City of South Bend | CE Services for Coal Line Trail Phase IIB
Des # 2200199 in the LaPorte District
August 23, 2022
Finnian Cavanaugh, E.I., Project Manager
227 W. Jefferson Blvd
South Bend, IN, 46601
Dear Members of the Board of Public Works:
Lawson-Fisher Associates P.C. (LFA) is pleased to submit our Letter of Interest (LOI) to
provide construction inspection services on the Coal Line Trail — (Phase IIB) Project.
Calling upon more than 35 years of LPA/INDOT construction inspection experience as
well as our recent/ongoing experience with the City of South Bend on Phase I of Coal
Line Trail, the LFA team stands behind its proven project approach that focuses on client
satisfaction, proactive inspection, and outward communication. LFA is ready to lead this
project with the City of South Bend. Your vision, becomes our vision.
Our locally-owned firm, in the heart of South Bend, is just 5 minutes from the
project site. Not only are we managing Phase 1 of Coal Line Trail; we also have the
reputation, experience, capacity, and flexibility to provide valuable management and
project continuity to this Rails-to-Trails project. We look forward to reinforcing these
demonstrated attributes to the City and are confident you will be satisfied with your
choice of the LFA Team.
Very truly yours,
LAWSON-FISHER ASSOCIATES P.C.
Paul A. Hummel, PE Jared M. Huss, PE
President / Construction Director Business Development Director
Construction Team
The proposed LFA Team will be led by Ric Riemke, P.E., maintaining
continuity from the successful completion of Phase I of Coal Line Trail,
and will be bolstered by the addition of Randy Kilbase and Carter Vravis.
This Team has nearly 100 years of collective engineering and construction knowledge
and has significant Bridge Rehabilitation experience; making this group ideal to
manage the conversion of the rail bridge to a pedestrian facility. (See pages 2-4 for
Organizational Chart and supporting resumes.)
Capacity to Perform Work
With an anticipated September 2022 Letting Date, a September 1, 2023,
Intermediate Completion Date, and a May 1, 2024, NOT Completion
Date; LFA will focus its fullest attention on the critical path items to
meet contract goals. The LFA Team will target on-schedule adherence
by addressing potential schedule impacts such as long lead procurement items and
permitting time restrictions. This LFA team has depth and breadth of experiences
in bridge, trails, waterway permitting, ADA requirements and hard-scape features to
ensure this project’s success. (See pages 5 through 8 for the Project Understanding
& Approach.)
$$Cost Savings
LFA was selected for inspection of Phase II Coal Line Trail that was
subsequently split into two Phases to accommodate the current
bidding climate. Both Phases are to be completed in the 2023-24
construction seasons and can be managed, as previously planned, by
one inspection team. LFA proposes one team to lead both projects, thereby eliminating
the need for a second and separate inspection team to lead Phase IIB. This would
result in an appreciable savings for the City. (See pages 5 through 8 for our Project
Understanding and Project Approach.)
City of South Bend | CE Services for Coal Line Trail Phase IIB (Des # 2200199) in the LaPorte District | Page 2LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
ORGANIZATION
Percentage
of Work
13.1
Construction Inspection
LFA 97%
ME* 3%
Solicited Services Prime Support * DBE
*Disadvantaged Business Enterprise (DBE)
Paul Hummel, PE
QC/QA and Client Liaison
Jon "Ric" Riemke, PE
Project Supervisor/Engineer
INDOT
Steve Hauersperger, PE
Area Engineer
City of South Bend
Finnian Cavanaugh, EI
Project Manager
Why the LFA Team?
Ric Riemke will be leading the LFA Team as the project engineer/supervisor throughout the entirety of the project. LFA's recent experience on Phase I of the project provided
us valuable insights we will apply to subsequent phases of this project to exceed the City of South Bend expectations. Further, the LFA Team's specific project experience on
multi-use paths, ADA requirements and bridge reconstruction projects will be critical to this project’s success. Recent specific examples of LFA’s experience with the City of South
Bend and multi-use path projects include the on-going Coal Line Trail — (Phase 1) Project, Olive & Sample Reconstruction Project, the Bendix Drive Road Reconstruction, and
LaSalle Trail. Having the Team Capacity, Work Type Experience and Team Availability makes the LFA Team the right choice for this project.
LFA Staff Yrs. Exp.
Randy Kilbase 33
Carter Vravis 32
Mike Wuszke 2
Project Partners Yrs. Exp.
Tracy McCormick (ME)26
Team Capacity
With an Intermediate Contract Completion Date of
September 1, 2023, this project will require specific
attention to waterway permitting restrictions, material
availability and shop-drawing review elements having
direct schedule impacts.
Having an available experienced team provides Ric
the opportunity to focus on driving critical schedule
items, thus resulting in a project that is completed
on schedule and in accordance with contract
documents.
Work Type Experience
In addition to managing Phase I of Coal Line Trail,
please note additional experience the LFA Team
possess in each of its major project elements. This
experience will ultimately provide required insight
to supervise and inspect each major element while
identifying potential time and cost saving measures
as the project progresses. Specific experience
in bridge reconstruction, waterway permitting,
utility relocation, drainage, ADA requirements and
architectural features will be critical.
Team Availability
The LFA Team is already prepared to be on-site for
Phase IIA of the project. We will ensure that the LFA
Team will be dedicated to the project upon selection.
Ensuring Ric's availability also provides consistency
of staff involved for project continuity across Phases
I, IIA and IIB.
This consistency will be critical to maintaining the
project schedule, managing two contractors in close
proximity and working to ensure opening prior to
Notre Dame Football season.
Paul and Ric’s Involvement:
Resolution Assistance
As Needed Progress Meeting Attendance
Schedule Oversight
City of South Bend | CE Services for Coal Line Trail Phase IIB (Des # 2200199) in the LaPorte District | Page 3LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
PROJECT SUPERVISOR
Certifications
Bituminous Paving
Bridge Construction/Deck Repair
Concrete Paving
Traffic, Miscellaneous Concrete, and Miscellaneous
Construction Items
Construction Layout/Measurement and Pipe
Structures
Construction Earthwork
INDOT PE/PS Training
Competent Trenching & Excavation
INDOT Storm Water Certification
Construction Project Types
Roadway Construction/Reconstruction/Resurfacing/
Roundabouts
Concrete Pavement Restoration
Sanitary/Storm Sewers/Watermain
Traffic Signals
Utility Relocations
Intersection Improvements
ADA and Curb Ramp Reconstruction
Past Project Experience
Coal Line Trail (Phase I) — South Bend
Shared Use Path — CR 8 — Elkhart County
North Oakland Avenue, Nappanee
Boston/Larson Street, LaPorte
SR 23 over Koontz Lake Dam, Road and Bridge
Reconstruction, INDOT and DNR
Old Darden Road Bridge over St. Joseph River — St.
Joseph County
Edison and Ash Road Roundabout — St. Joseph
County
County Bridge 12 over Geyer Ditch — St. Joseph
County
LaSalle Trail (Phase I) — St. Joseph County
Hospice Site Infrastructure, Mishawaka
US 30 over Hunsley Ditch — INDOT
Ric’s Focus for the Success of
This Project:
Monitoring construction sequencing and utility
coordination progress.
Oversee Waterway Permitting Requirements
Ensuring compliance to ADA requirements.
Intentional and consistent communication with
project partners and impacted residents.
Jon "Ric" Riemke, PE
Senior Construction Engineer
Ric’s areas of experience and knowledge
include:
LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
LFA and Ric Riemke have significant knowledge
coordinating work with LPA Projects involving
trails and bridges and will apply this experience
to the success of the City of South Bend's project.
Jon "Ric" Riemke, PE will be the Senior
Construction Engineer for this
Construction Inspection project.
With over 32 years of experience in the
engineering construction industry, Ric has been involved
in numerous multi-use paths, road rehabilitation projects
involving turn lanes with traffic signals, and various
roadway construction projects requiring extensive
utility relocations. Ric has supervised projects of various
sizes and types and is certified in all INDOT testing
requirements. He has managed multiple local and state
funded projects.
Ric’s experience in various multi-use path projects, will
be critical to the success of Phase IIB of the Coal Line
Trail project.
Relevant Trail Experience:
Coal Line Trail (Phase I) — South Bend
LaSalle Trail (Phase I) from Cleveland Road to
Darden Road — St. Joseph County, Indiana
CR 8 Shared Use Path — Elkhart,Indiana
North Oakland Avenue — Nappanee, Indiana
Coal Line Trail (Phase I)LaSalle Trail
North Oakland AvenueCR 8 Shared Use Path
South Bend | CE Services for Coal Line Trail Phase IIB (Des # 2200199) in the LaPorte District | Page 4LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
KEY STAFF
Certifications
Professional Engineer — Indiana 19800331
INDOT SiteManager Certificate of Proficiency
INDOT Certified Technician
INDOT Construction Storm Water Certification
Construction Project Types
Hydrologic & Hydraulic Calculations
Grading Plans
Earthwork Calculations
Site Development
Storm Sewer Design
Concrete Testing
Construction Observation for INDOT & LPA Projects
Field Testing
Tracy McCormick
Construction Inspector
Certifications
BSCE Valparaiso University (CTP Exempt)
Construction Project Types
Watermain Installation
HMA Paving
Storm Sewer Installation
Concrete Testing and Observation
Concrete Curb/Sidewalks/Approaches
Water Main
Lighting
Past Project Experience
Ada Street and Filbert Street Reconstruction — New
Carlisle
Helen Delorenzo Road Reconstruction — Mishawaka
Cedar Street Reconstruction — Mishawaka
Mike Wuszke, E.I.
