 ) IS OVER $3,000 $0.00 ( 30 )
-------------------
GRAND TOTAL SUBCONTRACTS : LINES ( 28 ) + ( 29 ) + ( 30 ) $0.00 ( 31 )
-------------------
TOTAL : LINES ( 12 ), ( 17 ), ( 20 ), ( 26 ), & ( 31 ) $29,690.87 ( 32 )
-------------------
1.0% BOND RATE BASED UPON LINE ( 32 ) $296.91 ( 33 )
-------------------
10% X LINE ( 33 ) $29.69 ( 34 )
-------------------
TOTAL EXTRA WORK : LINES ( 32 ) + ( 33 ) + ( 34 )$30,017.47 ( 35 )
-------------------
EWA 003 Added Beacons for Stock (Revised)PAGE 5 OF 5
QTY UNIT DESCRIPTION COST EXTENSION
5 EA School Zone Flashing Beacon
5 EA Pedestal Base Cap
--------------- ----------------- -------------------------------------------------------------------------------------
SUBTOTAL MATERIALS
1 LSUM MISC. MATERIALS
--------------- ----------------- -------------------------------------------------------------------------------------
1,276.00$
19,615.00$
6,380.00$
25,995.00$
-$
25,995.00$ TOTAL MATERIALS
3,923.00$
NNumber 646807
QQUOTATION
PPage:1 of 1
10435 ARGONNE WOODS DRIVE
WOODRIDGE, IL 60517
P:574-243-0901 F:630-543-5050
TTo:10675
MICHIANA CONTRACTING, INC
7843 LILAC ROAD
PO BOX 929
PLYMOUTH IN 46563 USA
PPhone:574-936-8613 Fax:
QQuote Date:7/14/2022 EExpires:9/12/2022
SJK@TCC1.com
(630) 506-7813PPhone:
STEPHEN KETTLESTRINGSSSalesperson:
EEmail:
FFOB:
TTerms:NET 30 BASED ON APPROVED CREDIT
Attn:
Email:
574-936-6201
110Book / Call / Item:
Letting Date:12/8/2021
5 ADD'L A.I. SZ FL BCNS - adderDescription:
Location:SOUTH BEND
T-41189 -- 12-8-21Contract No:
*** ADDER TO ORIGNAL QUANTITIES, SPARE UNITS
Part Number / Description Net PriceUnit PriceQty/UM
SOLAR POWERED FLASHING BEACON
ITEM 1; SCHOOL ZONE FLASHING BEACON WITH APPLIED
INFORMATION TIME CLOCK & MONITORING
* ASSUMES A CLEAR UNOBSTRUCTED VIEW OF SUN; NO SHADING ON
THE ARRAY.
** IF THERE IS A KNOCK-DOWN AND THE LOCATION IS STILL ACTIVE
ON GLANCE, THE AI TIME CLOCK WILL BE REPLACED BY A NEW UNIT
AS PART OF THE APPLIED INFORMATION WARRANTY PROGRAM,
THEREFORE, THERE IS NOT A CHARGE FOR THE UNIT
5.00 3,923.00 19,615.00EA
SIGNAL POLE, PEDESTAL 16FT
ITEM 2; 16' PEDESTAL-BASE-CAP-ANCHORS
5.00 1,276.00 6,380.00EA
Quote Total:25,995.00
Item Total: 25,995.00
Misc Charges and Adjustments: 0.00
PPricing does not include applicable sales taxes. If order is to be exempt sales tax, documentation must be provided at time of order.
Additional terms may apply. Review our full Terms & Conditions of Sale at www.trafficcontrolcorp.com.
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 9/20/2022
Name Scott Kreeger
Department Public
Works
BPW Date 9/27/2022 Phone Extension 9245
Required Prior to Submittal to Board
BPW Attorney Attorney Name Clara McDaniels
Dept. Attorney Attorney Name
Purchasing Michael Schmidt
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 2 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Michiana Contracting
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Installation of School Zone Flashing Beacons
Project Number DFO Proj. 077 (City PN: 117-075)
Funding Source Major Moves
Account No. 412-442001
Amount $30,017.45
Terms of Contract
Purpose/Description __Change Order #2 for the additional 5 flashing beacons for replacement and
knockdowns. See Change order documents below for more
details.______________________
For Change Orders Only
Amount of Increase
Decrease
$ 30,017.45
($ )
Previous Amount $ 1,008,548.91
Current Percent of Change:
Increase
Decrease
4.059%
( %)
New Amount $ 1,038,566.36
Total Percent of Change:
Increase
Decrease
40.418%
( %)
Time Extension Amount:
New Completion Date: