HomeMy WebLinkAboutAmendment No 1 to LPA Consulting Contract - Olive Rd. Recon, Phase I Proj No. 114-064 - HWC Engineering Inc.
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT JORDAN V. GATHERS MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
February 22, 2022
Mr. Terry M. Baker
HWC Engineering, Inc.
135 N. Pennsylvania St., Suite 2800
Indianapolis, IN 46204
tbaker@hwcengineering.com
RE: Amendment No. 1 to LPA Consulting Contract
Dear Mr. Baker:
At its February 22, 2022 meeting, the Board of Public Works approved the above
referenced amendment for additional inspection services due to utilities delaying the project for
one (1) year for Olive Road Reconstruction, Phase I, Project No. 114-064 in an amount not to
exceed $25,528.
Enclosed please find the original of the amendment for your signature. Please sign and
return the original amendment to lhensley@southbendin.gov. Please retain a copy for your
records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Laura Hensley/Acting
Clerk
Enclosures
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENVIRONMENTAL SERVICES
TO: Board of Public Works
Anne Fuchs, Clerk
FROM: Leslie Biek, P.E., Assistant City Engineer
SUBJECT: Supplement #1 to Construction Inspection Contract with HWC
Engineering
Olive Road Reconstruction Ph 1
114-064
DATE: January 27, 2022
Attached is Supplement #1 to the Construction Inspections Services contract for the
Reconstruction of Olive St from Prairie Ave to Tucker Dr (Ph 1). INDOT Des # 1400637, City project
# 114-064.
The supplement is to cover additional costs HWC incurred due to a utility not relocating in time
and causing a year long delay to the construction.
It is requested the Board of Public Works approve the Supplement #1 with HWC
Engineering for Inspection of Olive Reconstruction Ph 1 a price increase of of $25,528.
Thank you for your consideration of this request.
January 26, 2022
City of South Bend
Attn: Ms. Leslie Biek, PE
RE: Olive Street Phase I – Des No. 1400637 Supplemental Inspection Agreement Summation
Dear Leslie,
I appreciate you taking the time to discuss the proposed supplemental fee for the Olive Street Phase I project. Described
below are some of the major bullet points to justify the request for this supplemental agreement. Also included in this
enclosure is the formal supplemental contract with man-hour justification.
As of this letter, HWC has exhausted its entire original contract amount and is respectively requesting the City consider the
attached supplemental fee. In an effort to partner with the City and extend the original budget, HWC has absorbed some
previous overtime hours and tried to be effective with our initial budget throughout the 2020 utility relocation phase.
Our initial fee proposal was drafted in December 2019 based on the anticipated project costs and project timeline known at
that time. Throughout the life cycle of the project, HWC attempted to mitigate our budget by having our inspection staff help
on alternate projects when appropriate, and we also requested the two sub-consultants for this project only work on the
project when critical path operations were being performed.
Our requested overage is due to two primary reasons. Additional efforts were required by HWC staff to help with utility
coordination issues during the 2020 construction season prior to formal construction efforts by the contractor. As you are
aware, these utility delays resulted in a full year extension of the project completion date. This resulted in significant efforts
by the HWC team to assist with utility coordination and host utility coordination meetings. Secondly, the project has sustained
13 total change orders. Although processing change orders is an assumed part of our initial fee, we could not have anticipated
this amount of change orders and the significant effort in coordinating, processing, and executing the work required by the
change orders.
HWC is requesting a supplemental fee amount of $25,528.00 hourly, not to exceed. We will continue to minimize our effort
during the final record process to efficiently close out the project on behalf of the city.
We thank you for the opportunity to continue serving the City of South Bend and look forward to a successful completion of
this project.
Respectfully,
HWC Engineering
Jon Day
Construction Inspection Services Manager
Cc: James Rice
Page 1 of 2
LPA – CONSULTING CONTRACT
SUPPLEMENT #1
This is a Supplemental Contract, entered into by City of South Bend, a local public
agency, (hereinafter referred to as LPA) and HWC Engineering (hereinafter to as
CONSULTANT).
WHEREAS, the LPA and CONSULTANT entered into a Contract, providing for the
necessary Construction Inspection Services for the Reconstruction of Olive Street from Prairie
Avenue to Tucker Drive required in connection with INDOT Project Number 1400637, dated
December 10, 2019
WITNESSETH
WHEREAS there exists a need to modify the inspection agreement not to exceed amount
to allow for additional inspection. The original HWC budget for the project did not account for
the extensive utility relocation efforts needed during the 2020 construction season. As per
change order #1, the contract was extended a full year to due to these utility delays. There were
also additional efforts by HWC to host several utility coordination meetings in 2020 and create
and process stored material change orders due to these delays. We are modifying the inspection
agreement to allow for the extra time associated with these items.
THEREFORE, it is necessary to amend the Contract as follows:
1. APPENDIX “D”, Compensation:, A.1 is amended to read as follows:
1. The CONSULTANT shall receive as payment for the work performed under
this Contract the total amount not to exceed $ 474,040.95, unless a
supplement is executed by the parties that increases the maximum amount
payable. This adjusted not to exceed fee provides for an additional
$25,528.00 for inspection and travel expenses (mileage).
2. All other matters previously agreed to and set forth in the original Contract dated
December 10, 2019 are not affected by this Supplement shall remain in full force
and effect.
Page 2 of 2
The undersigned attests, subject to the penalties for perjury, that he/she is the LPA, or that he/she is
the properly authorized representative, agent, member or officer of the LPA, that he/she has not,
nor has any other member, employee, representative, agent or officer of the LPA, directly or
indirectly, to the best of his/her knowledge, entered into or offered to enter into any combination,
collusion or agreement to receive or pay, and that he/she has not received or paid, any sum of
money or other consideration for the execution of this Contract other than that which appears upon
the face of this Contract.
HWC Engineering
Signature
Terry M. Baker, President
Date
February 22, 2022
HWC Engineering (Prime Consultant)
I.Resident Inspection MANHOURS RATE/HOUR*COSTS
Senior Project Manager 0 $207.15 -$
Project Manager 0 $158.03 -$
Inspection Group Manager 5 $157.10 785.50$
Senior Construction Inspector 200 $120.69 24,138.00$
Sr. Const. Inspection (overtime)0 $140.66 -$
Construction Inspector 0 $101.66 -$
Construction Inspector (overtime)0 $118.48 -$
Design Engineer 0 $137.40 -$
Landscape Architect 0 $141.68 -$
Designer/Technician 0 $103.19 -$
Engineering Intern 0 $46.05 -$
Engineering Intern (overtime)0 $53.67 -$
Clerical Support 0 $81.86 -$
205 24,923.50$
Total Labor costs-HWC 24,923.50$
Direct Expenses-HWC 604.50$
DBE Subcontractor McCormick Engineering LLC 5%$0.00
I.Total Inspection Costs 25,528.00$
Direct Expense Summary
Mileage Weeks Miles/Week Total mileage $0.39/mile
Inspection Manager 1 300 300 $117.00
Construction Inspector 0 100 0 $0.00
Senior Construction Inspector 5 250 1250 $487.50
Direct Expenses Total $604.50
Note: Mileage rate of $.39 based on INDOT mileage reimbursement rate dated July 11, 2016. Mileage rate will be adjusted to match
current INDOT rate should a new rate be implemented during course of this contract.
Travel reimbursement will be paid as described in the most current State of Indiana travel policy
One full time senior inspector is expected to be required for 5 weeks (0 hours preconstruction, 0 hours construction, 200 hours final records).
Inspection manager to visit site 1 time to help finish final records.
2018-19 INDOT approved rates
INDOT
approved
rate
INDOT
approved
overhead
rate
162.07%
Allowable 15%
profit FCCM (0.84%)
Total rate/hour
for 2019-20
Total rate/hour
for 2020-
21**Effective
7/1/20
Total rate/hour for
2021-
22**Effective
7/1/21
Calculations for hourly rates
Senior Project Manager $64.86 $105.12 $25.50 $0.54 $196.02 $201.70 $207.15
Project Manager $49.48 $80.19 $19.45 $0.42 $149.54 $153.88 $158.03
Inspection Manager $49.19 $79.72 $19.34 $0.41 $148.66 $152.97 $157.10
Senior Construction Inspector $37.79 $61.25 $14.86 $0.32 $114.21 $117.52 $120.69
Sr. Const. Inspection (overtime) $56.69 $61.25 $14.86 $0.32 $133.10 $136.96 $140.66
Construction Inspector $31.83 $51.59 $12.51 $0.27 $96.20 $98.99 $101.66
Construction Inspector (overtime) $47.75 $51.59 $12.51 $0.27 $112.11 $115.36 $118.48
Design/Project Engineer $43.02 $69.72 $16.91 $0.36 $130.02 $133.79 $137.40
Landscape Architect $44.36 $71.89 $17.44 $0.37 $134.07 $137.95 $141.68
Designer/Technician $32.31 $52.36 $12.70 $0.27 $97.65 $100.48 $103.19
Engineering Intern $14.42 $23.37 $5.67 $0.12 $43.58 $44.84 $46.05
Engineering Intern (overtime)$21.63 $23.37 $5.67 $0.12 $50.79 $52.26 $53.67
Clerical Support $25.63 $41.54 $10.08 $0.22 $77.46 $79.71 $81.86
INDOT Des. 1400637
City of South Bend
Inspection Fee Man-hour Justification Supplemental #1
Olive Street Reconstruction Phase I
HWC Engineering
1
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 1/27/2022
Name Leslie Biek, PE Department PW
BPW Date 2/22/2022 Phone Extension 9323
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer Officer Name
BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name HWC Engineering INC
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Olive Road Reconstruction Ph 1
Project Number 114-064 PROJ- 59
Funding Source
Account No. PO 1776
Amount $25,528
Terms of Contract
Purpose/Description Amendment #1 is for additional inspection services needed for Olive Ph 1 due
to utilities not relocating in time and delaying the project. This caused
additional utility and contractor coordination as well as a year delay.
For Change Orders Only
Amount of Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: