Loading...
HomeMy WebLinkAboutChange Order Nos 4-7 & 9-15 - Coal Line Trail Proj No. 115-063 - INDOT & Selge Construction  ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER 1316 COUNTY-CITY BUILDING 227 W. JEFFERSON BOULEVARD SOUTH BEND, INDIANA 46601-1830 PHONE 574/ 235-9251 FAX 574/ 235-9171 CITY OF SOUTH BEND JAMES MUELLER, MAYOR BOARD OF PUBLIC WORKS July 12, 2022 Mr. Robert Kuhns Selge Construction Co., Inc. 2833 South 11TH St. Niles, MI 49120 aswinehart@selgeconstruction.com RE: Change Order Nos. 4-7 and 9-15 – Coal Line Trail, Phase I – (DES#1401810) Project No. 115-063 Dear Mr. Kuhns: At its July 12, 2022 meeting, the Board of Public Works approved the above referenced Change Orders to be increased by $68,665.95, bringing the revised contract amount to $68,665.95 with a new total contract amount of $1,871,262.80 and the amount to be paid by the City in an amount not to exceed $29,921.77. Enclosed is a copy of the Change Order for your records. If you have any further questions, please call this office at (574) 235-9251. Sincerely, /s/ Theresa Heffner Theresa Heffner, Clerk Enclosures TH/lh INTER-OFFICE MEMORANDUM DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING TO: Theresa Heffner, Clerk, Board of Public Works FROM: Finn Cavanaugh, Project Engineer SUBJECT: Project No. 115-063 Coal Line Trail – Phase I Change Orders 4-7,9-15 DATE: July 1, 2022 Attached are Change Orders 4, 5, 6, 7, 9, 10, 11, 12, 13, 14, and 15 for the Coal Line Trail Phase I project, INDOT DES#1401810. Change Order 4 Due to a design error, an outdated and incorrect special provision for the shade structures was included in the bid specifications. This was corrected after fabrication had begun, thus additional material and labor costs were required. This change results in an addition of $4,558.40 and is a participating item, meaning the City would pay 20% of this cost, $911.68. Change Order 5 In 2021 additional design work was done to revise the trail alignment to match with the original railroad, since at the time of original design the City had not acquired the full width of right-of- way. This design change necessitated an update to the Stormwater Quality Control Plan. Since the change of alignment was not part of the original contract, this change is non-participating and the cost to the City is $1,712.00. Change Order 6 Michiana Area Council of Governments (MACOG) as the MPO for this project, requested that pedestrian traffic counter loops be added to the project. These are also a participating line item with an overall additional cost of $2,810.70. The City’s 20% share of this cost is $562.14. Change Order 7 Due to the aforementioned change in alignment, the tree clearing subcontractor was required to stop work for a 4-month period, and resume clearing at a later time. As such the subcontractor incurred remobilization costs that the City is responsible for. This is a non-participating item and the cost to the City is $4,066.00. Change Order 9 This change order is for additional cost to replace traffic detector loops damage during milling of Wilber Street at the intersection of the Trail and Lincoln Way West. This is a participating line item with a total additional cost of $2,406.85. The City’s 20% share of this cost is $481.37. Change Order 10 Due to the aforementioned change in alignment, the contractor was required to do additional construction engineering to adjust to the new alignment. Since this change in alignment was not part of the original contract the change is non-participating and the cost to the City is $6,577.83. Change Order 11 Due to design error, the plans for inlet structures at the intersection of the Trail and Woodward Avenue called for incorrect castings that would not be flush with the pavement and curb. This change order is to replace the designed Type 7 “beehive” castings with Type 10 “curb box” castings. The change order is participating with a total cost of $2,006.26. The City’s 20% share of this is $401.25. Change Order 12 Due to design error, the fence between the trail and the parking lot of the Portage Plaza strip mall was directed to be removed but not replaced. The City deemed it a necessary safety measure to replace the fence, deterring vehicle traffic from entering the trail from the parking lot. The work is necessary for safety and is deemed participating, with a total cost of $14,178.00. The City’s 20% share of this is $2,835.60. Change Order 13 Due to design error, a 32” gap between the stairs and bridge structure at Portage Avenue was instructed to be filled with topsoil and seeding, which would be very difficult to maintain. The City and INDOT agreed to a proposed solution from the contractor that would fill the gap with decorative boulders held in place by a 5” layer of concrete, which would provide an aesthetic but non-attention grabbing infill at the stairs. The change order was not deemed part of the original scope of work by INDOT and is non-participating. The cost to the City is $7,879.90. Change Order 14 Due to design error, there was no item for HMA patching in the contract. HMA Patching was necessary along the boundary between the trail and the Portage Plaza parking lot, as well as around the raised crossing at Woodward Avenue. Since this work was necessary to complete the scope of the contract, this change is participating with a total cost of $22,470.00. The City’s 20% share of this is $4,494.00. Change Order 15 Change Orders 1, 2, and 3 were processed and approved by the Board of Public Works on November 23rd, 2021, in the total amount of $178,895.51. These change orders covered, respectively, a change of trail material from HMA to Concrete, change of service point type, and change to color temperature of luminaires along the trail. Per direction of the INDOT Area Engineer, the intention was for the City to pay 100% of the increase in cost for each new line item. However, the new (non-participating) items needed a separate purchase order to be paid for according to the correct cost-share. This change order corrects the amounts of cost share between the City and INDOT. This change order does not create a net change to the project and does not result in additional charge to the City. The total increase to the overall project cost for the above change orders is $68,665.95 (4.2%). The total additional cost to the City from these items is $29,921.77. The costs for all items have been found to be within typical unit prices for similar work and are thus recommended by Engineering. This project is being funded out of the TIF River West Development fund, with DFO project code PROJ-00000018. Engineering requests the Board of Public Works approve the change orders subject to financial approvals. Engineering has submitted the funding request in PR-00017412. The INDOT Change Order Summaries for all pertinent change orders are attached. If you have any questions, please respond. July 12, 2022 Contract No:R -38064 Change Order No.: 005 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -38064 Letting Date:03/10/2021 District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Riemke, Ric Status:Draft Change Order Information Change Order No.: 005 EWA: Y or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: SCOPE CHANGES, Added Quantities/Items Description: Storm Water Quality Control Plan Revisions Original Contract Amount $ 1,623,701.34 Current Change Order Amount $ 1,712.00 Percent: 0.105 % Total Previous Approved Changes $ 178,895.51 Percent: 11.018 % Total Change To-Date $ 180,607.51 Percent: 11.123 % Modified Contract Amount $ 1,804,308.85 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00 Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______ SS Days____________ SP Days Value $ _______________ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -38064 Change Order No.: 005 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______* ($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- ) (Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days) Verbal Approval Required?Y / N If Y, by_____________ Date Issued___________ Total Change To-Date>5%?Y / N If Y , Copy to Program Budget Manager_________________ Scope/Design Recommendation Required? Y / N If Y, Referred to Project Manager(PM) __________________ Date to PM__________ Date Returned___________ Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________ If N,Resolution: Approved __________ Disapproved ___________ Resolved by_________________________ Date__________ LPA Signatures Required?Y / N If Y, Date to LPA _____________ Date Returned _________ FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________ * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer _________________________Date _____________ Comments: ____________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:005 Department of Transportation Page: 3 Contract:R -38064 Project:1401810 - State:140181000LC4 Change Order Nbr: 005 Change Order Description: Storm Water Quality Control Plan Revisions Reason Code:SCOPE CHANGES, Added Quantities/Items CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change 0134 1401810 0133 205-12618 LS 1,712.000 1.000 C Amount:$ 1,712.00 Item Description:SWQCP PREPARATION Supplemental Description1: Additional Supplemental Description2: Total Value for Change Order 005 = $ 1,712.00 Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation The Stormwater Quality Control Plan was completed for the original trail alignment. The original trail alignment was shifted approximately 25 feet to the south to align with the railroad roadbed. This was due to the design was completed before the City of South Bend had acquired all the railroad right of way. When design was completed, the City only owned the north half of the right of way. Once clearing began the City desired to have the trail follow the center of the right of way on old railroad roadbed. This required revising the alignment from approximately Station 15.00 to 38.00. The SWQCP was revised in this area to account for the shift in the alignment. This change order is for the costs of revising the SWQCP. The contractors request for change order is attached to this change order. A cost analysis was not performed; however, the revised cost is in comparison with the original cost for the total contract and the percentage of trail that was realigned and deemed acceptable. This work is not in the original scope of the contract and therefore deemed non participating. The AE and PM have been notified and their notification, concurrence emails are attached. Change Order Explanation for Specific Line Item **************************************************************************************************************************** It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor:____________________________________________Signed By:_____________________________________________ Date:__________________________________________________ *************************************************************************************************************************** NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Selge Construction Co., Inc. 6/28/22 Robert P. Kuhns, P.E. Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:005 Department of Transportation Page: 4 **************************************************************************************************************************** APPROVED FOR LOCAL PUBLIC AGENCY ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) **************************************************************************************************************************** SUBMITTED FOR CONSIDERATION PE/S _________________________ **************************************************************************************************************************** APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION Approval Level Name of Approver Date Status July 12, 2022 July 12, 2022 Contract No:R -38064 Change Order No.: 007 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -38064 Letting Date:03/10/2021 District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Riemke, Ric Status:Draft Change Order Information Change Order No.: 007 EWA: Y or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: SCOPE CHANGES, Work Outside Const Limits Description: KC Tree Additional Mobilization and Tree Removal Original Contract Amount $ 1,623,701.34 Current Change Order Amount $ 4,066.00 Percent: 0.250 % Total Previous Approved Changes $ 178,895.51 Percent: 11.018 % Total Change To-Date $ 182,961.51 Percent: 11.268 % Modified Contract Amount $ 1,806,662.85 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00 Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______ SS Days____________ SP Days Value $ _______________ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -38064 Change Order No.: 007 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______* ($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- ) (Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days) Verbal Approval Required?Y / N If Y, by_____________ Date Issued___________ Total Change To-Date>5%?Y / N If Y , Copy to Program Budget Manager_________________ Scope/Design Recommendation Required? Y / N If Y, Referred to Project Manager(PM) __________________ Date to PM__________ Date Returned___________ Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________ If N,Resolution: Approved __________ Disapproved ___________ Resolved by_________________________ Date__________ LPA Signatures Required?Y / N If Y, Date to LPA _____________ Date Returned _________ FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________ * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer _________________________Date _____________ Comments: ____________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:007 Department of Transportation Page: 3 Contract:R -38064 Project:1401810 - State:140181000LC4 Change Order Nbr: 007 Change Order Description: KC Tree Additional Mobilization and Tree Removal Reason Code:SCOPE CHANGES, Work Outside Const Limits CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change 0136 1401810 0135 201-52370 LS 4,066.000 1.000 C Amount:$ 4,066.00 Item Description:CLEARING RIGHT OF WAY Supplemental Description1: Additional Supplemental Description2: Total Value for Change Order 007 = $ 4,066.00 Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation The subcontractor began clearing right of way for the original trail alignment. Shortly after beginning clearing, they were instructed to stop as the alignment of the trail was going to move after the City of South Bend realized they owned all the right of way and could move the trail to the old railroad roadbed, which was much more desirable. After 4 months of redesign and environmental review work resumed on clearing the right of way. This change order is for the costs for the subcontractor to remobilize to the site and for two trees that were removed outside of the construction limits at the request of the city. The contractors request for change order is attached to this change order. A cost analysis was not performed; however, the costs agree with the original cost of clearing right of way for the contract and deemed acceptable. This work is not necessary to complete the original scope of the contract and therefore deemed non participating. The AE and PM have been notified and their notification, concurrence emails are attached. Change Order Explanation for Specific Line Item **************************************************************************************************************************** It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor:____________________________________________Signed By:_____________________________________________ Date:__________________________________________________ *************************************************************************************************************************** NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Selge Construction Co., Inc. 6/28/22 Robert P. Kuhns, P.E. Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:007 Department of Transportation Page: 4 **************************************************************************************************************************** APPROVED FOR LOCAL PUBLIC AGENCY ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) **************************************************************************************************************************** SUBMITTED FOR CONSIDERATION PE/S _________________________ **************************************************************************************************************************** APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION Approval Level Name of Approver Date Status July 12, 2022 July 12, 2022 Contract No:R -38064 Change Order No.: 010 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -38064 Letting Date:03/10/2021 District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Riemke, Ric Status:Draft Change Order Information Change Order No.: 010 EWA: Y or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: SCOPE CHANGES, Added Quantities/Items Description: Additional Construction Engineering Original Contract Amount $ 1,623,701.34 Current Change Order Amount $ 6,577.83 Percent: 0.405 % Total Previous Approved Changes $ 178,895.51 Percent: 11.018 % Total Change To-Date $ 185,473.34 Percent: 11.423 % Modified Contract Amount $ 1,809,174.68 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00 Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______ SS Days____________ SP Days Value $ _______________ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -38064 Change Order No.: 010 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______* ($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- ) (Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days) Verbal Approval Required?Y / N If Y, by_____________ Date Issued___________ Total Change To-Date>5%?Y / N If Y , Copy to Program Budget Manager_________________ Scope/Design Recommendation Required? Y / N If Y, Referred to Project Manager(PM) __________________ Date to PM__________ Date Returned___________ Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________ If N,Resolution: Approved __________ Disapproved ___________ Resolved by_________________________ Date__________ LPA Signatures Required?Y / N If Y, Date to LPA _____________ Date Returned _________ FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________ * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer _________________________Date _____________ Comments: ____________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:010 Department of Transportation Page: 3 Contract:R -38064 Project:1401810 - State:140181000LC4 Change Order Nbr: 010 Change Order Description: Additional Construction Engineering Reason Code:SCOPE CHANGES, Added Quantities/Items CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change 0138 1401810 0137 105-06845 LS 6,577.830 1.000 C Amount:$ 6,577.83 Item Description:CONSTRUCTION ENGINEERING Supplemental Description1: Additionall Supplemental Description2: Total Value for Change Order 010 = $ 6,577.83 Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation The subcontractor completed construction engineering of the original trail alignment prior to the decision to realign the trail as explained in change order 5. This change order is for the cost to complete construction engineering of the new trail alignment between approximately Station 15.00 to 38.00. The contractors request for change order is attached to this change order. A cost analysis was not performed; however, the cost compares with the original contract price and the percentage of work completed and deemed acceptable. The work is not necessary to complete the original scope of the contract and therefore deemed non participating. The AE and PM have been notified and their notification, concurrence emails are attached. Change Order Explanation for Specific Line Item **************************************************************************************************************************** It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor:____________________________________________Signed By:_____________________________________________ Date:__________________________________________________ *************************************************************************************************************************** NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Selge Construction Co., Inc. 6/28/22 Robert P. Kuhns, P.E. Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:010 Department of Transportation Page: 4 **************************************************************************************************************************** APPROVED FOR LOCAL PUBLIC AGENCY ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) **************************************************************************************************************************** SUBMITTED FOR CONSIDERATION PE/S _________________________ **************************************************************************************************************************** APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION Approval Level Name of Approver Date Status July 12, 2022 Contract No:R -38064 Change Order No.: 011 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -38064 Letting Date:03/10/2021 District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Riemke, Ric Status:Draft Change Order Information Change Order No.: 011 EWA: Y or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: ERRORS & OMISSIONS, Design/Plan Related Description: Provide Type 10 Casting to Replace Type 7 Casting Original Contract Amount $ 1,623,701.34 Current Change Order Amount $ 2,006.26 Percent: 0.124 % Total Previous Approved Changes $ 178,895.51 Percent: 11.018 % Total Change To-Date $ 180,901.77 Percent: 11.142 % Modified Contract Amount $ 1,804,603.11 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00 Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______ SS Days____________ SP Days Value $ _______________ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -38064 Change Order No.: 011 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______* ($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- ) (Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days) Verbal Approval Required?Y / N If Y, by_____________ Date Issued___________ Total Change To-Date>5%?Y / N If Y , Copy to Program Budget Manager_________________ Scope/Design Recommendation Required? Y / N If Y, Referred to Project Manager(PM) __________________ Date to PM__________ Date Returned___________ Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________ If N,Resolution: Approved __________ Disapproved ___________ Resolved by_________________________ Date__________ LPA Signatures Required?Y / N If Y, Date to LPA _____________ Date Returned _________ FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________ * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer _________________________Date _____________ Comments: ____________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:011 Department of Transportation Page: 3 Contract:R -38064 Project:1401810 - State:140181000LC4 Change Order Nbr: 011 Change Order Description: Provide Type 10 Casting to Replace Type 7 Casting Reason Code:ERRORS & OMISSIONS, Design/Plan Related CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change 0139 1401810 0138 720-44055 EACH 1,003.130 2.000 C Amount:$ 2,006.26 Item Description:CASTING 10 FURNISH AND ADJUST TO GRADE Supplemental Description1: Replace F7 Supplemental