HomeMy WebLinkAboutRescind LPA-Utility Reimbursement Agreement - Relocating Five (5) Hydrants at Auten Rd. – SJC Board of Comm.Page 1 of 2
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Zach Hurst, Project Engineer
SUBJECT: Rescind Approval of LPA/Utility Reimbursement Agreement - Project No.
121-036
Auten Road Fire Hydrants
DATE: 06/16/2022
On May 24, 2022, the Board of Public Works approved an agreement between the City of South
Bend and the St. Joseph County Commissioners for the City to reimburse the County for
relocation of five (5) City-owned fire hydrants located along Auten Road as part of the County’s
project to construct a multi-use path along Auten Road.
The construction project is a federal aid project managed by the Indiana Department of
Transportation (INDOT). The reimbursement agreement was also subject to final approval by
INDOT, who ultimately decided that these hydrant relocations could not be performed as part of
St. Joseph County’s construction project.
Because this work cannot be completed by St. Joseph County as part of their contract, and that
St. Joseph County will not sign this agreement, the City’s Department of Public Works
respectfully requests that the Board rescind its approval of the Agreement, rendering it null and
void.
The hydrant relocations will be completed by using a public quote process in accordance with
Indiana State code.
Thank you.
Page 2 of 2
Department of Public Works
Request for Rescission of Approval of LPA/Utility Reimbursement Agreement
June 16, 2022
On this 28th day of June, 2022, the Board of Public Works hereby rescinds its May 24, 2022
approval of the LPA/Utility Reimbursement Agreement between the City of South Bend and the
St. Joseph County Commissioners for the reasons set forth above.
June 28, 2022
Page 1 of 5
October 2019
Revised Agreement
Work in Contract
LPA/UTILITY REIMBURSEMENT AGREEMENT
(WORK IN CONTRACT)
Agreement Amount: $19,410.00
Agreement Type: Work in Contract
Work Description: Fire hydrant relocation.
Des No: 1400638
Project No: 1400638
Road: Auten Road
County: St. Joseph
THIS AGREEMENT, made and entered into the day of , 2022, by and between
City of South Bend Indiana, acting by and through its Board of Public Works
(hereinafter referred to as the Utility), and St. Joseph County Board of Commissioners, acting by and
through its appropriate elected officials, (hereinafter referred to as the “Local Public Agency” or “LPA”).
WITNESSETH:
WHEREAS, the LPA desires to improve the condition of the above referenced road as
referenced by the Des No. and Project No. given above (hereinafter referred to as the “Project”); and
WHEREAS, due to the said highway construction certain adjustments, removals, alterations,
and/or relocations of the existing facilities of the Utility will have to be made as shown on the plan
marked Exhibit “A” attached hereto and incorporated by reference;
WHEREAS, the State of Indiana, through the Indiana Department of Transportation,
(hereinafter referred to as “INDOT”) will recommend approval of this Project, if applicable, to the
Federal Highway Administration for construction with funds apportioned to INDOT under Title 23,
United States Code and Acts amendatory thereof and supplementary thereto;
WHEREAS, INDOT has confirmed that the Project as well as the LPA expenses as forth in
Section 5, below, have been approved for and are eligible for federal reimbursement.
WHEREAS, INDOT will advertise for bids for construction of the Project, award the contract,
and act as liaison agent for the LPA with the Federal Highway Administration. The LPA will supervise
the construction of the Project;
WHEREAS, it is necessary for the parties hereto to comply with the applicable terms and
provisions of the Federal-Aid Policy Guide (hereinafter called the Policy Guide and available at
http://www.fhwa.dot.gov/legsregs/directives/cfr23toc.htm on the FHWA website) and 23 CFR 645
Subpart A, which is hereby incorporated by reference, in order to receive reimbursement;
WHEREAS, it is in the best interests of the Utility and the LPA, for the necessary utility
adjustments, removals, alterations, and/or relocations of its existing facilities as shown on Exhibit “A” to
Page 2 of 5
be made by a contractor paid under the contract let by INDOT.
NOW, THEREFORE, IN CONSIDERATION OF THE PREMISES AND THE MUTUAL
AGREEMENTS AND COVENANTS HEREIN CONTAINED (THE ADEQUACY OF WHICH
CONSIDERATIONS AS TO EACH OF THE PARTIES TO THIS AGREEMENT IS HEREBY
MUTUALLY ACKNOWLEDGED), AND OTHER GOOD AND VALUABLE
CONSIDERATIONS, THE RECEIPT OF WHICH IS HEREBY ACKNOWLEDGED AND
INTENDING TO BE LEGALLY BOUND, THE PARTIES HEREBY COVENANT AND
AGREE AS FOLLOWS:
SECTION 1 – PREPARATION OF RELOCATION PLANS FOR INDOT’S CONSTRUCTION
CONTRACT
The Utility shall prepare, or cause to be prepared, at its own cost and expense, all plans,
specifications and a preliminary itemized cost estimate, for relocation of the Utility’s facilities that need to
be relocated in order to construct the LPA’s Project. INDOT’s construction contract will require the
contractor, which is awarded the contract, to list the Utility as an additional named insured. In addition,
INDOT’s construction contract will provide that the Utility is a third-party beneficiary with respect to the
relocation work. No changes to the plans or specifications for relocation of the Utility’s facilities shall be
made without the written approval of the Utility. INDOT will prepare the final engineer’s estimate for the
Project construction contract.
SECTION 2 – AWARDING OF CONSTRUCTION CONTRACT
INDOT will advertise one (1) contract for bids which includes the plans and specifications for
relocation of the Utility’s facilities and the LPA’s plans and specifications for the LPA’s Project. Upon
receipt of an acceptable bid in accordance with State law, INDOT will award a contract for construction of
the Project, inclusive of the relocation of the Utility’s facility. The Utility agrees to have the contractor to
whom INDOT awards the contract relocate the Utility’s facilities as part of the Project.
SECTION 3 – CONSTRUCTION TESTING AND INSPECTION
The LPA will provide, or cause to be provided, construction inspection and testing services to
monitor the contractor’s relocation of the Utility’s facilities. The costs for said services shall be paid
pursuant to the terms set forth in Section 5. The Utility may inspect, at its own cost, the relocation of the
Utility’s facilities. The Utility shall timely advise the LPA, in writing, of any deficiencies that are
observed. Prior to INDOT and the LPA’s final acceptance of the construction contract and improvements
and relocation of the Utility’s facilities, the Utility shall make an inspection of the Utility’s relocation work
and advise the LPA in writing of the Utility’s acceptance thereof. Such acceptance shall not be
unreasonably withheld.
SECTION 4 – SUBORDINATION OF RIGHTS
[Check the following that applies]
☒The existing facilities are located on public right-of-way.
☐The existing facilities are not located on public right-of-way
If such facilities are located on property, other than public right-of-way, and the Utility either has
an easement thereon or a continuing right to maintain the facilities in that location, the Utility, for and in
consideration of this Agreement, shall subordinate the Utility’s rights herein to those of the LPA in the
highway right-of-way by executing a subordination Agreement.
Page 3 of 5
SECTION 5 – REIMBURSEMENT
(a)0 % of the cost to design and prepare construction plans, specifications and preliminary
itemized cost estimate for relocation of the Utility’s facilities shall be borne by the LPA.
The Utility shall be responsible for 100% of these costs.
(b)0 % of the cost to provide testing and inspection services for relocation of the Utility’s
facilities shall be borne by the LPA, subject to federal reimbursement. The Utility shall
be responsible for 100% of the cost to provide testing and inspection services for
relocation of the Utility’s facilities. In addition to its 100% share, the Utility shall also be
responsible for any portion of the LPA’s share that is not reimbursed through federal
funds.
(c) The LPA shall bear 0 % of the cost of relocating the Utility’s facilities, subject to federal
reimbursement., and 0% of the cost of betterment items. (See Exhibit “B”). The Utility
shall be responsible for 100% of the cost of relocating the Utility’s facilities and 100% of the
betterment items identified in Exhibit “B”. In addition, the Utility shall be responsible for any
portion of the LPA’s share that is not reimbursed through federal funds.
The cost of relocation of the Utility’s facilities (provided for in (c)) shall equal the amount paid by
the LPA to the contractor (based upon the actual units of work performed at the unit prices set out in the
contractor’s itemized proposal or extra work agreement), selected in accordance with the procedure in
Section 2.
The estimated cost of relocation, including construction and inspection, is $19,410.00. (See
Exhibit “B” for an itemized estimate of all anticipated costs, including but not limited to, materials, labor,
and equipment costs.)
The estimated cost of non-reimbursable relocation work to the utility’s facilities is $ 19,410.00 .
The Utility has appropriated, duly made and entered of record, the sum of $ 19,410.00 to apply to the cost
of the Project and further agrees to appropriate additional funds if federal reimbursement funds are not
available to cover the LPA’s 100% of the relocation and inspection costs as set forth in Section 5.
SECTION 6 – COMPLETION OF PROJECT
Upon final acceptance of the contractor’s work (the construction contract) by INDOT and the
LPA, the Utility shall be responsible for maintenance, repair, and/or reconstruction of the Utility’s
facilities.
SECTION 7 – WAIVER
In consideration for INDOT’s participation in this contract, the Utility waives any claim, demand,
or expectation it may have in the future against INDOT and/or the LPA based upon any negligent omission
and/or commission by INDOT’s contractor performing the relocation of the Utility’s facilities.
SECTION 8 – PAYMENTS
Within forty-five (45) days after the contract is awarded, the Utility shall pay the LPA a sum equal
to one hundred percent (100%) of the Utility’s share of the bid price for construction as stated above in
Section 5. If an Advice of Change Order (AC) is approved which increases the Utility’s share of the
Project cost, the Utility shall pay the LPA within thirty (30) days a sum equal to one hundred percent
(100%) of such increased cost. If any of the LPA’s costs set forth herein are not reimbursed through
federal funds, the Utility shall pay the LPA for any unreimbursed funds within thirty (30) days of receiving
notice of the amount due from the LPA.
All payments shall be made in arrears in conformance with State fiscal policies and procedures
Page 4 of 5
and, as required by IC 4-13-2-14.8, by electronic funds transfer to the financial institution designated by the
Utility in writing unless a specific waiver has been obtained from the Auditor of State. No payments will be
made in advance of receipt of the goods or services that are the subject of this agreement except as
permitted by IC 4-13-2-20
SECTION 9 – BINDING UPON SUCCESSORS OR ASSIGNS
This Agreement shall be binding upon the parties and their successors and assigns.
SECTION 10 – GENERAL LIABILITY PROVISIONS
The Utility for itself, its employees, agents and representatives, shall indemnify, protect and save
harmless the Indiana Department of Transportation, the State of Indiana, and the LPA from and against
any and all legal liabilities and other expenses, claims, cost, losses, suits or judgments for damages, or
injuries to or death of persons or damage to or destruction of property (hereafter “Claim”), arising out of
intentional tortious acts or whether due in whole or in part to the negligent acts or omissions of the Utility,
its employees or agents or contractors, in relation to or in connection with any work performed or to be
performed pursuant to this agreement, provided however, that where the State has been found liable by a
court, tribunal or governing body entitled to make such a determination for intentional tortious acts and/or
negligence with respect to the occurrence or occurrences giving rise to the Claim, the Utility shall have no
duty to indemnify, protect, or save harmless either the Department of Transportation or the State.
SECTION 11 – INCORPORATION OF THE UTILITY POLICY GUIDE
The Policy Guide forms an essential part of this Agreement, and the terms or provisions of this
Agreement in no way abrogate or supersede the terms or provisions set forth in said Policy Guide.
SECTION 12 – PENALTIES/INTEREST/ATTORNEY’S FEES
The LPA will in good faith perform its required obligations hereunder and does not agree to pay
any penalties, liquidated damages, interest, and/or attorney’s fees, except as required by Indiana law.
SECTION 13 – COMPLIANCE WITH LAWS; APPLICABLE LAW
The UTILITY agrees to comply with all federal, state and local laws, rules, regulations, or
ordinances that are applicable at the time the UTILITY's services pursuant to this agreement are rendered, and
all provisions required thereby to be included herein are hereby incorporated by reference. The enactment of
any Indiana or federal statute or the promulgation of regulations there under after execution of this agreement
shall be reviewed by the LPA and the UTILITY to determine whether the provisions of this agreement require
formal amendment.
This Agreement shall be construed in accordance with and governed by the laws of the State of
Indiana and suit, if any, must be brought in the State of Indiana.
SECTION 14 – BUY AMERICA CERTIFICATION
The UTILITY agrees that all steel and cast iron materials and products to be used under this
agreement will be produced and manufactured in the United States of America pursuant to the
requirements of IC 5-16-8-1, et al. and 23 CFR 635.410.
THE REMAINDER OF THIS PAGE LEFT INTENTIONALLY BLANK
Page 5 of 5
IN WITNESS HEREOF, the parties hereto separately and severally have caused this instrument to be
executed in their respective names by and through their duly authorized officers.
UTILITY:
City of South Bend, Indiana
Board of Public Works
(Utility Name)
(Signature of Officer) (Date)
(Officer’s Name, Printed or typed)
(Officer’s Position)
LPA:
St. Joseph County Board of Commissioners
(Name of LPA) ATTEST:
(Name, Printed or Typed) (Name, Printed or Typed)
(Name, Printed or Typed)
(Name, Printed or Typed)
(Date)
May 24, 2022
2833 S. 11th Street,
Niles, MI 49120
Phone: 269-684-0842
Fax: 269-684-0846
______________________________________________________________________________
Page 1 of 1
PROPOSAL
April 21, 2022
City of South Bend
Dept. of Public Works
Attn: Mr. Zach Hurst, P.E.
227 W. Jefferson Blvd., Ste. 1316
South Bend, IN 46601
RE: INDOT 37502 – AUTEN ROAD TRAIL
FIRE HYDRANT RELOCATIONS
Zach,
Thank you for the opportunity to provide you with a proposal to relocate five (5) existing
hydrants along Auten Road that are currently in the proposed bike trail. The new hydrants, pipe,
and fittings for the relocation will be supplied by the City of South Bend, Water Department. The
hydrants to be relocated are as follows:
Station Distance (ft)
124+11 12
135+93 2.5
142+81 12
146+46 3.25
148+95 2
Total Cost to Relocate Hydrants: 5 ea. x $3,882.00/ea. = $19,410.00
Notes:
1. City of South Bend to supply new hydrants, pipe, and fittings.
2.Selge to supply labor, equipment, stone, backfill, and MOT.
3.Proposal assumes complete shutdown of hydrant.
4.Proposal based on relocation plan date 4/4/2022.
5.Old hydrants to be returned to the South Bend Water Department.
Feel free to call with any questions. Thank you again for the opportunity.
Respectfully submitted:
Selge Construction Co., Inc. City of South Bend
Robert P. Kuhns, PE Authorized Signature
Project Engineer
Exhibit B
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 06/21/2022
Name Zach Hurst Department DPW
BPW Date 06/28/2022 Phone Extension 3057
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name BPW Attorney Attorney Name Clara McDaniels
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: LPA/Utility
Reimbursement Agreement
[RESCIND]
Ease./Encroach
Required Information
Company or Vendor Name St. Joseph Co. Board of Commissioners
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Auten Road Hydrant Relocations
Project Number 122-036
Funding Source Water Works Capital
Account No. PR-00016939
Amount $19,410.00
Terms of Contract
Purpose/Description RESCIND APPROVAL of agreement for City to reimburse St. Joseph Co. for
relocating 5 hydrants as part of their Auten Road trail project.
For Change Orders Only
Amount of
Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount: