November 9, 2021
Mr. Dustin Hilary
Milestone Contractors North, Inc.
24358 State Road 23
South Bend, IN 46614
akrueger@milestonelp.com
RE: Change Order No. 4 – River Walk from Beyer Street to Howard Park
Project No. 117-083A
Dear Mr. Hilary:
At its November 9, 2021 meeting, the Board of Public Works approved the above
referenced Change Order for an increase of $6,268.50 with an additional ninety-eight (98) days,
bringing the revised contract amount to $3,329,034.78 with a new completion date of September
24, 2021.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Laura Hensley/Acting
Clerk
Enclosures
November 9, 2021