HomeMy WebLinkAboutChange Order No 1 - Guardrail Replacement and Installation Proj No. 118-084 - Northern IN Construction Co., Inc.  ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER 1316 COUNTY-CITY BUILDING 227 W. JEFFERSON BOULEVARD SOUTH BEND, INDIANA 46601-1830 PHONE 574/ 235-9251 FAX 574/ 235-9171 CITY OF SOUTH BEND JAMES MUELLER, MAYOR BOARD OF PUBLIC WORKS December 14, 2021 Mr. David J. Walorski Northern Indiana Construction Co., Inc. PO Box 1333 Mishawaka, IN 46546 dmarable.nic@gmail.com; davidwalorski@cs.com RE: Change Order No. 1 – Guardrail Replacement and Installation Project No. 118-084 Dear Mr. Walorski: At its December 14, 2021 meeting, the Board of Public Works approved the above referenced Change Order for an increase of $45,061.58 with an additional two hundred & thirteen (213) days, bringing the revised contract amount to $349,306.78 with a new completion date of December 31, 2021. Enclosed is a copy of the Change Order for your records. If you have any further questions regarding this matter, please call this office at (574) 235-9251. Sincerely, /s/ Laura Hensley/Acting Clerk Enclosures December 14, 2021 DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING Project Number: _______________ Project Name: __________________________ Change Order #: ____ DATE INITIATED: BPW DATE: Brief Summary of Change Order; (Construction Change, Alternative, Substitution, Differing Instructions, Out of Scope, Etc.). Attachments: (List documents support change – required) Amount of ☐Increase / ☐Decrease: $____________________ Categories (Pick One): ☐Scope of Work ☐Differing Site Conditions, Changed Conditions ☐Conflicted Specifications and Drawings ☐Failed Materials ☐Error ☐Omission ☐Final Quantity Adjustment ☐_______________________ Previously approved Change Order(s): $___________________ Current Percent of Change: ____________________ % New Total Amount: $____________________ Total Percent of Change: ____________________ % Funding Secured From: __________________________ (filled out by PM) RECOMMENDED BY: Project Inspector (Print Name) (Signature) (Date) REVIEWED BY: Construction Manager (Print Name) (Signature) (Date) APPROVED BY: Engineering Project Manager (Print Name) (Signature) (Date) Net deduct from base bid ($41,661.42); Add $86,724.00 for additional guardrail in various locations 10/29/2021Finnian Cavanaugh PO-0006554 12/14/2021 BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date: November 17, 2021 Name: Finnian Cavanaugh Department of Public Works – Engineering Division BPW Date: December 14, 2021 Phone Extension: 5961 or fcavanau@southbendin.gov Required Prior to Submittal to Board BPW Attorney X Attorney Name Clara McDaniels Dept. Attorney Attorney Name Purchasing Check the Appropriate Item Type – Required for All Submissions Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA Chg. Order, No. 1 Traffic Control Resolution Other: Ease./Encroach Required Information Company or Vendor Name Northern Indiana Construction Company Inc. New Vendor Yes If Yes, Approved by Purchasing No MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name Guardrail Repair and Installation Project Number 118-084 Funding Source PO-0006554 Account No. 251-06-600-506-436008—PROJ00000221 ($18,769.80) 667-06-600-506-442002—PROJ00000221 ($26,291.78) Amount $45,061.58 addition ($349,306.78 new total) Terms of Contract NTE Purpose/Description Deduct from base bid -$41,661.42, add guardrail replacement at additional locations +$86,724.00, for net addition to contract of +$45,061.58. For Change Orders Only Amount of Increase Decrease $ 45,061.58 ($ ) Previous Amount $ 304,245.20 Current Percent of Change: Increase Decrease 14.81% ( %) New Amount $ 349,306.78 Total Percent of Change: Increase Decrease 14.81% ( %) Time Extension Amount: 213 days New Completion Date: 12/31/2021