December 14, 2021
Mr. Robert Kuhns
Selge Construction Co., Inc.
2833 South 11TH St.
Niles, MI 49120
aswinehart@selgeconstruction.com
RE: Emergency Sewer Repair – Project No. 121-058
Dear Mr. Kuhns:
At its December 14, 2021 meeting, the Board of Public Works approved the above
referenced memo for the emergency repair of the brick elliptical 48” x 54” sewer at W.
Washington and the former Chapel Lane, Project No. 121-058 in the amount of $98,386.
Enclosed please find a copy of the memo for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Laura Hensley/Acting
Clerk
Enclosures
S:\Public Works\Projects\Projects by Year\2021 Projects\121-058 Emergency Sewer Repair - W Washington & Chapel Ln\1 - Admin\1 - BPW
Documents\20211102_121-058 Emergency Sewer Repair Washington & Chapel_Memo to BPW.doc Page 1
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Board of Public Works
FROM: Sue Ellen Doudrick, PE
SUBJECT: 121-058 Emergency Sewer Repair West Washington and Chapel Lane
DATE: November 22, 2021
On 8/11/2021 a sinkhole formed in West Washington Street near Chapel Lane in front of the
Civil Rights Heritage Center and Notre Dame Center of the Arts and Culture. The sewer is a
brick elliptical sewer 54” x 48” tall. The sinkhole was 15’ wide, 3’ long. Due to the size and depth
(18’ deep to sewer invert) of the sewer along with the complexity of work, a contractor was
needed to assist with the work. Selge Construction and Culy Contracting were contacted and
were both interested in performing work.
Selge met onsite on 8/11. Culy Contracting could not make it onsite and needed to look more
into the data to see if they could perform the work; they also indicated they could not provide an
estimate or mobilize until the following week 8/17 or 8/18. Selge indicated they could mobilize to
the site on 8/12/21 and estimated $50k for a doghouse manhole install. Selge was selected for
the work.
Description of work:
Selge mobilized to site on 8/11/21. The work included excavation and installation of a stacked
trench box on 8/13/21. The box was challenging to install due to the water line parallel to the
sewer and exposed in the sinkhole. The team began making preparations for the doghouse
install on 8/17/21. The work included new doghouse manhole install, water line replacement,
storm lead replacement, and determining limits of sewer repair, followed by backfill and
pavement and surface restoration. Work was completed around 8/21. The Sewer Department
coordinated and provided traffic control to save on costs and coordinated getting the sewer
cleaned by National Power Rodding. Sewer Department and Engineering coordinated with
adjacent businesses to locate clean outs and performed dye testing to make sure no backups
were occurring. Water works was onsite several times to verify no water leaks leading to the
sewer failure.
It was determined that the storm leads at nearly 45 degree angles jetting into the sewer likely
caused the failure due to the turbulence of flow during the heavy rain events in June thru August
of 2021. The business management staff at both the Civil Rights Heritage Center, Notre Dame
Center of the Arts and Culture, and the property owner/manager of the apartments directly in
front of the work area were extremely patient with the contractors and City as well as
understanding of the disruption of access and service. Due to the pandemic, there was not
much required access to each of the businesses.
Pictures of the project are as follows:
S:\Public Works\Projects\Projects by Year\2021 Projects\121-058 Emergency Sewer Repair - W Washington & Chapel Ln\1 - Admin\1 - BPW
Documents\20211102_121-058 Emergency Sewer Repair Washington & Chapel_Memo to BPW.doc Page 2
1. 8/11/2021: sinkhole with water
line shown
2. 8/13/2021: Full road closure on
Washington; ready for
excavation and trench box
install; steel beam used to hold
water line in place.
3. 8/13/21: Trench box
mobilization; tight fit due to
above and below grade utilities
S:\Public Works\Projects\Projects by Year\2021 Projects\121-058 Emergency Sewer Repair - W Washington & Chapel Ln\1 - Admin\1 - BPW
Documents\20211102_121-058 Emergency Sewer Repair Washington & Chapel_Memo to BPW.doc Page 3
4. 8/17/21: Crew making a plan for
how to cut out top of brick
sewer without bottom and sides
of pipe caving in and washing
away the base of the new
doghouse manhole; sewer
lateral from the south was
coming in and had to be
protected as well.
5. 8/18/21: crew installed base of
doghouse manhole
6. 8/18/21: Base of doghouse
installed
S:\Public Works\Projects\Projects by Year\2021 Projects\121-058 Emergency Sewer Repair - W Washington & Chapel Ln\1 - Admin\1 - BPW
Documents\20211102_121-058 Emergency Sewer Repair Washington & Chapel_Memo to BPW.doc Page 4
7.8/19/2021: installation was a
success
Contractor estimated the work to be $50,000, which was based on install of doghouse manhole.
The final cost of the work was $98,386 out of the following account 641-06-602-509-439001.
The estimate was exceeded due to:
a.Water line repair;
b.Storm lead repairs;
c.Pavement patch was full width across the street;
d.Challenges due to difficulty digging around the existing utilities (water and laterals).
December 14, 2021
From:Michael Schmidt
To:Laura Hensley
Subject:RE: DFO Question?
Date:Thursday, December 2, 2021 8:53:15 AM
Attachments:image001.png
Good question. Those PO’s were issued as a result of emergency situations which bypasses the
traditional workflow. However, with emergency public work projects, the Board does need to
retroactively approve the transaction. Thus, you will not see these come through workflow in the
traditional sense. Sue Ellen should provide you with the necessary paperwork to have these items
on the BPW agenda.
Does that make sense?
From: Laura Hensley <lhensley@southbendin.gov>
Sent: Thursday, December 2, 2021 8:34 AM
To: Michael Schmidt <mschmidt@southbendin.gov>
Subject: DFO Question?
Good morning, Michael,
I am new to this process and, am just wondering if since these have a PW-RQ code, should I assume,
these will be routing to my queue? I have them both scheduled to be on the next agenda on
December 14, 2021. Please advise?
A. Emergency Sewer Repair – Selge Construction Co., Inc.
1. Description: Emergency Repair of Brick Elliptical 48” x 54” Sewer at W. Washington
and Former Chapel Lane Project No. 121-058
2. Amount: $98,386
3. Funding: PO-0011161
B. Emergency Sewer Repair – Selge Construction Co., Inc.
1. Description: Emergency Repair of an 18” Sewer at Dubail Ave. under Bowman Creek
2. Amount: $38,969.85
3. Funding: PO-0011385
Thanks so much and hope you’re having a great day!
Laura Hensley
Administrative Assistant
Department of Public Works
(574) 235-5927
lhensley@southbendin.gov
City of South Bend
227 W. Jefferson Blvd., Ste. 1316
South Bend, IN 46601
Excellence | Accountability | Innovation | Inclusion | Empowerment
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 11/22/2021
Name Sue Ellen Doudrick Department DPW
BPW Date 12/14/2021 Phone Extension 5922
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title
Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. __ PCA
Chg. Order, No. 3 Traffic Control Resolution
Other: Emergency Repair
Memo
Ease./Encroach
Required Information
Company or Vendor Name Selge
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name W Washington & Chapel Lane – Emergency Sewer Repair
Project Number 121-058
Funding Source Sewer Utilities
Account No. 641-06-602-509-439001
Amount $98,386
Terms of Contract Lump Sum
Purpose/Description Emergency Repair of a brick elliptical 48” x 54” sewer in W. Washington
and former Chapel Lane (near the Civil Rights Heritage Center and Notre
Dame Center of the Arts and Culture properties)
For Change Orders Only
Amount of
Increase
Decrease
($)
Previous Amount
Current Percent of Change:
Increase
Decrease
%
(%)
New Amount
Total Percent of Change:
Increase
Decrease
%
(%)
Time Extension Amount: 0
New Completion Date: -