HomeMy WebLinkAboutChange Order No 1 - Ward Bakery Exterior Renovations-Masonry Bid Package Proj No. 121-061 - C&S Masonry Restoration, LLC
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
June 28, 2022
Mr. Steve Fields
C&S Masonry Restoration, LLC
3725 N. Foundation Ct., Suite AB
South Bend, IN 46628
stevecands@outlook.com
RE: Change Order No. 1 – Ward Bakery Exterior Renovations-Masonry Bid Package
Project No. 121-061R
Dear Mr. Fields:
At its June 28, 2022 meeting, the Board of Public Works approved the above referenced
Change Order be increased by $34,393, bringing the revised contract amount to $194,393.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Zach Hurst, Project Engineer
SUBJECT: Change Order No. 1 - Project No. 121-061R
Ward Bakery Exterior Renovations – Masonry Bid Package
DATE: June 21, 2022
Change Order no. 1 for the subject project brings the cumulative total of changes beyond the
state-mandated 20% threshold for added work. However, $9,000 of this change order is related
to unforeseen site conditions relating to the steel lintels above the existing window openings.
As such, scope additions to the project account for 15.9% of the total original contract amount,
and the project remains under the 20% limit.
Thank you.
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:5/15/2022
PROJECT NO:121-061R
PROJECT NAME:Ward Bakery Exterior Renovations BP1
CONTRACT DATE:1/11/2022
CHANGE ORDER NO:1
SUBJECT OF CHANGE ORDER:PCR #1-Added steel replacement- 9,000 & Added brick & terra
cotta- $25,393
The original contract sum $ 160,000.00
Net change by previously authorized change orders $0.00
The contract sum prior to this change order $ 160,000.00
By this Change Order, the project amount is X Increased
34,393.00Decreased $
The new contract sum including this change order $ 194,393.00
This Change Order represents a total change of 21.50 %
Total change for entire project 21.50 %
Original contracted completion date/time 9/22/2022
Extension of date/time by previous change orders 0 days
Date/time extension by this change order 0 days
New completion date/time 9/22/2022
CONTRACTOR RECOMMENDED FOR APPROVAL
Contractor Signature CONSTRUCTION MANAGER
CITY OF SOUTH BEND
Printed Name and Title BOARD OF PUBLIC WORKS
Approved Date:
C&S Masonry Restoration, LLC
Company Name
Elizabeth A. Maradik, President
3725 Foundation Ct
Address
Jordan V. Gathers, Member
South Bend, IN 46628
City, State, Zip
Joseph R. Molnar, Vice President
Gary A. Gilot, Member
Murray L. Miller, Member June 28, 2022
06/07/2022Toy Villa
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 06/21/2022
Name Zach Hurst Department DPW
BPW Date 06/28/2022 Phone Extension 3057
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 1 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name C&S Masonry
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Ward Bakery Exterior Renovations – Masonry Bid Package
Project Number 121-061R
Funding Source River West TIF
Account No. PO-0014206
Amount $34,393
Terms of Contract
Purpose/Description Change Order addresses unforeseen lintel repairs and added masonry scope.
For Change Orders Only
Amount of
Increase
Decrease
$ 34,393
($ )
Previous Amount $ 160,000
Current Percent of Change:
Increase
Decrease
21.5% (15.9% scope add, 5.6% unforeseen)
( %)
New Amount $ 194,393
Total Percent of Change:
Increase
Decrease
21.5%
( %)
Time Extension Amount:
New Completion Date: