HomeMy WebLinkAboutChange Order No 1 - SBPD Roof Rehab & Replacement Proj No. 119-080 - Midland Engineering Co., Inc.
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
September 27, 2022
Mr. Michael W. Frahn, CPA
Midland Engineering Company, Inc.
52369 State Road 933 North
South Bend, IN 46637
lconrad@midlandengineering.com
RE: Change Order No. 1 (Final) – South Bend Police Department Roof Rehabilitation and
Replacement – Project No. 119-08
Dear Mr. Frahn:
At its September 27, 2022 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $27,100, bringing the revised contract amount to
$1,295,500.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
September 27, 2022
52369 State Road 933 N.
South Bend, IN 46637
Phone: (574) 272-0200
Fax: (574) 272-7400
To: CITY OF SOUTH BEND
Leslie Biek
227 W JEFFERSON BLVD
SOUTH BEND, IN 46601
Project: SBPD HEADQUARTERS RE-ROOF
RFC No: 001
Date: 2/28/2022
Description: Provide and Install (9) new curb caps for Pate Rails
The above work is subject to the same conditions as specified in the original contract
unless otherwise stipulated.
Upon approval the sum of $1,400.00 will be added to the contract price.
Original Contract $1,268,400.00
Other Approved Change Orders $0.00
Total Contract to Date $1,268,400.00
This Request $1,400.00
Other Pending Requests $0.00
Total Contract plus Pending RFCs $1,269,800.00
Authorized Signature: ______________________________________ Date: _________
Midland Engineering Co Inc
Authorized Signature: ______________________________________ Date: _________
CITY OF SOUTH BEND
52369 State Road 933 N.
South Bend, IN 46637
Phone: (574) 272-0200
Fax: (574) 272-7400
To: CITY OF SOUTH BEND
Leslie Biek
227 W JEFFERSON BLVD
SOUTH BEND, IN 46601
Project: SBPD HEADQUARTERS RE-ROOF
RFC No: 002
Date: 5/5/2022
Description: OPTION 1 Additional Wall Panel Roof System Removal
The above work is subject to the same conditions as specified in the original contract
unless otherwise stipulated.
Upon approval the sum of $35,700.00 will be added to the contract price.
Original Contract $1,268,400.00
Other Approved Change Orders $0.00
Total Contract to Date $1,268,400.00
This Request $35,700.00
Other Pending Requests $1,400.00
Total Contract plus Pending RFCs $1,305,500.00
Authorized Signature: ______________________________________ Date: _________
Midland Engineering Co Inc
Authorized Signature: ______________________________________ Date: _________
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 9/13/2022
Name Leslie Biek, PE Department PW
BPW Date 9/27/2022 Phone Extension 9323
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title
Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 1 and Final Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Midland Engineering Company, Inc.
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name SBPD Roff Rehabilitation and Replacement
Project Number 119-080
Funding Source Escrow lease
Account No.
Amount
Terms of Contract
Purpose/Description Final balancing change order for the project. Change order includes
additional curb caps for pate rails and additional wall panel roof system
removal.
For Change Orders Only
Amount of
Increase
Decrease
$ 27,100.00
($ )
Previous Amount $ 1,268,400.00
Current Percent of Change:
Increase
Decrease
2.14%
( %)
New Amount $ 1,295,500.00
Total Percent of Change:
Increase
Decrease
2.14%
( %)
Time Extension Amount:
New Completion Date: