HomeMy WebLinkAboutChange Order No 1 & PCA - 2021 Drainage Improvements-Kaley St. & Marion St. Proj No. 121-006A - Selge
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
August 9, 2022
Mr. Robert Kuhns
Selge Construction Co., Inc.
2833 South 11TH St.
Niles, MI 49120
aswinehart@selgeconstruction.com
RE: Change Order No. 1 (Final)/Project Completion Affidavit
2021 Drainage Improvements - Kaley St. & Marion St. – Project No. 121-006A
Dear Mr. Kuhns:
At its August 9, 2022 meeting, the Board of Public Works approved the Final Change
Order for this project, be decreased by $6,193.92. The final contract amount is $246,810.33.
In addition, the Project Completion Affidavit for this project was approved in the amount
of $246,810.33. Copies of the Change Order and Project Completion Affidavit are enclosed for
your records.