Description2: Total Value for Change Order 011 = $ 2,006.26 Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation The casting for Structures 209 and 210 called for type 7 castings. These casting are in the pavement on Woodward Avenue. The castings being a beehive shape do not work as snowplows would hit them and most likely dislodge them. They also are not bicycle safe and would not provide proper drainage along the curb line. This change order is to replace the type 7 castings with type 10 castings with curb backs and bicycle safe grates. The contractors request for change order is attached to this change order. A cost analysis was performed and is outside the average unit price for this item. However it is below the average unit price and deemed acceptable. This work is necessary to complete the original scope of the contract and is therefore deemed participating. The AE and PM have been notified and their notification, concurrence emails are attached. Change Order Explanation for Specific Line Item **************************************************************************************************************************** It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor:____________________________________________Signed By:_____________________________________________ Date:__________________________________________________ *************************************************************************************************************************** NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Selge Construction Co., Inc. Robert P. Kuhns, P.E. 6/28/22 Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:011 Department of Transportation Page: 4 **************************************************************************************************************************** APPROVED FOR LOCAL PUBLIC AGENCY ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) **************************************************************************************************************************** SUBMITTED FOR CONSIDERATION PE/S _________________________ **************************************************************************************************************************** APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION Approval Level Name of Approver Date Status July 12, 2022 Contract No:R -38064 Change Order No.: 012 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -38064 Letting Date:03/10/2021 District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Riemke, Ric Status:Draft Change Order Information Change Order No.: 012 EWA: Y or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: ERRORS & OMISSIONS, Design/Plan Related Description: 6 Foot Chain Link Fence Original Contract Amount $ 1,623,701.34 Current Change Order Amount $ 14,178.00 Percent: 0.873 % Total Previous Approved Changes $ 178,895.51 Percent: 11.018 % Total Change To-Date $ 193,073.51 Percent: 11.891 % Modified Contract Amount $ 1,816,774.85 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00 Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______ SS Days____________ SP Days Value $ _______________ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -38064 Change Order No.: 012 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______* ($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- ) (Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days) Verbal Approval Required?Y / N If Y, by_____________ Date Issued___________ Total Change To-Date>5%?Y / N If Y , Copy to Program Budget Manager_________________ Scope/Design Recommendation Required? Y / N If Y, Referred to Project Manager(PM) __________________ Date to PM__________ Date Returned___________ Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________ If N,Resolution: Approved __________ Disapproved ___________ Resolved by_________________________ Date__________ LPA Signatures Required?Y / N If Y, Date to LPA _____________ Date Returned _________ FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________ * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer _________________________Date _____________ Comments: ____________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:012 Department of Transportation Page: 3 Contract:R -38064 Project:1401810 - State:140181000LC4 Change Order Nbr: 012 Change Order Description: 6 Foot Chain Link Fence Reason Code:ERRORS & OMISSIONS, Design/Plan Related CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change 0140 1401810 0139 603-92636 LFT 47.260 300.000 C Amount:$ 14,178.00 Item Description:FENCE CHAIN LINK 72 IN Supplemental Description1: Supplemental Description2: Total Value for Change Order 012 = $ 14,178.00 Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation The contract called to remove the existing chain link fence between the new trail construction and the parking lot at Portage Plaza. It did call to replace this fence. After the trail was constructed, it was determined that the fence should be replaced to keep pedestrians and vehicles from accessing the trail from the parking lot. It will also deter a vehicle from crossing the trail and heading down a steep embankment providing a level of safety. The contractors request for change order is attached to this change order. A cost analysis was performed, and the unit price was found to be inside the average unit price for this item and deemed acceptable. The work is necessary to complete the original scope of the contract and also provides additional safety measures and is there for deemed participating. The AE and PM have been notified and their notification, concurrence emails are attached. Change Order Explanation for Specific Line Item **************************************************************************************************************************** It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor:____________________________________________Signed