September 27, 2022
Mr. Ruben Alvarado
Rieth-Riley Construction Co., Inc.
25200 State Road 23
South Bend, IN 46614
ralvarado@rieth-riley.com
RE: Change Order No. 2 – 2022 Contractor Paving, Round II – Project No. 122-032
Dear Mr. Alvarado:
At its September 27, 2022 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $67,181, bringing the revised contract amount to
$2,157,982.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:9/20/2022
PROJECT NO:122-032
PROJECT NAME:2022 Contractor Paving Round 2
CONTRACT DATE:7/26/2022
CHANGE ORDER NO:1
SUBJECT OF CHANGE ORDER:PCR #1-Ireland & Ironwood Intersection
The original contract sum $ 2,090,801.00
Net change by previously authorized change orders $0.00
The contract sum prior to this change order $ 2,090,801.00
By this Change Order, the project amount is X Increased
67,181.00Decreased $
The new contract sum including this change order $ 2,157,982.00
This Change Order represents a total change of 3.21 %
Total change for entire project 3.21 %
Original contracted completion date/time 11/17/2022
Extension of date/time by previous change orders 0 days
Date/time extension by this change order 0 days
New completion date/time 11/17/2022
CONTRACTOR RECOMMENDED FOR APPROVAL
Contractor Signature CONSTRUCTION MANAGER
CITY OF SOUTH BEND
Printed Name and Title BOARD OF PUBLIC WORKS
Approved Date:
Rieth-Riley Construction Co., Inc.
Company Name
President
25200 State Road 23
Address
Member
South Bend, IN 46614
City, State, Zip
Member
Member
Member September 27, 2022
QUOTATION FOR ASPHALT PAVING - IRELAND AND
IRONWOOD
South Bend, IN 46614
25200 State Road 23
Rieth - Riley Construction Co., Inc.
Hannah Gritton
574 288-8321
574 233-3464
Contact:
Phone:
Fax:
Job Name:Quote To:COSB 2022 Contractor Paving Rd 2
8.30.22Date of Plans:
Phone:Revision Date:
Fax:
AMOUNTITEM DESCRIPTION QUANTITY UNIT UNIT PRICE
Mobilization LSM1.00 1 24,869.00 24,869.00
Maintaining Traffic LSM1.00 2 11,758.62 11,758.62
Milling 2"SYS1,463.00 3 4.28 6,261.64
HMA Surface 9.5 mm Type B TON161.00 4 131.31 21,140.91
Adjust Manhole to Grade EA1.00 5 632.23 632.23
Line, Thermoplastic, Solid, White, 4"LFT296.00 6 1.35 399.60
Line, Thermoplastic, Solid, Yellow, 4"LFT176.00 7 1.35 237.60
Line, Thermoplastic, Broken, White, 4"LFT90.00 8 1.55 139.50
Transverse Marking, Thermoplastic Solid, White 24"LFT37.00 9 10.60 392.20
Grooving for Pavement Markings, 4"LFT562.00 10 1.85 1,039.70
Pvmt Message Markings Thermo White Turn Arrow EA2.00 11 155.00 310.00
GRAND TOTAL $67,181.00
Page 1 of 1
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
Project Number: _______________ Project Name: __________________________ Change Order #: ____
DATE INITIATED: BPW DATE:
Brief Summary of Change Order; (Construction Change, Alternative, Substitution, Differing Instructions, Out of Scope, Etc.).
Attachments: (List documents support change – required)
Amount of ☐Increase / ☐Decrease: $____________________ Categories (Pick One):
☐ Scope of Work
☐ Differing Site Conditions, Changed Conditions
☐ Conflicted Specifications and Drawings
☐ Failed Materials
☐ Error
☐ Omission
☐ Final Quantity Adjustment
☐ _______________________
Previously approved Change Order(s): $___________________
Current Percent of Change: ____________________ %
New Total Amount: $____________________
Total Percent of Change: ____________________ %
Funding Secured From: __________________________
(filled out by PM)
RECOMMENDED BY:
Project Inspector (Print Name) (Signature) (Date)
REVIEWED BY:
Construction Manager (Print Name) (Signature) (Date)
APPROVED BY:
Engineering Project Manager (Print Name) (Signature) (Date)
Additional paving work at the intersection of Ireland and Ironwood. This section was not originally
part of the project scope and has been added to address major issues occurring on the roadway. See
attached quantity breakdown for more details.
City of South Bend
Department of Administration & Finance
Change Order Request Form
Multiple PO lines:
Project POs:
PO Number 18048
Line Number 5
Original Dollar Amount $1,161,746.00
New Dollar Amount
(For liquidation request, enter $0)$1,228,927.00 $67,181.00
Reason Code (if changed)
Financial Dimensions (fund-dept-
division-subdivision-main account)408-06-602-503-436008
Project Code (if applicable)330
Description of change (include
budget impact)Change Order #1 increase scope on project per Scott K
APPROVED BY PROJECT
ACCOUNTING TEAM (if applicable)Ron O'Connor 09/21/2022
PO Number
Line Number
Original Dollar Amount
New Dollar Amount
(For liquidation request, enter $0)
Reason Code (if changed)
Financial Dimensions (fund-dept-
division-subdivision-main account)
Project Code (if applicable)
Description of change (include
budget impact)
APPROVED BY PROJECT
ACCOUNTING TEAM (if applicable)
PO Number
Line Number
Original Dollar Amount
New Dollar Amount
(For liquidation request, enter $0)
Reason Code (if changed)
Financial Dimensions (fund-dept-
division-subdivision-main account)
Project Code (if applicable)
Description of change (include
budget impact)
APPROVED BY PROJECT
ACCOUNTING TEAM (if applicable)(PAT member's name and date to be completed by PAT member)
Changing the line amount:
You can only change a line amount if it has NOT been invoiced against.
• If the line has NOT been invoiced – reduce the line amount to equal what it should be.
• If the line has been invoiced – cancel the delivery remainder and finalize the individual line, then add a new line for the
amount that should be remaining.
If you have changes to more than two lines on the same PO, fill out a separate section for each line affected by the
change order.
For change orders on project-related POs, this form must be approved by the Project Accounting Team as described in
Supplement 508.
PO-18048 Reith Riley Construction PROJ-330 Increase Line 5 - ADD 67181.00 09-21-2022 per Scott K 1 of 3
City of South Bend
Department of Administration & Finance
Change Order Request Form
Multiple PO lines:
PO Number 18048
Line Number 5
Original Dollar Amount $1,161,746.00
New Dollar Amount
(For liquidation request, enter $0)$1,228,927.00
Reason Code (if changed)
Financial Dimensions (fund-dept-
division-subdivision-main account)408-436008
Project Code (if applicable)
Description of change (include
budget impact)Change in scope on the project.
PO Number
Line Number
Original Dollar Amount
New Dollar Amount
(For liquidation request, enter $0)
Reason Code (if changed)
Financial Dimensions (fund-dept-
division-subdivision-main account)
Project Code (if applicable)
Changing the line amount:
You can only change a line amount if it has NOT been invoiced against.
• If the line has NOT been invoiced – reduce the line amount to equal what it should be.
• If the line has been invoiced – cancel the delivery remainder and finalize the individual line, then add a new line for the
amount that should be remaining.
If you have changes to more than two lines on the same PO, fill out a separate section for each line affected by the change
order.
Supplement 508 Form - Change Order Request Form 1 of 5
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 9/16/2022
Name Scott Kreeger
Department Public
Works
BPW Date 9/27/2022 Phone Extension 9245
Required Prior to Submittal to Board BPW Attorney Attorney Name Michael Schmidt
Dept. Attorney Attorney Name
Purchasing Michael Schmidt
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 2 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Rieth-Riley Construction Co., Inc.
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name 2022 Contractor Paving Round 2
Project Number 122-032 (DFO PROJ00000330)
Funding Source
Major Moves, TIF River West, TIF West Washington, TIF Southside
Development
Account No.
412-423002, 324-10-102-121-442001, 422-10-102-121-442001, 430-
442001
Amount $67,181.00
Terms of Contract
Purpose/Description _Addition of Ireland & Ironwood intersection
For Change Orders Only
Amount of
Increase
Decrease
$ 67,181
($ )
Previous Amount $ 0
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $ 2,157,982
Total Percent of Change:
Increase
Decrease
3.21%
( %)
Time Extension Amount:
New Completion Date: