1. REVIEW OF MINUTES
A. Approve Agenda Review, and Regular Meeting Minutes of February 3, and
February 8, 2022
2. OPENING OF QUOTATIONS
A. Walker Field Park Shelterhouse Restoration – Project No. 120-010
1. Funding: PR-00014932
B. 2022 Biosolids Trucking for Land Application Annual Contract – Project No.
122-031
1. Funding: PR-00015085
3. OPENING OF PROPOSALS
A. Bendix Improvements, Phase II - Lathrop to Voorde – Project No. 121-047
B. Safe Routes to School - Muessel Primary and Holy Cross Area – Project No. 122-
006
1. Funding: INDOT DES #1900447
4. AWARD BIDS AND APPROVE CONTRACTS
A. 2021 Community Crossings, Round II – Project No. 121-052
1. Company: Rieth-Riley Construction Co., Inc.
2. Amount: $1,271,724.40
3. Funding: PR-00013986
5. CHANGE ORDERS
A. Olive Street Reconstruction, Phase I – Project No. 114-064
1. Company: INDOT & Milestone Contractors North, Inc.
2. Change Order No.: 12
3. Increase Amount: $3,997.40; Total ($799.48 Local)
4. Percent of Increase: 0.12%
5. Total Percent of Change: 13.73%
6. Revised Contract Amount: $3,796,759.83
7. Funding: PO-0009357
B. Howard St. and Corby Blvd. Streetscape Improvements – Project No. 120-024
1. Company: Milestone Contractors North, Inc.
2. Change Order No.: 1
3. Increase Amount: $36,365.48
4. Percent of Increase: 6.34%
5. Revised Contract Amount: $610,365.48
6. Funding: PO-0009355
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
AGENDA REVIEW SESSION
February 17, 2022 – 10:30 a.m.
Virtual Meeting Link https://tinyurl.com/2022BPWAgendaReview
1308 County-City Building, South Bend, IN 46601
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
Page 2
C. Wastewater Treatment Plant Final Clarifier Nos. 4-5, Aeration Tank Nos. 1-4, and
Disinfection Improvements – Project No. 119-069A
1. Company: Bowen Engineering Corporation
2. Change Order No.: 2
3. Increase Amount: $83,668.03
4. Percent of Increase: 1.94%
5. Total Percent of Increase: 3.13%
6. Revised Contract Amount/Completion Date: $4,406,803.96; May 17, 2022
7. Funding: PO-0005021
6. CHANGE ORDERS AND PROJECT COMPLETION AFFIDAVITS
A. West Side Quiet Zone Improvements – Project No. 117-114A
1. Company: Rieth-Riley Construction Co, Inc.
2. Change Order No.: 1 (Final)
3. Decrease Amount: ($1,890.96); Additional One-Hundred and Seventeen (117)
Days
4. Percent of Decrease: (5.90%)
5. Total Percent of Change: (5.90%)
6. Final Contract Amount:/Completion Date $30,145.20; December 16, 2021
7. Funding: PO-0006390
B. Wastewater Treatment Plant Electrical Improvements – Project No. 117-132
1. Company: Martell Electric
2. Change Order No.: 2
3. Increase Amount: No Cost
4. Total Percent of Increase: 1.33%
5. Revised Contract Amount/Completion Date: $6,416,399; December 31, 2021
6. Funding: PO-0000075
7. PROJECT COMPLETION AFFIDAVITS
A. 905, 907, 909 Michigan Demolition – Project No. 120-063R
1. Company: Green Demolition Contractors, Inc.
2. Final Contract Amount: $179,800
3. Funding: PR-00008115
8. REQUEST TO ADVERTISE FOR THE RECEIPT OF BIDS
A. 2022 Street and Sewer Material Bid – Project No. 122-028
1. Funding: PR-00015077
B. 2022 Asphalt Materials Bid – Project No. 122-029
1. Funding: PR-00015079
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
AGENDA REVIEW SESSION
February 17, 2022 – 10:30 a.m.
Virtual Meeting Link https://tinyurl.com/2022BPWAgendaReview
1308 County-City Building, South Bend, IN 46601
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
Page 3
9. RESOLUTIONS
A. Resolution No. 04-2022
A Resolution of the City of South Bend, Indiana Board of Public Works
Authorizing the Transfer of Real Property of the South Bend Building
Corporation
1. Description: Transfer of City Property to Building Corporation; Segment of
Wall St. and Segment of Greenlawn Ave. for Potawatomi Zoo Improvements
B. Resolution No. 05-2022
A Resolution of the City of South Bend, Indiana Board of Public Works for the
Disposal of Surplus Property
1. Description: Retirement of Detective Galen Pelletier’s Firearm
C. Resolution No. 06-2022
A Resolution of the City of South Bend, Indiana Board of Public Works for the
Disposal of Surplus Property
1. Description: Retirement of Patrolman First Class Kenneth Ryan’s Firearm
D. Resolution No. 07-2022
A Resolution of the City of South Bend, Indiana Board of Public Works for the
Disposal of Surplus Property
1. Description: Retirement of Patrolman First Class Michael VanVynckt’s
Firearm
E. Resolution No. 08-2022
A Resolution of the City of South Bend, Indiana Board of Public Works
Authorizing Staff to Effectuate the Acquisition of Certain Real Property
1. Description: Authorizing Payment of Acquisition of Property through
Condemnation Proceedings for East Bank Trail
F. Resolution No. 09-2022
A Resolution of the City of South Bend, Indiana Board of Public Works
Accepting Transfer of Real Property from Cross Community, Inc.
1. Description: Properties at 620 and 722 Sherman Ave., South Bend, IN
10. AGREEMENTS/CONTRACTS/PROPOSALS/ADDENDA
A. Amendment No. 1 to LPA Consulting Contract – HWC Engineering
1. Description: Additional Inspection Services due to Utilities Delaying Project
One (1) Year for Olive Road Reconstruction, Phase I Project No. 114-064
2. Amount: NTE $25,528
3. Funding: PO-0001776
B. Professional Services Agreement – A&Z Engineering, LLC
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
AGENDA REVIEW SESSION
February 17, 2022 – 10:30 a.m.
Virtual Meeting Link https://tinyurl.com/2022BPWAgendaReview
1308 County-City Building, South Bend, IN 46601
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
Page 4
1. Description: Design Services for 2022 Community Crossing Roadway
Rehabilitation Project No. 122-024 for Five (5) City Streets
2. Amount: $318,350
3. Funding: PR-00014717
C. Uniform Property or Easement Acquisition – April Bouchard & Tracie Bouchard
1. Description: Access and Installation of Water Main Near 22708 State Road 23
South Bend for Prairie Ave. Water Main Loop Project No. 117-068
2. Amount: $5,909.70 (50% to Each Owner)
3. Funding: PR-00012637
D. Professional Services Agreement – Black and Veatch Corporation
1. Description: Engineering Services for Century Center Electrical & HVAC
Improvements, Project No. 122-017
2. Amount: $65,635
3. Funding: PR-00014781
E. Amendment No. 1 to Owner-Engineer Agreement – Christopher B. Burke
Engineering, LLC
1. Description: Provide As Needed, On-Call Support to Implement the
Impervious Cover-Based Stormwater Utility Project No. 119-010
2. Amount: NTE $23,010.76 (Hourly); Adjusted Total Amount: $98,510.76
3. Funding: PO-0000355
F. Professional Services Agreement – Alliance Architects
1. Description: Design Services for Roof Repairs for Studebaker Museum
Project No. 122-030
2. Amount: NTE $16,500 (Hourly)
3. Funding: PR-00015075
G. Professional Services Agreement – Christopher B. Burke Engineering, LLC
1. Description: Inspection Services for Prairie Avenue Water Main Loop Project
No. 117-068
2. Amount: NTE $83,500 (Hourly)
3. Funding: PR-00014858
H. 2022 Indemnification Agreement – The Tire Rack, Inc.
1. Description: City Usage of Tire Rack’s Training Track for Police Emergency
Vehicle Operations Training March 30, 2022 through October 28, 2022
I. Right-of-Way Occupancy Agreement – Lykowski Construction, Inc., and Indiana
Landmarks
1. Description: Encroachment for House Move from 130 Park Ln. to 846 Park
Ave. South Bend
J. Amendment No. 5 to Owner-Engineer Agreement – SmithGroup Inc.
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
AGENDA REVIEW SESSION
February 17, 2022 – 10:30 a.m.
Virtual Meeting Link https://tinyurl.com/2022BPWAgendaReview
1308 County-City Building, South Bend, IN 46601
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
Page 5
1. Description: Additional Construction Administrative Services for Seitz Park
Reconstruction, Phase I Project No. 117-093
2. Amount: NTE $74,956 (Hourly); Total Adjusted Amount $1,139,716
3. Funding: PO-0006606
K. Streetlight Service Agreement – Indiana Michigan Power Company
1. Description: Contract Approved in 2020, LED Street Light Upgrades and
Associated Rates, Indiana Utility Regulatory Commission Cause No. 45285
L. Professional Services Agreement – Danch, Harner, and Associates, Inc.
1. Description: Prepare ALTA/NSPS Land Title Survey for 215 Martin Luther
King Jr. Blvd. (SBSC Administrative Building)
2. Amount: $3,550 (Hourly); 33-40 Days
3. Funding: Department of Community Investment
11. LICENSES AND PERMITS
A. Street Closures for Special Events
1. Event: Chet Waggoner Little League Opening Day Parade
a) Date/Times: April 23, 2022; 7:00 a.m. to 9:00 a.m.
b) Location: Wilber St. to Portage Ave., Continuing to Boland and Riverside
Dr. to Park
2. Event: St. Patrick’s Day Parade
a) Date/Times: March 12, 2022; 9:30 a.m. to 12:30 p.m.
b) Location: E. Jefferson Blvd. from S. Frances St. to Niles Ave., Niles Ave.
from Jefferson Blvd. to Washington St., Washington St. to Niles Ave. to
N. Hill Ave.
B. Encroachments/Revocable Permits
1. Applicant: Aloft South Bend
a) Location: 111 N. Main St.
b) Description: Pergola on Front of Building to Extend Patio
c) Favorable Recommendations/See Comments
12. STREET/ALLEY VACATIONS
A. Applicant: Mr. Mike Danch - Five Corners, LLC
1. Location: Alley at 1200 Block of Howard St.
2. Purpose: Allow Mixed-Use Development
3. Favorable Recommendations and Meets All I.C. 36-7-3-13 Criteria
B. Applicant: Ms. Maggie VanZalen – Transformation Ministries
1. Location: Street and Alley near 1101 King St., See Description
2. Purpose: Development of Transformation Ministries
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
AGENDA REVIEW SESSION
February 17, 2022 – 10:30 a.m.
Virtual Meeting Link https://tinyurl.com/2022BPWAgendaReview
1308 County-City Building, South Bend, IN 46601
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
Page 6
3. See Comments; Public Works, Community Investment & Fire are Favorable
for Alley however, Street Does Not Meet Two (2) of the Four (4) I.C. 36-7-3-
13 Criteria (2,4) and Due to Loss of Fire Hydrant Access
13. TRAFFIC CONTROL DEVICES
A. New Installation – Three (3) Honorary Street Signs
1. Location(s): Napoleon St. & St. Louis Blvd., Napoleon St. & St. Peter St.,
Napoleon St. & Notre Dame Ave.
a) Pastor Leroy Sutton St.
b) All Criteria Met
14. CONSENT TO ANNEXATION AND WAIVER OF RIGHTS TO
REMONSTRATE
A. 53465 Quince Rd. – Sewer
15. RATIFY BONDS
A. Contractor Bonds
1. Larson Danielson Construction, Released effective March 3, 2022
16. CLAIMS
A. Ratification of Preapproved City of South Bend Claims Payments
1. Claim No.: GBLN-30954, GBLN-30955, GBLN-31063
a) Date: 02/07/2022
b) Amount: $415,045.24
2. Claim No.: GBLN-31158, GBLN-31159
a) Date: 02/07/2022
b) Amount: $673,451.55
17. PRIVILEGE OF THE FLOOR
18. ADJOURNMENT
NOTICE
FOR HEARING AND SIGHT IMPAIRED PERSONS
Auxiliary Aid or Other Services are Available upon Request at No Charge.
Please Give Reasonable Advance Request when Possible.