By:_____________________________________________ Date:__________________________________________________ *************************************************************************************************************************** NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Selge Construction Co., Inc. Robert P. Kuhns, P.E. 6/28/22 Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:012 Department of Transportation Page: 4 **************************************************************************************************************************** APPROVED FOR LOCAL PUBLIC AGENCY ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) **************************************************************************************************************************** SUBMITTED FOR CONSIDERATION PE/S _________________________ **************************************************************************************************************************** APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION Approval Level Name of Approver Date Status July 12, 2022 Contract No:R -38064 Change Order No.: 013 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -38064 Letting Date:03/10/2021 District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Riemke, Ric Status:Draft Change Order Information Change Order No.: 013 EWA: Y or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: SCOPE CHANGES, Project Upgrades Description: Concrete Staiway Infill Original Contract Amount $ 1,623,701.34 Current Change Order Amount $ 7,879.90 Percent: 0.485 % Total Previous Approved Changes $ 178,895.51 Percent: 11.018 % Total Change To-Date $ 186,775.41 Percent: 11.503 % Modified Contract Amount $ 1,810,476.75 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00 Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______ SS Days____________ SP Days Value $ _______________ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -38064 Change Order No.: 013 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______* ($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- ) (Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days) Verbal Approval Required?Y / N If Y, by_____________ Date Issued___________ Total Change To-Date>5%?Y / N If Y , Copy to Program Budget Manager_________________ Scope/Design Recommendation Required? Y / N If Y, Referred to Project Manager(PM) __________________ Date to PM__________ Date Returned___________ Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________ If N,Resolution: Approved __________ Disapproved ___________ Resolved by_________________________ Date__________ LPA Signatures Required?Y / N If Y, Date to LPA _____________ Date Returned _________ FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________ * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer _________________________Date _____________ Comments: ____________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:013 Department of Transportation Page: 3 Contract:R -38064 Project:1401810 - State:140181000LC4 Change Order Nbr: 013 Change Order Description: Concrete Staiway Infill Reason Code:SCOPE CHANGES, Project Upgrades CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change 0141 1401810 0140 616-12161 SYS 60.290 130.700 C Amount:$ 7,879.90 Item Description:RIPRAP GROUTED 6-9 IN Supplemental Description1: Supplemental Description2: Total Value for Change Order 013 = $ 7,879.90 Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation Concrete stairs were constructed as part of this contract along side of the existing Portage Road bride. A gap between the stairs and the bridge 32 inches wide did not make sense to topsoil and seed as it would be difficult to maintain as it is behind stair railing. The proposed solution from the contractor to place 5 inches of concrete in the space depress decorative boulders into fresh concrete providing no need to maintain. It would also deter pedestrians from using this space. The City of South Bend agreed with this proposal. The contractors change order request form is attached to this change order. A cost analysis was performed using the closest item to this installation. The was not enough data to complete the analysis, however the contractors unit price was lower that all listed. They have also included costs for labor, materials, and equipment and have been deemed acceptable. The cost analysis data is attached to this change order. The work is not necessary to complete the original scope of the contract and therefore deemed nonparticipating. The AE and PM have been notified and their notification, concurrence emails are attached. Change Order Explanation for Specific Line Item **************************************************************************************************************************** It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor:____________________________________________Signed By:_____________________________________________ Date:__________________________________________________ *************************************************************************************************************************** NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Selge Construction Co., Inc. 6/28/22 Robert P. Kuhns, P. E. Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:013 Department of Transportation Page: 4 **************************************************************************************************************************** APPROVED FOR LOCAL PUBLIC AGENCY ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) **************************************************************************************************************************** SUBMITTED FOR CONSIDERATION PE/S _________________________ **************************************************************************************************************************** APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION Approval Level Name of Approver Date Status July 12, 2022 Contract No:R -38064 Change Order No.: 014 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -38064 Letting Date:03/10/2021 District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Riemke, Ric Status:Draft Change Order Information Change Order No.: 014 EWA: Y or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: ERRORS & OMISSIONS, Design/Plan Related Description: HNA Patching Original Contract Amount $ 1,623,701.34 Current Change Order Amount $ 22,470.00 Percent: 1.384 % Total Previous Approved Changes $ 178,895.51 Percent: 11.018 % Total Change To-Date $ 201,365.51 Percent: 12.402 % Modified Contract Amount $ 1,825,066.85 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00 Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______ SS Days____________ SP Days Value $ _______________ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -38064 Change Order No.: 014 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______* ($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- ) (Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days) Verbal Approval Required?Y / N If Y, by_____________ Date Issued___________ Total Change To-Date>5%?Y / N If Y , Copy to Program Budget Manager_________________ Scope/Design Recommendation Required? Y / N If Y, Referred to Project Manager(PM) __________________ Date to PM__________ Date Returned___________ Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________ If N,Resolution: Approved __________ Disapproved ___________ Resolved by_________________________ Date__________ LPA Signatures Required?Y / N If Y, Date to LPA _____________ Date Returned _________ FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________ * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer _________________________Date _____________ Comments: ____________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:014 Department of Transportation Page: 3 Contract:R -38064 Project:1401810 - State:140181000LC4 Change Order Nbr: 014 Change Order Description: HNA Patching Reason Code:ERRORS & OMISSIONS, Design/Plan Related CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change 0142 1401810 0141 304-07490 TON 401.250 56.000 C Amount:$ 22,470.00 Item Description:HMA PATCHING TYPE B Supplemental Description1: Supplemental Description2: Total Value for Change Order 014 = $ 22,470.00 Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation There was no pay item for HMA patching in the contract. HMA patching was necessary along the edge of the Portage Plaza parking lot after constructing the trail and on Woodward Avenue after construction of the pedestrian crossing and install storm sewer across Woodward Avenue. The contractors change order request form is attached to this change order. A cost analysis was performed, and the cost was found to be within the average unit price for this item and deemed acceptable. The work is necessary to complete the original scope of the contract and therefore deemed participating. The AE and PM have been notified and their notification, concurrence emails are attached. Change Order Explanation for Specific Line Item **************************************************************************************************************************** It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor:____________________________________________Signed By:_____________________________________________ Date:__________________________________________________ *************************************************************************************************************************** NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Robert P. Kuhns, P.E. Selge Construction Co., Inc. 6/28/22 Contract No:R -38064 INDIANA Date:06/27/2022 Change Order No:014 Department of Transportation Page: 4 **************************************************************************************************************************** APPROVED FOR LOCAL PUBLIC AGENCY ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) **************************************************************************************************************************** SUBMITTED FOR CONSIDERATION PE/S _________________________ **************************************************************************************************************************** APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION Approval Level Name of Approver Date Status July 12, 2022 Contract No:R -38064 Change Order No.: 015 INDIANA Department of Transportation Page: 1 Construction Change Order and Time Extension Summary Contract Information Contract No.: R -38064 Letting Date:03/10/2021 District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Riemke, Ric Status:Draft Change Order Information Change Order No.: 015 EWA: Y or Force Acct: N Date Generated: 00/00/0000 Date Approved: 00/00/0000 Reason Code: FINAL QUANTITY ADJUSTMENT Description: Concrete Sidewalk Participating and Non Participating Original Contract Amount $ 1,623,701.34 Current Change Order Amount $ 0.00 Percent: 0.000 % Total Previous Approved Changes $ 178,895.51 Percent: 11.018 % Total Change To-Date $ 178,895.51 Percent: 11.018 % Modified Contract Amount $ 1,802,596.85 Time Extension Information Date Initiated 00/00/0000 Date Completed 00/00/0000 Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SP Date 00/00/0000 or SP Days (SS = Standard Specification, SP = Special Provision) Time Element Description: Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00 Previous Time Approved SS Days by AE:______ DCE:______ SCE:______ DDCM:______ SS Days____________ SP Days Value $ _______________ Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 SS Date 00/00/0000 or SP Days 0 Contract No:R -38064 Change Order No.: 015 INDIANA Department of Transportation Page: 2 Construction Change Order and Time Extension Summary Review and Approval Information Required Approval Authority AE:________ DCE:________ SCE:________* DDCM:_______* ($ per Change Order) (- LE $ 250K-) (- LE $ 750K - ) ( -- LE $ 2 M -- ) ( -- GT $ 2 M -- ) (Days per Contract) ( 50 SS days ) ( 100 SS days ) ( 200 SS Days ) ( GT 200 SS days) Verbal Approval Required?Y / N If Y, by_____________ Date Issued___________ Total Change To-Date>5%?Y / N If Y , Copy to Program Budget Manager_________________ Scope/Design Recommendation Required? Y / N If Y, Referred to Project Manager(PM) __________________ Date to PM__________ Date Returned___________ Approval Authority Concurs with PM? Y / N If Y, Concurrence by_______________ Date___________ If N,Resolution: Approved __________ Disapproved ___________ Resolved by_________________________ Date__________ LPA Signatures Required?Y / N If Y, Date to LPA _____________ Date Returned _________ FHWA Signatures Required? Y / N If Y, Date to FHWA____________ Date Returned_________ * Field Engineer Recommendation (Required for SCE or DDCM Approval) Field Engineer _________________________Date _____________ Comments: ____________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Contract No:R -38064 INDIANA Date:06/28/2022 Change Order No:015 Department of Transportation Page: 3 Contract:R -38064 Project:1401810 - State:140181000LC4 Change Order Nbr: 015 Change Order Description: Concrete Sidewalk Participating and Non Participating Reason Code:FINAL QUANTITY ADJUSTMENT CLN PCN PLN Item Code Unit Unit Price CO Qty Comment Amount Change 0130 1401810 0128 604-06070 SYS 41.500 -3207.663 C Amount:$ -133,118.01 Item Description:SIDEWALK CONCRETE Supplemental Description1: Supplemental Description2: 0143 1401810 0142 604-06070 SYS 41.500 3207.663 C Amount:$ 133,118.01 Item Description:SIDEWALK CONCRETE Supplemental Description1: Supplemental Description2: Total Value for Change Order 015 = $ 0.00 Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. General or Standard Change Order Explanation Change Orders 1, 2 and 3 created new non participating items which replaced participation items that were reduced to zero. The non participating items needed their own purchase order in order for payment to be made on those items. Once the dollar amount of change order 1 exceeded the dollar amount of the new non participating purchase order additional funds were requested to pay for PLN 0128. This was in error as the total dollar amount of the non participating purchase order should have been the net total of the three change orders which it is and the second non participating purchase order should not have been requested. This change order reduces the amount of the non participating item PLN 0128 and creates a new item for the amount of the portion of that item that should have been participating. This change order does not increase the cost of the contract, it just puts the dollar amounts into the purchase orders where they belong. Change Order Explanation for Specific Line Item **************************************************************************************************************************** It is the intent of the parties that this change order is full and complete compensation for the work describe above. Notification and consent to this change order is hereby acknowledged. Contractor:____________________________________________Signed By:_____________________________________________ Date:__________________________________________________ *************************************************************************************************************************** NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. Selge Construction Co., Inc. 6/29/22 Robert P. Kuhns, P.E. Contract No:R -38064 INDIANA Date:06/28/2022 Change Order No:015 Department of Transportation Page: 4 **************************************************************************************************************************** APPROVED FOR LOCAL PUBLIC AGENCY ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) ______________________________________________________________________________ (SIGNATURE)(TITLE)(DATE) **************************************************************************************************************************** SUBMITTED FOR CONSIDERATION PE/S _________________________ **************************************************************************************************************************** APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION Approval Level Name of Approver Date Status July 12, 2022 BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date: July 1st, 2022 Name: Finnian Cavanaugh Department of Public Works – Engineering Division BPW Date: July 12th, 2022 Phone Extension: 5961 or fcavanau@southbendin.gov Required Prior to Submittal to Board BPW Attorney X Attorney Name Clara McDaniels Dept. Attorney Attorney Name Purchasing Check the Appropriate Item Type – Required for All Submissions Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA Chg. Order, No. 4-7,9-15 Traffic Control Resolution Other: Ease./Encroach Required Information Company or Vendor Name Indiana Department of Transportation (INDOT) New Vendor Yes If Yes, Approved by Purchasing No MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name Coal Line Trail Phase I (CN) Project Number 115-063 Funding Source TIF River West Development Account No. 324-10-102-121-444000--PROJ00000018 Amount $29,921.77 to be paid by City Terms of Contract NTE Purpose/Description Change orders for construction of Coal Line Trail Phase I. Project is a federal cost-share with INDOT – requesting new PO. See attached memo with explanation. For Change Orders Only Reflecting *Total* Project Cost (Federal and Local Funds) Amount of Increase Decrease $68,665.95 ($ ) Previous Amount $ 1,802,596.85 Current Percent of Change: Increase Decrease 4.2% ( %) New Amount $ 1,871,262.80 Total Percent of Change: Increase Decrease 15.2% ( %) Time Extension Amount: None New Completion Date: