HomeMy WebLinkAboutRejection of Bid - Northwest Elevated Storage Tank Improvements Proj No. 122-018 - Viking Painting LLC.
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
June 28, 2022
Mr. Rory Sudbeck
Viking Painting, LLC
10905 Harrison St.
La Vista, NE 68128
dominic@viptanks.com
RE: Rejection of Bid – Northwest Elevated Storage Tank Improvements
Project No. 122-018
Dear Mr. Sudbeck:
At its June 28, 2022 meeting, the Board of Public Works approved the rejection of your
bid for the above referenced project as non-responsive due to the MWBE goals not being met.
The project will go to Open Market.
Thank you for bidding, and we hope you bid with us in the future.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Becca Plantz, Project Engineer
SUBJECT: Reject Project No. 122-018
Northwest Elevated Storage Tank Rehabilitation
DATE: June 17, 2022
On June 14, 2022 the Board of Public Works opened bids for the above project.
The bids ranked as follows:
Quoter Base Bid Alternate 1 Alternate 2 Alternate 3 Total of Base Bid
and Alternates
1. Viking
Painting
LLC
$1,193,800.00 $12,500.00 $162,800.00 $26,800.00 $1,395,900.00
Upon review of the bid package, I recommend rejecting the bid as non-responsive due to it not
meeting MWBE goals or good faith effort. In addition to the lack of good faith effort, there were
missing training certificates, evidence of an approved surety according to the Bureau of Fiscal
Service “Department of Treasury’s Listing of Approved Sureties,” and accompanying
attachments for statements as required by the Responsible Bidder Ordinance.
Due to rejecting the one bid received, I recommend rejection and negotiating in the open market
for an agreement in accordance with IC 36-1-12-5.
Please call with your questions (5998).
Enc. Bid Tabulation
June 28, 2022
CITY OF SOUTH BEND, INDIANA
NORTHWEST ELEVATED STORAGE TANK REHABILITATION PROJECT
CITY PROJECT NO: 122-018
UNITED PROJECT NO: 21-918-01
BID TABULATION
BID DATE: June 14, 2022
# DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE
1
Application of exterior and interior (wet) coatings to
1.5-million gallon elevated steel water pedestal
storage tank, spot coatings for corroded pipe
penetrations through the tank bulb, replacement of
degraded/missing seals and gaskets from the third
level platform up to the tank roof in accordance with
plans & specifications including abrasive blasting,
full containment and disposal, mobilization, testing,
disinfection, demobilization, etc., complete.
1 LS $ 980,000.00 980,000.00$ 1,133,800.00$ 1,133,800.00$
2
Allowance for service of cathodic protection system
in accordance with plans & specifications including
replacement of anodes, mobilization, testing,
demobilization, etc., complete.
1 LS $ 15,000.00 15,000.00$ 15,000.00$ 15,000.00$
3
Allowance for service of swing check and altitude
valves in accordance with plans & specifications
including replacement of defective parts, calibration
of altitude valve, mobilization, disinfection,
demobilization, etc., complete.
1 LS $ 25,000.00 25,000.00$ 25,000.00$ 25,000.00$
4
Allowance for miscellaneous component repairs in
accordance with plans & specifications including
replacement of insulation straps, spot coating
repairs not shown in Appendix D, mobilization,
disinfection, demobilization, etc., complete.
1 LS $ 20,000.00 20,000.00$ 20,000.00$ 20,000.00$
$100,000.00
1,140,000.00$ 1,193,800.00$
BID BOND / CERTIFIED CHECK
ADDENDUM #1
Construction Contingency (10%)
N/A
Yes
N/A
ITEM DESCRIPTION
Yes
Yes
N/A
Viking Painting, LLCEngineer's Estimate
N/A
PROPOSAL FORM
FORM #96
E-VERIFY AFFIDAVIT
EVIDENCE OF GOOD FAITH EFFORTS
Yes
Yes
N/A
N/A
FINANCIAL STATEMENT
TOTAL BASE BID AMOUNT
ITEM BID AMOUNT ITEM BID AMOUNT
N/A
BASE BID ITEMS
Incomplete
Yes
DRUG TESTING PROGRAM N/A Yes
M/WBE UTILIZATION N/A No
COMPLETED RESPONSIBLE BIDDERS CHECKLIST N/A Incomplete
Page 1 of 3
CITY OF SOUTH BEND, INDIANA
NORTHWEST ELEVATED STORAGE TANK REHABILITATION PROJECT
CITY PROJECT NO: 122-018
UNITED PROJECT NO: 21-918-01
BID TABULATION
BID DATE: June 14, 2022
# DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE
1
Additive price for application of insulative coatings
to valve vault piping installed in accordance with
plans & specifications including surface preparation,
priming, painting, testing, mobilization,
demobilization, etc., complete.
1 LS $ 11,000.00 11,000.00$ 12,500.00$ 12,500.00$
11,000.00$ 12,500.00$
# DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE
1
Additive price for installation of a stormwater inlet,
type E, with 158 LF of 12-inch French drain pipe in
accordance with plans & specifications including
excavation, backfill, site restoration, mobilization,
demobilization, etc., complete.
1 LS $ 34,000.00 34,000.00$ 124,600.00$ 124,600.00$
2
Additive price for the installation of waterproofing
grout in valve vault and replacement of damaged
hatch door upstream of the elevated storage tank in
accordance with plans & specifications including
any drilling, grout application, disposal, testing,
mobilization, demobilization, etc., complete.
1 LS $ 10,000.00 10,000.00$ 38,200.00$ 38,200.00$
44,000.00$ 162,800.00$
# DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE
1
Additive price for the installation of a new fall
protection safety system and relocation of the
existing FAA obstruction light photo-sensor in
accordance with plans & specifications including
ladder accessories, removal of existing system,
related electrical accessories, conduit, testing,
mobilization, demobilization, etc., complete.
1 LS $ 24,000.00 24,000.00$ 26,800.00$ 26,800.00$
24,000.00$ 26,800.00$
ITEM DESCRIPTION Engineer's Estimate
ITEM BID AMOUNT ITEM BID AMOUNT
ITEM DESCRIPTION Engineer's Estimate Atlas Excavating, Inc.
MANDATORY BID ALTERNATE #2 ITEM BID AMOUNT ITEM BID AMOUNT
TOTAL MANDATORY ALTERNATE #1 AMOUNT
Atlas Excavating, Inc.
MANDATORY BID ALTERNATE #1
MANDATORY BID ALTERNATE #3 ITEM BID AMOUNT ITEM BID AMOUNT
TOTAL MANDATORY ALTERNATE #3 AMOUNT
TOTAL MANDATORY ALTERNATE #2 AMOUNT
ITEM DESCRIPTION Engineer's Estimate Atlas Excavating, Inc.
Page 2 of 3
CITY OF SOUTH BEND, INDIANA
NORTHWEST ELEVATED STORAGE TANK REHABILITATION PROJECT
CITY PROJECT NO: 122-018
UNITED PROJECT NO: 21-918-01
BID TABULATION
BID DATE: June 14, 2022
Paul D. Glotzbach Troy A. Casey
Reg. Engineer No. 10100222 Reg. Engineer No. 11800761
State of Indiana State of Indiana
Signed:Signed:
Date:06/16/2022 Date:06/16/2022
Page 3 of 3
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 06/17/2022
Name Becca Plantz Department Public Works
BPW Date 06/28/2022 Phone Extension 5998
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name Michael Patton BPW Attorney Attorney Name Clara McDaniels
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Northwest Elevated Tank Improvements
Project Number 122-018
Funding Source Water Works Capital – Distribution /Reservoirs
Account No. PROJ 319
Amount
Terms of Contract Lump Sum
Purpose/Description Install new coatings for the Northwest Elevated Storage Tank as well as
several minor site and structure improvements.
For Change Orders Only
Amount of
Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: