HomeMy WebLinkAboutChange Order No 3 - WWTP Final Clarifiers 4-5, Aeration Tanks 1-4, & Disinfection Improvements Proj No. 119-069A - Bowen Engineering
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
July 26, 2022
Mr. John Dettman
Bowen Engineering Corporation
8802 N. Meridian St.
Indianapolis, IN 46260
Johnd@BowenEngineering.com
RE: Change Order No. 3 – Wastewater Treatment Plant Final Clarifiers 4-5, Aeration Tanks
1-4, and Disinfection Improvements – Project No. 119-069A
Dear Mr. Dettman:
At its July 26, 2022 meeting, the Board of Public Works approved the above referenced
Change Order be decreased by $68,781.27 with an additional one hundred (100) days, bringing
the revised contract amount to $4,475,585.23 with a new completion date of August 25, 2022.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE: 07-13-2022
PROJECT NO: 119-069A
PROJECT NAME: WWTP Final Clarifiers 4-5, Aeration Tanks 1-4, and Disinfection
Improvements
CONTRACT DATE: 11/13/2020 Notice to Proceed
CHANGE ORDER NO. 003
SUBJECT OF CHANGE ORDER: Scope of Work Changes and Credits including sludge removal,
electrical, instrumentation, pipe repairs, integration, contract
unit price quantity adjustments. See details.
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns.
The original contract sum $ 4,272,999.00
Net change by previously authorized change orders $ 133,804.96
The contract sum prior to this change order $ 4,406,803.96
By this Change Order, the project amount is Increased
Decreased $ 68,781.27
The new contract sum including this change order $ 4,475,585.23
This Change Order represents a total change of 1.61 %
Total change for entire project 4.74 %
Original contracted completion date/time 05/17/2022
Extension of date/time by previous change orders 0 days
Date/time extension by this change order 100 days (due to manufacturer delays)
New completion date/time 08/25/2022
RECOMMENDED FOR APPROVAL
CONTRACTOR Construction Manager
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Date: Contractor Signature
Printed Name and Title
Bowen Engineering Corporation
President
Company name
8802 North Meridian Street
Member
Address
Indianapolis, IN 46260
Member
City, State, Zip Member
Member
Pat Stanford, Project Manager
07-18-2022
July 26, 2022
Page 1 of 2
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
April 18, 2021
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project # 15-21-008
RE: RFQ-014 – Backside Aeration Sludge Removal
Dear Mr. Burroughs:
Bowen Engineering Corporation (BEC) is pleased to provide you with the following change request to remove
the sludge and grit from the entire backside aeration influent channel. This pricing includes haul off of 261,381
gallons of biosolids. This pricing is inclusive of all Subcontractor, Labor, Equipment, and Materials to complete
the work as outlined in the RFQ.
Labor/Equipment: $6,646.00
Material: $0
Subcontractor: $57,365.56
Markup on Additional: $3,865.18
Bonds/Insurance: $746.64
Allowance: $15,000.00
Total Additional Cost: $53,623.3 8
Fifty Three Thousand Six Hundred Twenty-Three Dollars and Thirty-Eight Cents
Clarifications/Scope of Work
- Price includes haul off of 261,381 gallons of biosolids
- Upon completion of project South Bend will receive certificate of disposal verifying proof of legal
disposal
- Plant supplied reuse water will be provided to BEC at no cost
- Biosolids will be pushed with a skid steer towards the pump in the channel
We look forward to the opportunity to review this proposal with you. If you have any questions regarding this
Page 1 of 1
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
April 18, 2021
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project # 15-21-008
RE: RFQ-017 – Aeration Pod Modifications
Dear Mr. Burroughs:
Bowen Engineering Corporation (BEC) is pleased to provide you with the following change request to remove
modify the Aeration pods. All work was tracked as T&M.
Labor/Equipment: $4,183.00
Material: $0
Subcontractor: $0
Markup: $626.00
Bonds/Insurance: $42.00
Total Additional Cost: $ 4,851 .00
We look forward to the opportunity to review this proposal with you. If you have any questions regarding this
proposal, feel free to contact me at 317-518-9721.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
Page 1 of 3
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
April 18, 2021
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project # 15-21-008
RE: RFQ-018 – Electrical CL Modifications
Dear Mr. Burroughs:
Bowen Engineering Corporation (BEC) is pleased to provide you with the following change request for the
electrical CL Modifications. All work was tracked as T&M.
24 +/- Additional Digital/Analog Points
Labor/Equipment: $0
Material: $11,426.00
Subcontractor: $13,300.00
Markup: $2,534.10
Bonds/Insurance: $0
Total Additional Cost: $27,26 0 .1 0
Conduit/Wire for the 24 Volt Signal from PLC 104 to Start Scrubber
Labor/Equipment: $0
Material: $1,032.00
Subcontractor: $1,320.00
Markup: $365.00
Bonds/Insurance: $0
Total Additional Cost: $2,717 .00
Work to Control Interior Louver, WME Said Not In Their Scope, Had to Tie in
a Relay in the Scrubber Control Panel
Labor/Equipment: $0
Material: $53.00
Subcontractor: $440.00
Markup: $50.90
Bonds/Insurance: $0
Total Additional Cost: $543.90
Page 2 of 3
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
Time and Work Related to the Halogen Panels Needing 24 Volts
Labor/Equipment: $0
Material: $0
Subcontractor: $880.00
Markup: $90.20
Bonds/Insurance: $0
Total Additional Cost: $970.2 0
LCP 104 Panel Modifications to Extend 24 Volt to Internal Terminal Blocks
Labor/Equipment: $0
Material: $100.00
Subcontractor: $880.00
Markup: $100.45
Bonds/Insurance: $0
Total Additional Cost: $1,080 .45
Install Wire in Existing Conduit to Create a Signal that Scrubber is Running if
in the Manual on Switch is Why it is Running
Labor/Equipment: $0
Material: $53.00
Subcontractor: $330.00
Markup: $39.10
Bonds/Insurance: $0
Total Additional Cost: $422.1 0
Conduit, Fittings, Wire, etc to Run 120 Volt Power to the Regulators from the
120/208 Volt Panel
Labor/Equipment: $0
Material: $1,382.00
Subcontractor: $1,760.00
Markup: $321.95
Bonds/Insurance: $0
Total Additional Cost: $3,463 .95
Relocate the Old Building Trouble Light and Horn to the Scrubber Panel
Labor/Equipment: $0
Material: $57.00
Subcontractor: $440.00
Markup: $51.10
Bonds/Insurance: $0
Total Additional Cost: $548.1 0
Page 3 of 3
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
Install a Push Button Switch from the Old 104 Panel on the New Panel,
Wire it to Reset the Actuator Closed Indication on the SCADA Screen
Labor/Equipment: $0
Material: $0
Subcontractor: $440.00
Markup: $45.10
Bonds/Insurance: $0
Total Additional Cost: $485.1 0
TOTAL COST OF CHANGE ORDER $37,490.90
We look forward to the opportunity to review this proposal with you. If you have any questions regarding this
proposal, feel free to contact me at 317-518-9721.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
Page 1 of 1
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
April 18, 2021
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project # 15-21-008
RE: RFQ-019 – CL Hanger Credit
Dear Mr. Burroughs:
Bowen Engineering Corporation (BEC) is pleased to provide you with the following change request for the
change in the CL hangers on the chlorine contact tank.
Labor/Equipment: $1,570.00
Material: $0
Subcontractor: $0
Markup: $0
Bonds/Insurance: $0
Total Reduced Cost: ( $1,5 70.00)
We look forward to the opportunity to review this proposal with you. If you have any questions regarding this
proposal, feel free to contact me at 317-518-9721.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
Page 1 of 1
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
April 18, 2021
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project # 15-21-008
RE: RFQ-022 – Emergency Pipe Repair
Dear Mr. Burroughs:
Bowen Engineering Corporation (BEC) is pleased to provide you with the following change request for the
emergency pipe repair. All work was tracked as T&M.
Labor/Equipment: $3,737.00
Material: $420.05
Subcontractor: $1875.00
Markup: $904.81
Bonds/Insurance: $0
Total Additional Cost: $ 6,936 .86
We look forward to the opportunity to review this proposal with you. If you have any questions regarding this
proposal, feel free to contact me at 317-518-9721.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
Page 1 of 1
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
April 18, 2021
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project # 15-21-008
RE: RFQ-023 – Chlorine O Ring Valve Exchange
Dear Mr. Burroughs:
Bowen Engineering Corporation (BEC) is pleased to provide you with the following change request to exchange
the o rings in the chlorine valves. All work was tracked as T&M.
Labor/Equipment: $425.72
Material: $1,418.00
Subcontractor: $0
Markup: $276.56
Bonds/Insurance: $0
Total Additional Cost: $ 2,120 .28
We look forward to the opportunity to review this proposal with you. If you have any questions regarding this
proposal, feel free to contact me at 317-518-9721.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
Page 1 of 1
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
April 18, 2021
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project # 15-21-008
RE: RFQ-024 – Temporary Chlorine Bypass Modifications
Dear Mr. Burroughs:
Bowen Engineering Corporation (BEC) is pleased to provide you with the following change request to modify
the temporary chlorine bypass piping. All work was tracked as T&M.
Labor/Equipment: $201.00
Material: $1,418.00
Subcontractor: $0
Markup: $242.85
Bonds/Insurance: $0
Total Additional Cost: $ 1,861 .85
We look forward to the opportunity to review this proposal with you. If you have any questions regarding this
proposal, feel free to contact me at 317-518-9721.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
Page 1 of 1
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
April 15, 2022
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project #15-21-008
RE: CR--025 – Electric Power Cost Allowance
Dear Mr. Burroughs:
Below is the summary of the Electric Power Allowance which resulted in a credit to the project.
Bid Amount Completed Difference
Utility Power Allowance $50,000.00 $42,472.00 ($7,528.00)
Total Project Credit: $7,528.00
Pl ease r evi ew and l et m e know i f yo u have any quest i on s.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
Page 1 of 1
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
April 15, 2022
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project #15-21-008
RE: CR--026 – System Integration Allowance
Dear Mr. Burroughs:
Below is the summary of the work performed under the System Integration Allowance. The work performed
exceeded the allotted allowance dollars
System Integration Allowance $158,950.00
Wunderlich-Malec Base Bid $156,975.00
LCP-104 Modifications $10,580.00
Scrubber Relays Modifications $5,865.00
Total Project Addition: $14,470.00
Pl ease r evi ew and l et m e know i f yo u have any quest i on s.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
Page 1 of 1
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
April 15, 2022
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project #15-21-008
RE: CR--027 – Unit Price Work Settle up
Dear Mr. Burroughs:
Below is the summary of the actual unit price work performed, the estimated bid quantities and the settle-up
which resulted in a credit to the project.
Bid Amount Completed Difference
Spall Repair $88,000.00 $2,420.00 ($85,580.00)
Crack Repair $6,600.00 $0.00 ($6,600.00)
Slab Repair $32,000.00 $90,240.00 $58,240.00
Anchor Repair $11,500.00 $23,900.00 $12,400.00
Railing Replacement $60,500.00 $53,790.00 ($6,710.00)
Slurry $57,750.00 $42,525.00 ($15,225.00)
Total Project Credit: $43,475.0 0
Pl ease r evi ew and l et m e know i f yo u have any quest i on s.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
Page 2 of 2
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
proposal, feel free to contact me at 317-518-9721.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 07-14-2022
Name: Jacob M. Klosinski Department of Public Works – Engineering Division
BPW Date: 07-26-2022 Phone Extension: 9496
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Clara McDaniels
Dept. Attorney Attorney Name Clara McDaniels
Purchasing Michael Schmidt
Check the Appropriate Item Type –Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 003 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Bowen Engineering Corporation (V-00000243)
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name
WWTP Final Clarifiers 4-5, Aeration Tanks 1-4, and Disinfection
Improvements
Project Number 119-069A (PROJ00000078)
Funding Source Venues, Parks and Arts - Services & Charges-Other-Misc Charges & Svcs
Account No. PO # PO-0005021 (642-06-605-514-442005; Sewage Works Capital)
Amount $68,781.27
Terms of Contract
Special Contract Provisions
Purpose/Description The Division of Engineering and Division of Utilities requests the Board of
Public Works approval of Change Order No. 3 for the subject project. Refer to
attached detail regarding changes in scope (increase) and adjustment of
quantities for unused unit price items (credits). Net Increase.
For Change Orders Only
Amount of
Increase
Decrease
$ 68,781.27
($ )
Previous Amount $ 4,406,803.96
Current Percent of Change:
Increase
Decrease
1.61%
(%)
New Amount $ 4,475,585.23
Total Percent of Change:
Increase
Decrease
4.74%
(%)
Time Extension Amount: 100 days (Due to Manufacturing and Materials Delays)
New Completion Date: 08-25-2022