Coal Line Trail Phase II
October 26, 2021
Page 1
October 26, 2021
Dear Mr. Silveus:
Trail projects can appear to be a walk in the park to those of us in the engineering field, but
to the many families and businesses adjacent to the project that must adjust their lives during
construction, it becomes inconvenient and frustrating without effective communications
and coordination by an experienced construction team. The City of South Bend’s Coal Line
Trail, Phase II project will benefit from a construction management team who can bring
solid communication skills, recent trail experience, seamless construction coordination, and
familiarity with the project area.
Burke has experience working for the City on many different challenging construction inspection
projects. Our team knows and understands your process. This knowledge, experience, and
longstanding established relationship provides us with the necessary tools to avoid gaps or
missteps in the construction management process.
Our proposed subconsultant, Advanced Engineering Services, completes our construction
management team. AES is a registered MBE/DBE and they will be a key member to our team
by providing crucial material testing and geotechnical support. Our commitment to detail and
strong communications has afforded us a reputation as a professional team that can address
nearly any construction issue, even an accidental discovery like the one found on the Boland
Trail project.
We applaud your efforts to improve the trail connectivity in South Bend and we look forward
to working with you during the construction of this project. Thank you in advance for your
consideration.
Sincerely,
Jon D. Stolz, PE
Managing Vice President
jstolz@cbbel-in.com
C City of South Bend
Coal Line Trail Phase II
cbbel-in.com | 888.463.1974
Table of Contents
Firm Profile ............................................................Page 2
Project Team ..........................................................Page 3
Relevant Experience .............................................Page 7
Project Approach ................................................Page 10
Project Team
Christopher B. Burke Engineering, LLC
Team Lead (95%)
220 W. Colfax Ave., Ste 700
South Bend, IN 46601
Advanced Engineering Services (MBE)
Material Testing/Geotechnical (5%)
7439 Calumet Ave.
Hammond, IN 46324
City of South Bend
Coal Line Trail Phase II
October 26, 2021
Page 2
FIRM PROFILE
Stemming from water resources, our passion to enhance and
preserve our environment has deepened through exciting and
diverse projects. This passion drives our staff to deliver the
exceptional service our clients have come to expect. Christopher
B. Burke Engineering, LLC, provides planning, design and
construction management services for municipal and private
infrastructure projects ranging from transportation and
recreation to flood control and environmental management.
When it comes to construction engineering, Burke engineers
have tackled multi-year tunneling projects, week-long ADA
update projects, and everything in between. Inspections
involve not only visually confirming construction practices
but also coordinating teams in sometimes difficult situations.
Burke’s commitment to communication means fair and
effective management in the ability to address nearly any
construction issue.
Services
Underground infrastructure
Dam and levee inspection
Private development
Sewer rehabilitation
Roadway and trail construction
Small structure replacement
52 18
professionalssolving problems years servingSouth Bend
4 8
officesacross Indiana INDOT-
certified inspectors
Burke by the numbers
“With their skills in effective
communication and proactive
problem solving, Burke
successfully managed the design
and construction team and
worked in our best interest,
helping us stick to our budget
and achieve our goals.
Officer Chad Gray
Special Projects Coordinator
Indianapolis Police Department
”
City of South Bend
Coal Line Trail Phase II
October 26, 2021
Page 3
City of South Bend
Kyle Silveus
Mike Carey
Project Engineer /
Project Supervisor
Jason Durr
Project Manager /
Principal in Charge
T.J. Gordon
Highway Technician
Daniel Parrett
Highway Technician
Burke Team
AES Team
Akhtar Zaman
Principal Geotechnical
Engineer
Jose Vargas
Project Manager/
Senior Inspector
Paul Taylor
Field & Lab Technician
ORGANIZATIONAL CHART
Below is an organizational chart depicting the Burke project team. Led by our South
Bend office’s project engineer/project supervisor Mike Carey, our local team offers
the knowledge and capacity to successfully complete the Coal Line Trail, Phase II
project. Our team includes Advanced Engineering Services, with whom Burke has
worked on several projects. We believe that our strong relationship and technical
expertise will be instrumental in providing efficient, responsive and creative solutions
for the trail project. We have assembled our team members based on availability
as well as technical expertise. Each firm has the depth and capacity to successfully
complete the project in a timely manner. Specifically, Mike will be 100% available for
this project based on his current and projected workload.
City of South Bend
Coal Line Trail Phase II
October 26, 2021
Page 4
PROJECT TEAM
EDUCATION
Bachelor of Science
Civil Engineering
Michigan State University
REGISTRATIONS
Professional Engineer
IN, MI
CERTIFICATIONS
FEMA Certified
IS-00100, PW
FEMA Certified IS-00200
With nearly two and a half decades of experience,
Jason serves as Burke’s director of northern Indiana.
His experience in both engineering and environmental
roles has allowed him to develop an understanding of
not only infrastructure needs and requirements, but
also the ability to design and manage projects as an
environmental steward. He is also active in the Indiana
chapter of the American Society of Civil Engineers,
having served on the board for the past four years.
RELEVANT EXPERIENCE
• Boland Drive Improvements Construction
Inspection, South Bend, IN
• South Main Street Streetscape, Elkhart, IN
• Berens Monaldi Drainage and Roadway
Improvements, Dyer, IN
• Ireland Road Intersection Improvements, South
Bend, IN
• Mascot Hall of Fame Site and Parking Lot
Design, Whiting, IN
• 117th Street Sewer and Water Replacement
Project, Whiting, IN
• Beckett’s Run Relocation Project,
Fort Wayne, IN
• Upper Beaver Lake East Lateral Ditches,
Newton County, IN
• Eisenhower Detention Basin Design and
Downstream Drainage Report, Warsaw, IN
• Weasel Creek Regulated Drain Maintenance
Design, Grant County, IN
• 5 Points Utility Relocation Report,
South Bend, IN
EDUCATION
Bachelor of Science
Mechanical Eng. Tech.
Purdue North Central
CERTIFICATIONS
American Concrete Institute -
Concrete Field Testing
Technician - Grade I
Confined Space Entry
OSHA Construction Safety
and Health
INDOT Certified Technician:
• Bridge Construction &
Deck Repair
• Construction Earthworks
• Constr. Procedures Part 1
• Constr. Procedures Part 2
• Hot Mix Asphalt Paving
• Concrete Paving
Mike will lead the Burke team for the Coal Line Trail
project. He has nearly 15 years of experience, including
working for South Bend’s engineering department,
giving him a familiarity with municipal projects and
procedures. Mike’s responsibilities include planning,
analysis, design, and review of site development,
utility and stormwater, and roadway design projects.
He coordinates with clients and government agencies,
prepares contract documents, and assists with project
bidding and construction administration.
RELEVANT EXPERIENCE
• Boland Drive Improvements Construction
Inspection, South Bend, IN
• Berens Monaldi Neighborhood Drainage and
Roadway Improvements, Dyer, IN
• South Main Street Streetscape Improvements,
Elkhart, IN
• High and Ireland Intersection Improvements,
South Bend, IN
• Weasel Creek Regulated Drain Maintenance
Design, Grant County, IN
• Chet Waggoner Court Construction
Observation, South Bend, IN
• Eisenhower Detention Basin Design,
Warsaw, IN
• Carmel Creek Floodway Permit and Letter of
Map Revision, Carmel, IN
• Sheetz Hardiman Tile Reconstruction, Benton
County, IN
• Mascot Hall of Fame Site and Parking Lot
Design, Whiting, IN
JASON DURR, PE
Project Manager / Principal in Charge
MIKE CAREY
Project Engineer / Project Supervisor
City of South Bend
Coal Line Trail Phase II
October 26, 2021
Page 5
PROJECT TEAM
CERTIFICATIONS
Certified Inspector of
Sediment & Erosion Control
Daniel provides both part- and full-time construction
inspection services for a variety of projects, from
large-scale tunnels to on-call stormwater projects
for private clients. He also is a certified inspector
of soil and erosion control and regularly provides
stormwater inspection services for multiple clients.
Daniel has always been interested in construction, and
specifically the construction of water transportation
systems.
RELEVANT EXPERIENCE
• City of Indianapolis Pennsy Trail Phase 3B,
Indianapolis, IN
• Taggart Memorial Restoration and Performance
Venue, Indianapolis, IN
• Franklin and Perry Townships Drainage
Improvements, Indianapolis, IN
• 21st & Butler Neighborhood Drainage
Improvements Phase II, Indianapolis, IN
• 37th & Lafayette/Washington & Burke Drainage
Improvements, Indianapolis, IN
• City of Indianapolis Department of
Neighborhood and Business Services On-call
Inspection Services, Indianapolis, IN
• Fall Creek Tunnel CCS Inspection,
Indianapolis, IN
• Lower Pogues Tunnel CCS Inspection,
Indianapolis, IN
• Upper Pogues Abatement Inspection,
Indianapolis, IN
• Service Area 21 Water and Sewer Extension
Inspection, Lafayette, IN
EDUCATION
Bachelor of Science
Civil Engineering;
Construction
Valparaiso University
CERTIFICATIONS
INDOT Site Manager
INDOT Certified Technician
American Concrete Institute
Concrete Field Testing
Technician - Grade 1
IDOT Documentation of
Contract Quantities
T.J. works closely with other staff to provide
construction observation, project reports,
documentation of quantities, pay estimates,
coordination of material testing and inspection, site
surveys, and interaction with the contractor and
client. T.J. is skilled in various software, including
AutoCAD, RISA 3-D Modeling, Inventor Modeling,
Microstation V8i, and Microsoft Office. He is
passionate about helping clients find sustainable and
cost-saving solutions to stormwater problems.
RELEVANT EXPERIENCE
• South Shore Stormwater Improvement Project,
Cedar Lake, IN
• Squirrel Creek Diversion/Midway Drive
Detention Expansion, South Haven, IN
• Taft Street Construction Services, Merrillville,
IN
• Lake County On-call MS4 Coordination
Services, Lake County, IN
• 129th Avenue Road Improvements,
Cedar Lake, IN
• Town Club Ditch Water Quality/BMP
Improvement Project, Cedar Lake, IN
• NIPSCO Gas Pipeline Project, South Bend, IN
• Martha Street Storm Sewer Improvement,
Highland, IN
• 133rd Avenue Reconstruction, Cedar Lake, IN
• Little Calumet Watershed Study, Lake County
Surveyor’s Office, IN
• Town Engineer Services, Cedar Lake, IN
T.J. GORDON
Highway Technician
DANIEL PARRETT, CISEC
Highway Technician
City of South Bend
Coal Line Trail Phase II
October 26, 2021
Page 6
REGISTRATIONS
Professional Engineer
IN, IL, MI, WI
LEED AP BD+C
CERTIFICATIONS
OSHA 40-hours HAZOPER
OSHA 30-hours Construction
Safety and Health
ABET Program Evaluator
for Civil Engineering
Accreditation Programs
RELEVANT EXPERIENCE
• CN Underpass on 45th Street, Munster, IN
• Wisconsin Street Bridge over Lake George,
Hobart, IN
• Bridges along Interstate 65 over Kankakee River,
Lake/Newton Counties, IN
• Railroad Relocation at Gary International
Airport, Gary, IN
• Main Street Bridge over Hart Ditch, Munster, IN
• Chase Street Bridge over Little Calumet River,
Gary, IN
• Little Calumet River Levee, Lake County, IN
• Wolf Lake Pedestrian Bridge over Calumet
Avenue, Hammond, IN
• State Road 249 Bridge over US Route 12 and
Railroad Tracks, Porter County, IN
AKHTAR (ART) ZAMAN, PE
PRINCIPAL GEOTECHNICAL ENGINEER
CERTIFICATIONS
ACI Concrete Field
Technician Level 1
ACI Concrete Laboratory
Technician Level 1
ACI Aggregate Laboratory
Technician Level 1
INDOT Approved Field and
Lab Technician
10-Hour OSHA & 8 Hour
Confined space entry training
RELEVANT EXPERIENCE
