Redevelopment Commission Agenda Item
DATE: September 20, 2022
FROM: Chris Dressel
SUBJECT: Budget Request (Coal Line Multiuse Trail Construction)
Which TIF? (circle one) River West; River East; South Side; Douglas Road; West Washington
PURPOSE OF REQUEST:
Staff requests the Redevelopment Commission's approval of an additional $300,000 to be
budgeted for construction of the Coal Line Trail Phase II (between Riverside Drive and IN 933)
based upon bids that were recently received through INDOT.
This request should allow completion of construction of Phase II in 2023 with two concurrent
projects, one including the trail plus amenities and a second including the river bridge crossing.
Phase I project construction (Lincoln Way West to Riverside Drive) is complete and will be
closed out this fall.
If you should have any questions or need more information, please feel free to contact me at
either cdressel@southbendin.gov or 235-5847.
INTERNAL USE ONLY: Project Code: _______________________________________________;
Total Amount new/change (inc/dec) in budget:; Break down:
Costs: Engineering Amt: ______________________; Other Prof Serv Amt_________________;
Acquisition of Land/Bldg (circle one) Amt: ________; Street Const Amt _______;
Building Imp Amt_________; Sewers Amt_________; Other (specify) Amt: ________________
___________________________________________. Going to BPW for Contracting? Y/N
Is this item ready to encumber now? ____ Existing PO#__________ Inc/Dec $_____________