Construction Inspector
LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
Randy has significant experience in bridge reconstruction
and rehabilitation projects on US and State Routes with
significant traffic volumes. He will use this experience to
help inspect the critical elements for rehabilitating the
rail bridge to a pedestrian facility.
Certifications:
INDOT PE/PS Training
INDOT Certified Technician Program
INDOT SiteManager Certified
Confined Space Entry
IDEM/NIRPC Stormwater Technical Training —
Construction and Erosion Sediment Control
NASSCO Cured-In-Place Pipe Inspector Training
and Certification
Construction Project Types:
Roadway Construction/Reconstruction/Resurfacing
Bridge Construction/Rehabilitation/Overlays
HMA Pavement and Resurfacing
Concrete Pavement Restoration
Past Project Experience
SR 933 Over St. Joseph River — Bridge Deck
Overlay (B-36679)
SR 23 Over St. Joseph River — Bridge Replacement
and Beam Painting (B-36679)
St. Joseph County Resurfacing, Various Locations
Through County, HMA (SR-32453)
US 31 Tie-In South Bend — New Roadway and
Bridges (IR-30132)
US 31 over Yellow River & Elmer Seltenright Ditch —
Testing for Bridge Replacements (IR-30143)
US 31 from I-80 (Toll Road) to Michigan State Line/
Brick Road over US 31 — Road Replacement (R-
41975)
Randy Kilbase
Senior Construction Inspector
LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
McCormick Engineering, LLC, is a
certified Indiana WBE and DBE. The
firm was created to service the public
through civil engineering planning
and design.
They are committed to understanding
the needs of each project and are able
to define project success by their ability
to meet the goals and objectives of the
client. Based on these objectives, ME
will be an asset to the success of your
project.
Carter Vravis
Project Supervisor/Highway
Technician
LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
Certifications
INDOT PE/PS Training
INDOT Certified Technician Program
INDOT SiteManager Certified
PCCP/HMA Field Supervisor
Concrete Paving and Restoration
Past Project Experience
INDOT Contract B-41865 Bridge
INDOT Contract R-41432 Small Structure Replacement *
INDOT Contract B-41543 Bridge Rehabilitation*
INDOT Contract R-30867 Traffic Signals, Resurface and
Pavement Rehabilitation*
INDOT Contract T-33899 ITS Traveler Monitoring
Systems*
INDOT Contract T-34250 ITS Monitoring Systems*
INDOT Contract R-29729 Small Structure Replacement*
*Work completed at INDOT.
City of South Bend | CE Services for Coal Line Trail Phase IIB (Des # 2200199) in the LaPorte District | Page 5LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
PROJECT UNDERSTANDING
Trail Nodes and Continuity
This phase of the project will serve to connect Phase I of the Coal
Line Trail with Riverside Trail in addition to connecting Phase
IIA, which includes connectivity to the East Bank Trail and SR
933 Trail. LFA will focus on pedestrian MOT and construction
sequencing between construction of the Riverside Trail Node
and the bridge to reduce rework and limit impacts to existing
trail use. LFA will bring lessons forward from the Lawndale and
Vasser Trail node to ensure continuity between phases.
Architectural Features
Similar to Phase 1 and Phase IIA, this Phase has
various features to enhance user experience.
Several items have been procured in advance
during Phase 1. This is important as the
construction industry continues to see material
shortages and backorder delays.
The remaining features such as the bike repair
station, drinking fountain and lighting will need to
be ordered as soon as the contractor is provided
Notice to Proceed. LFA will also focus on
coordination regarding bolt patterns, foundation
locations, water service connections and site
preparation work to ensure proper installation of
these features.
Bridge Rehabilitation
A major component of the project is the
rehabilitation and transition of the existing
bridge from a rail bridge to a pedestrian facility.
To accomplish the improvements the contract
calls for superstructure and substructure repairs
as well as scour protection at the piers and end
bents. These work items include rehabilitating
the existing steel and concrete, improving
concrete beam seats and concrete approaches,
installation of new bearings and installation
of a 14' Concrete deck with decorative rails
and recessed lighting. LFA will also focus on
permitting requirements during the cleaning,
painting and scour protection activities.
Coal Line Trail — (Phase IIB)
This is the final section of the Coal Line Trail project that connects the west side with multiple neighborhoods and trails throughout the City and provides greater connectivity for
the residents of South Bend. The project is scheduled to let in September 2022 along with Phase IIA and has an intermediate completion date of September 1, 2023, which has
been set to complete construction in advance of Notre Dame Football season. Through a meeting with Project Manager Finnan Cavanaugh, E.I. on August 8th, and a subsequent
site visit, the following items below are areas of focus to deliver a successful project on behalf of the City of South Bend.
PHASE IIB
PHASE IIA
City of South Bend | CE Services for Coal Line Trail Phase IIB (Des # 2200199) in the LaPorte District | Page 6LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
Bridge Scour Protection
Class I Riprap will be placed at each pier. Outside piers will
require cofferdams as excavation will be required to achieve
placement of geotextile and desired depth of Rip-Rap
placement. In advance of riprap placement LFA will ensure the
contractor will remove debris along the piers and remove the
18" tree on the east shoreline. Precaution should be taken to
protect the 30" Sycamore tree, also on the east shoreline.
LFA will coordinate with the Contractor and City to address
access for placement of riprap and cofferdams. It is anticipated
that staging will occur near the proposed Riverside Trail Node.
Waterway Permitting
Tree removals and placement of materials (coffer dam and
riprap) in the St. Joseph River will require adherence to time
restrictions and permits conditions.
LFA is well versed in IDNR Construction in a Floodway, IDEM
401 and Army Corp 404 permits and associated restrictions.
Our inspectors can rely on our in-office staff should questions
or additional contractor permitting needs arise. These permit
requirements will be added to the Pre-Construction Meeting
Agenda to ensure they don't negatively impact project
schedule.
PROJECT UNDERSTANDING
Bridge Rehabilitation Elements
Abutment, End Bent and Pier Beam Seat Restoration:
Coordinate Review of Beam Jacking and Supports
Inspect remaining concrete post removals for required repairs (pneumatically placed mortar)
Prep and Install new beam seats — Ensure Final Plan Elevations for Bearing
Installation of Structural Steel Clean, Repair and Paint:
Review Permitting/Containment Requirements and Coordinate Review of Plan
Inspect Cleaned Surface and Identify/Execute Required Repairs (Pack Rust and Web Section Loss)
Test Paint Thickness and Regularly Inspect Containment System for Permit Compliance
Framing and Concrete Deck with Bridge Railing:
Coordinate Review of Construction Plan for Live Loading Limits
Check Screed and Clearance for Concrete Finishing Machine
Review conduit riser locations for Lighting Base Plates against proposed rail spacing for proper alignment.
Bridge Rehabilitation and Scour Protection
Work on the bridge includes both superstructure and substructure repairs as well as the addition of new bearings on reconstructed seats, improved abutments, 14-foot concrete
deck, decorative railings, and rail-recessed lighting. Additional improvements include sandblasting and painting the existing steel bridge members as well as placement of
rip-rap at each pier for scour protection. LFA anticipates coordinating construction loading, waterway permitting, river access and ensuring proper site security measures as
described below:
Site Security and Access
Providing a safe and secure site
during construction will be vitally
important as bridge work
progresses. LFA will work with
the Contractor to ensure
appropriate fencing and security
checks are a daily activity.
Similarly, access and staging will need to be
coordinated at both Riverside Drive and Northshore
Drive as bridge materials and construction activity
require. Having LFA as the inspector on both Phase
IIA and IIB will allow us to coordinate between both
contractors to achieve proper communication for
project success.
City of South Bend | CE Services for Coal Line Trail Phase IIB (Des # 2200199) in the LaPorte District | Page 7LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
PROJECT UNDERSTANDING
Trail Nodes and Access
Northshore Trail Crossing
This node is being constructed during Phase IIA but will require coordination
with the contractor for Phase IIB. This coordination will likely include MOT,
concrete path tie-in points, lighting conduit connections, pedestrian railing
and ADA grading.
Northshore
Riverside Trail Node
This node serves to connect the Riverside Trail and Phase 1 of Coal Line
Trail to this second phase. Here, LFA will focus on inspecting decorative
concrete patterns, placement of foundations for the pre-cast pavilion,
wayfinding sign foundations, water service connection for the drinking
fountain, and bolt patterns/foundations for lighting, benches, trash
receptacles and bollards. Pedestrian MOT is critical at this node as
Riverside Drive and Angela Boulevard are busy corridors. Ensuring clear signage for safe
pedestrian crossings will be paramount.
Riverside
Architectural Features
Architectural features on the project are shown in the diagram below. While
some items are already procured; the remaining items have recently incurred
long lead times, making early shop drawing review imperative to the project
schedule. Also critical is ensuring bolt patterns for the foundations of these
various features procured so that the contractor can proceed with construction
while waiting for the manufacturing and delivery process. Both items will be
emphasized during the Pre-Construction Meeting and will remain focal points
on progress meetings until completion.
Pre-Cast
Pavilion
Benches
and Trash
Receptacles
Decorative
Concrete
All features with the exception of
the Bike Repair Station/Rack, Drinking
Fountain, Limestone Seatwall, Bridge/Path
Lighting and Decorative Concrete are previously
procured materials being stored at Rum Village
and High Street location. We will focus efforts
on Shop Drawing review on the listed
items for procurement.
Limestone
Seatwall Bridge/Path
Lighting
Bike Rack & Repair Station
Bollard and
Swing Gate
Drinking
Fountain
and Dry Well
Wayfinding
Signage
Pedestrian MOT
Riverside Trail is a heavily used trail within the City's trail network. Maintaining
proper detour signage during construction will be an important aspect of
resident satisfaction and maintaining a safe project. LFA will check these
detour signs daily.
ADA Compliance
As a pedestrian facility, adhering to ADA requirements is a crucial component
of the project. LFA worked with the contractor on Phase I to ensure grading
at trail nodes, crossings and other critical areas were met. We will maintain
the same focus during this phase of the project.
Drinking Fountain & Electric Service Point
Similar to Phase I, a drinking fountain is planned for Riverside Trail Node.
Coordination with South Water will be required for service and connections.
Additionally, coordination will be required between Phase IIA and IIB as the
TESCO Service Point on Phase IIA will power the lights on Phase IIB.
Contractor Continuity
LFA will make certain the contractor submits concrete jointing plans, which
will ensure that jointing at each node is consistent between the Phases I, IIA
and IIB of the project.
City of South Bend | CE Services for Coal Line Trail Phase IIB (Des # 2200199) in the LaPorte District | Page 8LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
PROJECT APPROACH
Communication
LFA’s goal is to keep City of South Bend Public Works
staff well informed of project progress through biweekly
Progress Meetings. An example of the items to be
covered at the progress meeting can be seen adjacent to
this paragraph. LFA would propose combining progress
meetings for both Phase IIA and IIB so that directives
can be clearly communicated to both contractors,
which will ensure continuity and allow for increased
communication between phases.
However, communication is not limited to the owner
nor to the bi-weekly time frame. LFA has found creating
a Log of Resident Concerns serves to not only keep
a timeline of issues and concerns but also allows for
timely responses, resulting in more satisfied residents
and businesses. Finnian Cavanaugh, E.I., City of South
Bend’s Project Manager, will be updated regularly as to
the status of all construction activities.
Also critical is to ensure Change Orders, Pay Applications
and any P.O. requests be discussed in advance with
the City, INDOT and Contractor so there is a clear
understanding of impact to funding and schedule.
Proactive Project Inspection
We challenge our staff to be problem solvers, to look
forward anticipating and identifying potential issues.
Individual members of LFA’s construction inspection
team can draw upon the collective experience of our
entire inspection team should issues arise requiring
specialized attention.
Our experience allows us to identify issues early, enabling
multiple possible solutions to be explored with the most
fitting being presented to City staff for consideration and
evaluation. This cross-sharing of experience provides
a proactive approach to resolving construction issues
resulting in savings of both time and expense.
Cost Savings And Containment
Two Projects — One Team
$$As mentioned previously, we see
significant cost savings for the City by
utilizing one inspection team for both
Phases IIA and IIB. Doing so allows for
more than the obvious inspection contract cost savings;
it also reduces the number of required coordination
points for the City and Contractors; which ultimately is
a savings in time and reduction in potential
communication gaps.
As demonstrated in the previous pages of the Letter
of Interest this project will rely heavily on previous
experience in the areas of bridge rehabilitation,
ADA requirements, waterway permitting, contractor
coordination, and installation of architectural features.
Having experience in these above identified areas
through past projects and the recent Phase I Coal Line
Trail Project allows LFA to employ the proactive project
inspection techniques that have often resulted in cost
savings to the client on the constructed project and the
inspection budget.
An example of this approach resulting in a successful
project is the Olive Street & Sample Street Overpass
Project that resulted in a savings of $400,000 in
construction costs while using just approximately 85%
of the construction inspection fee.
Finishing Strong
As Phase 1 of the Coal Line Trail nears completion, LFA
will submit the Final Construction Record within two
weeks of the Final Project Walk-Through; far ahead of
the 45-day requirement set by INDOT. LFA is ready to
serve the City of South Bend on this important quality of
life and mobility project.
Bi-Weekly Progress Meeting Agenda
Appropriate Attendees — Contractor,
Subcontractors, City of South Bend, INDOT, LFA,
Utilities, and Designer (if needed)
Review of Construction Progress-to-Date
Scheduled Work for Upcoming Period
Overall Schedule Review
Seeding, Sodding Dates, Tree Removal Dates
Delays
Permitting Status and Requirements
Change Orders
City of South Bend Concerns
Material Certifications/Testing
Submittals/Shop Drawings
Benches, Ballards, Lighting, Shelter, etc.
Failed Materials
Maintenance of Traffic
Safety
Site Security
Utility — Service Point and AEP
Public Relations (Municipal Concerns, Resident
Issues, Public Communication)
Contractor Issues
Inspection Team Issues
Ongoing Communication
Material Submittals and Shop Drawings
Schools, Resident and Business Concerns Log
Discuss Changes to (MOT) and Notifications —
Provide Proper Notifications
Upcoming Work/Progress-to-Date/Outstanding
Issues
Site Security and Staging
Erosion Control and Environmental/Waterway
Permit Requirements and Status
Weekly Email Updates to Finnian Cavanaugh on
Progress and Contract Status
South Bend | CE Services for Coal Line Trail Phase IIB (Des # 2200199) in the LaPorte District | Page 9LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
RELEVANT EXPERIENCE
This project was for the rehabilitation of twin structures on US 30. The work was completed
in two phases with two-way traffic on either structure via crossovers while work was
completed on the structures. At the beginning of Phase I, Construction Memorandums
15-07 and 15-09 where issued. These Memorandums pertained to the temporary concrete
barrier, Type 2, Anchored needed to meet NCHRP 350 or MASH crash testing. Since the
temporary concrete barrier was to be placed in existing earth median, it did not meet this
requirement.
LFA coordinated with INDOT, the contractor and the designer to implement the use of
temporary guardrail to replace the temporary concrete barrier, thus meeting the crash test
requirement and provide the same level of protection to the work site. The original contract
called for a large quantity of existing guardrail to be reset. After consulting with the designer,
LFA determined that the majority of the guardrail did not need to be reset resulting in a
savings to the contract of $26,000. The plans did not show an existing Indiana Department
of Transportation bench mark that was located on the existing westbound structure. LFA
coordinated with INDOT survey crew to have a new bench mark placed on the new
eastbound structure and establish new elevation. Construction began in May of 2015 and
traffic was returned to their normal lanes by the intermediate completion date in October of
2015. The final cost of the project was approximately 0.7 percent under the original contract
amount.
US 30 Bridges over Hunsley Ditch (B-33440)
Client: INDOT — LaPorte District
Cost: $1.83 million
Key Staff: Jon "Ric" Reimke, Paul Hummel
Project Manager: Jon Kruger
Coal Line Trail Phase I | from Lincoln Way West to Riverside Drive
(R-38064)
City of South Bend
Client: City of South Bend
Cost: $1.825 Million
Key Staff: Paul Hummel, Jon "Ric" Riemke
Project Manager: Kyle Silveus, PE
LFA provided construction inspection services for the Coal Line Trail Project Phase I. This
shared-use path connects the Lincolnway West corridor and surrounding neighborhoods
to the established Riverside Trail, with improved pedestrian safety and connectivity
to community assets such as schools and parks. Phase I construction included
approximately 4,000 linear feet of separated, shared-use path requiring roadway work,
intersection improvements, and significant grading near Portage Avenue. The entire trail,
Including curb ramps, at each intersection were constructed to ADA standards.
Wilber Street was reduced in overall pavement width to accommodate the trail
necessitating adjustments to the storm sewer network, overhead utilities, and intersection
improvements at Lincolnway West and VanBuren Street in advance of the old railroad
right-of-way. LFA’s construction team worked with Monarch Laundry, a laundering
business with facilities on both sides of Wilber Street, to maintain easy access for hand
carts to move freely across Wilber Street during the construction of curb, walk and drives.
Construction required closure of the intersection at Vassar and Lawndale for required
radius improvements, installation of curb ramps, storm sewer adjustments, and
additional concrete work for trail amenities. This intersection closure impacted Holy
Cross School (NE corner of Wilber/Vassar) with LFA’s Construction team coordinating
construction activities with the school including identification of the best detour routes
to minimize disruption to student drop-off and pick-up.
South Bend | CE Services for Coal Line Trail Phase IIB (Des # 2200199) in the LaPorte District | Page 10LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
RELEVANT EXPERIENCE
Leading a team of LFA, Lochmueller, and McCormick Engineering staff, Don
Dietz served as the Project Supervisor and provided
Construction Observation and Inspection services for
the Olive Street & Sample Street Overpass Intersection
Reconstruction Project. The project was a combined
effort between St. Joseph County and the City of South
Bend. This multi-jurisdictional and multi-construction
season project included bridge rehabilitation on both
Olive Street and Sample Street bridges over the Norfolk
Southern and Grand Trunk Western Railroad (Canadian
National), requiring significant coordination. Additional
work included reconstruction of 3,660 ft of Olive Street and 2,750 ft of Sample Street
to improve drainage, install lighting, and improve pedestrian movement. A roundabout
was also constructed at the intersection of Olive Street and Sample Street. Significant
effort was required to coordinate utility relocations for MetroNet, AEP, NIPSCO, and
Comcast. Additionally, LFA coordinated water utility work with the City of South Bend
during the street reconstruction and roundabout construction process. Beyond the
coordination challenges on the project, Don worked
with the County to determine a better temporary barrier
rail system on the bridge that resulted in less long term
maintenance concerns on the bridge deck. One of the
most critical items of this project was Maintenance of
Traffic and impacts on local residents, businesses, and
industry. Don proactively addressed these concerns
through direct contact with the impacted parties.
By actively engaging the contractor on work flow and
anticipated upcoming work, Don Dietz successfully managed the Olive Street &
Sample Street Overpass Intersection Reconstruction project which resulted in a
savings of $400,000 in construction costs while only utilizing 85% of the construction
inspection budget.
