HomeMy WebLinkAboutChange Order No 1 - 2021 Roadway Reconstruction Proj No. 121-008 - Rieth-Riley Construction Co., Inc.
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
May 10, 2022
Mr. Ruben Alvarado
Rieth-Riley Construction Co., Inc.
25200 State Road 23
South Bend, IN 46614
ralvarado@rieth-riley.com
RE: Change Order No. 1 – 2021 Roadway Reconstruction – Project No. 121-008
Dear Mr. Alvarado:
At its May 10, 2022 meeting, the Board of Public Works approved the above referenced
Change Order be increase by $32,557.16 with an additional one hundred & ninety-eight (198)
days, bringing the revised contract amount to $2,029,973.22 with a new completion date of May
1, 2022.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
May 10, 2022