Olive Street & Sample Street Overpass Intersection Reconstruction (R-35727)
South Bend, Indiana
Client: St. Joseph County, Indiana
Cost: $10.6 million
Key Staff: Paul Hummel, Don Dietz, Darrell Baker
Project Manager: Andrew Hayes
Key Relevant Project Aspects
Road Reconstruction
Significant Utility Relocations
Significant Public Communication and
Coordination Efforts
Pedestrian MOT
South Bend | CE Services for Coal Line Trail Phase IIB (Des # 2200199) in the LaPorte District | Page 11LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
RELEVANT EXPERIENCE
The Diamond Avenue Reconstruction Project, Phase I consisted of a full reconstruction
of the Riverside Drive/Angela Boulevard Intersection. This project included full-depth
pavement replacement, new storm drainage, roundabout
installation, Conspan structure, retention basin and green
outfall treatments, manufactured stone retaining walls and
installation of a pedestrian/bike path near the Notre Dame
Campus. The pedestrian/bike path included features such
as handrails, architectural brick and pillar treatments, and
access ramps with specific signage. Field adjustments to the
drainage and path features enhanced the final product and
client satisfaction.
A challenging feature of the project included a highly active adjacent neighborhood which,
during Notre Dame home games, experiences elevated levels of traffic. The use of Google
Documents software and public daily blogs allowed the project supervisor to provide
real-time project updates to the public including access and maintenance of traffic issues.
Additionally, it allowed the City of South Bend to track quantities, change orders, budget and
overall project status in real time. LFA was heavily involved in coordinating the Maintenance
of Traffic set-up for the construction area for home game weekends. This coordination
included interaction and planning with the South Bend Police Department, Engineering,
and the general public. Utilizing the Internet-based application allowed LFA to effectively
communicate with the general public during these high-traffic time periods.
Diamond Avenue
City of South Bend, Indiana
Client: City of South Bend
Cost: $3.1 million
Key Staff: Paul Hummel, Don Dietz
Project Manager: Toy Villa
Lawson-Fisher Associates P.C. was selected by St. Joseph County to perform
construction inspection services for an extension of the LaSalle Trail multi-use path
between Cleveland Road and Darden Road. This section
of trail is approximately 1/2 mile in length, along a straight
and generally level section of an old railroad right-of-way
and includes crossings of both Cleveland Road and Juday
Creek. The high volume of traffic along Cleveland Road
made an uncontrolled pedestrian and bicycle crossing
hazardous. The plans included a High intensity Activated
CrosswalK (HAWK) pedestrian crossing at this location.
The HAWK signal is pedestrian activated and coordinated
with the nearby traffic signal located at the intersection of
SR 933 and Cleveland Road. The curve on Cleveland road west of the crossing made
visibility of the HAWK signal difficult. During construction, LFA coordinated with St.
Joseph County and INDOT to add a flashing beacon at the beginning of the curve to
warn motorists of the upcoming activated HAWK signal. LFA performed inspection of
the construction activities that included testing of subgrade, portland cement concrete
pavement and modular block retaining wall. The existing railroad bridge over Juday
Creek was utilized by rehabilitating the structure with new wooden decking and
handrails. LFA prepared and submitted the Final Construction Record at the end of
construction.
LaSalle Trail
St. Joseph County, Indiana
Client: St. Joseph County
Cost: $441,000
Key Staff: Paul Hummel, Jon "Ric" Riemke
Project Manager: Jessica Clark, PE
Key Relevant Project Aspects
Multi-Use Path Construction
Significant Utility Relocations
Significant Client and Public Communication
and Coordination Efforts
Road Reconstruction
South Bend | CE Services for Coal Line Trail Phase IIB (Des # 2200199) in the LaPorte District | Page 12LAWSON-FISHER ASSOCIATES LAWSON-FISHER ASSOCIATES P.C.P.C.
RELEVANT EXPERIENCE
This project was for the construction of approximately 1/2 mile of a new shared path
along CR 17 and CR 10/8. LFA provided construction services and worked closely
with the Elkhart County Engineering Department who provided onsite inspection.
The path was built over an existing tributary to the St. Joseph River. In the area of
the tributary, approximately 675 ft of peat needed to be excavated along the path.
After the peat was removed the contractor placed and
compacted into the soft soil (marl) No. 2 stone. This
operation continued until the stone could no longer
be pushed into the soil. Prior to, during and after the
placement of the stone a Geotechnical Engineer from
INDOT’s list of approved firms visited the site to provide
guidance and recommendations. LFA coordinated
with the Geotechnical Engineer and implemented the
recommendations. At the end of the operations the Geotechnical Engineer approved
the subgrade and the remaining pavement section was constructed which consisted
of geotextile over the stone, approximately 1/2 ft of "B" Borrow and 1 ft of No. 53
stone for the base of the asphalt path. The contract quantity of the No. 2 stone was
not needed to obtain the approved subgrade to begin construction, this resulted in
a savings to the contract of approximately $21,000. In this area LFA also ensured the
contractor placed and maintained appropriate erosion control measures to prevent
sediment from entering the waterway. The project was completed on time and was
approximately 11 percent under the original contract amount.
CR 8 Shared Use Path (R-34337)
Elkhart, Indiana
Client: Elkhart County, Indiana
Cost: $315,750
Key Staff: Jared Huss, Jon "Ric" Riemke
Project Manager: Tom Rushlow, PE
LFA provided construction inspection services for the Boston Street/Larson Street and
SR 2 Intersection reconstruction project in LaPorte. This intersection improvement project
included HMA pavement replacement, significant utility relocations (NIPSCO, Verizon,
Comcast), multiple Maintenance of Traffic Phases, new storm sewer construction, water main
relocation, modular block wall construction, installation and maintenance of erosion control
measures. and traffic signal installation. Project improvements
required the demolition of two houses and one business. LFA
ensured the contractor secured the proper IDEM permits
and disposed of abandoned underground storage tanks in
accordance with State and Federal regulations. LFA also
ensured the contractor coordinated with the Norfolk Southern
Railroad during the jack and bore of a 60-inch steel casing
pipe under their tracks for the proposed 36-inch storm sewer.
LFA coordinated with the City, local residents and businesses to ensure that access was
provided to their properties during construction. LFA was able to coordinate with the City and
one business, which was impacted the most by the construction, to revise the maintenance
of traffic plan to accommodate their delivery trucks which cut approximately one month off
the completion date for the project.
LFA provided complete construction inspection services in accordance with INDOT criteria
and played a key role in all on-going construction engineering decisions. Construction
documentation was completed using INDOT’s SiteManager software.
.
Boston/Larson Street Reconstruction and SR 2 Intersection
LaPorte, Indiana | (R-29578)
Client: City of LaPorte, Indiana
Cost: $1.1 million
Key Staff: Paul Hummel, Jon "Ric" Riemke, Darrell Baker
Project Manager: Dale Clingerman, PE
Key Relevant Project Aspects
Significant Utility Coordination Efforts
Multi-Lane Road Reconstruction with Multi-Use
Path
Pedestrian and Vehicular MOT
Page 1 of 1
Request for Proposals Bulletin: City of South Bend, Indiana -
CE Services for Coal Line Trail
Phase IIB (Des. No. 2200199) in the
LaPorte District
AFFIRMATIVE ACTION CERTIFICATION
I do hereby certify that my company intends to affirmatively seek out and consider Disadvantaged Business
Enterprises (DBEs) certified in the State of Indiana to participate as part of this proposal. I acknowledge that this
certifications to be made an integral part of this proposal. I understand and agree that the submission of a blank
certification may cause the proposal to be rejected. I certify that I have consulted the following DBE website to
confirm that the firms listed below are currently certified DBEs:
https://financial.gmis.in.gov/psc/guest/EMPLOYEE/ERP/c/SOL_APPS_MWBE.SOI_DBE-CERT.GLD?&
I certified that I have contacted the certified DBEs listed below, and if my company becomes the CONSULTANT,
these DBEs have tentatively agreed to perform the services as indicated.
I understand that neither my company nor I will be penalized for DBE utilization that exceeds the goal. After contract
award, any change to the firms listed in this Affirmative Action Certification to be applied toward the DBE goal must
have prior approval by INDOT’s Economic Opportunity Division.
SUBCONSULTANTS
DBE SUBCONSULTANTS TO BE APPLIED TOWARD GOAL
Certified DBE Name Service Planned Estimated Percentage to be Paid to
DBE*
McCormick Engineering, LLC 13.1 3%
DBE SUBCONSULTANTS TO BE USED BEYOND GOAL
Certified DBE Name Service Planned Estimated Percentage to be Paid to
DBE*
Total Percentage Credited toward DBE Goal: 3 %
DBE Total Percentage of Voluntary DBE Work Anticipated over DBE Goal: 0 %
Name of Company: Lawson-Fisher Associates P.C.
By: Date: August 23, 2022
Paul A. Hummel, P.E., President/Senior Civil Engineer
*It is understood that these individual firm percentages and dollar amounts are estimates only and that amounts paid
may be greater or less as a result of negotiation of the contract scope of work. My firm will use good fa ith efforts
to meet the overall DBE goal through the use of these or other certified and approved DBE firms.
Indiana DBE Certification Program
In accordance with 49 CFR Part 26 as published in the code of federal regulations, the Indiana
Department of Transportation acknowledges
Elizabeth Kiefner Crawford, Director
Economic Opportunity Division
Derrick Casson, Certification Manager
Economic Opportunity Division
(Reference the Indiana Department of Transportation's DBE Public Search at
http://www.in.gov/2674.htm for the most current information regarding this certification)
as a certfied DBE in the State of Indiana.
Date Issued:01/26/2017 No Change Affidavit Due:12/31/2022
McCormick Engineering, LLC