• Wolf Lake Pedestrian Bridge over Calumet
Avenue, Hammond, IN
• Gary Chicago International Airport Taxiway
Improvements, Gary, IN
• Crisman/Willowcreek Road Bypass
Improvements, Portage, IN
• US12/20 Intersection Reconstruction, Gary, IN
• Joliet Road Reconstruction, St. John, IN
• CN Underpass on 45th Street, Munster, IN
• Marquette Greenway Trail, Burns Harbor, IN
JOSE VARGAS
PROJECT MANAGER/SENIOR INSPECTOR
CERTIFICATIONS
ACI Field Technician Level I,
Troxler Certified, Safety trained
through e-rail safe
ACI Lab Concrete Strength
Testing Technician
RELEVANT EXPERIENCE
• 45th Street Grade Separation, Munster, IN
• Data Center, Hammond, IN
• USS Lead Remediation, East Chicago, IN
• Gary Fire Station No. 5, Gary, IN
• Hammond Sanitary District Improvements,
Hammond, IN
• BP Amoco Refinery, Whiting, IN
• Lyons Levee, Lyons, IL
• Cline Avenue Bridge Reconstruction, East
Chicago, IN
PAUL TAYLOR
FIELD AND LAB TECHNICIAN
PROJECT TEAM
City of South Bend
Coal Line Trail Phase II
October 26, 2021
Page 7
RELEVANT EXPERIENCE
133RD AVENUE & KING STREET
Town of Cedar Lake, IN
BOLAND DRIVE SHARED-USE PATH
City of South Bend, IN
PROJECT HIGHLIGHTS
• Trail construction to connect
communities with existing
downtown trail system
• Construction in
environmentally-sensitive
areas
• Construction observation and
project management services
• INDOT SiteManager
and mobile workstations
streamlined the process and
kept costs to a minimum
CLIENT
City of South Bend
Toy Villa
574.235.5920
TIME PERIOD
2018 - 2019
COST
$1,346,996
PROJECT TEAM
Jason Durr
Mike Carey
PROJECT HIGHLIGHTS
• Intersections improvements to
address increased traffic due
to housing development
• Controlled intersection to
allow for pedestrian access to
adjacent school
• Full-time project inspection
services
• Team approach allowed
project engineer/project
supervisor to maximize
time on site with project
administration support in the
office
• INDOT coordination
CLIENT
Town of Cedar Lake
Jill Murr
219.374.7400
TIME PERIOD
2021
PROJECT TEAM
T.J. Gordon
Mike Carey
Jason Durr
City of South Bend
Coal Line Trail Phase II
October 26, 2021
Page 8
RELEVANT EXPERIENCE
SOUTH MAIN STREET STREETSCAPE IMPROVEMENTS
City of Elkhart, IN
CLIENT
City of Elkhart
Jeff Schaffer
574.293.2572
TIME PERIOD
2017 - Present
PROJECT TEAM
Jason Durr
Mike Carey
PROJECT HIGHLIGHTS
• Extensive public involvement
phase which included
neighborhood meetings
• Challenging drainage design to
stay within current right-of-way
• Main route to multiple schools
meant increased pedestrian traffic
• Proposed improvements
including curb, pave drain gutter,
drainage swales, sidewalk, multi-
use path, and a chicane for traffic
calming
• PaveDrain gutter above an
infiltration system to collect
runoff and improve water quality
PROJECT HIGHLIGHTS
• Topographic survey
• Geotechnical investigation
• Community engagement
• Concept development
• Design
• Rule 5 Permit
• Bidding assistance
CLIENT
City of Columbus
Dave Hayward
812.376.2540
TIME PERIOD
2006 - 2013
2016 - 2019
PROJECT TEAM
Jason Durr
WESTENEDGE DRIVE IMPROVEMENTS
City of Columbus, IN
City of South Bend
Coal Line Trail Phase II
October 26, 2021
Page 9
RELEVANT EXPERIENCE
S:\2019\19-0550 (St. Joseph County - Capital Ave Sidewalk)\CAD\SHEETS\EXHIBITS\2021-01-05 Trail Layout Exhibit.dwg
agebhard
TRAIL LAYOUT-11X17
CLIENT:PROJ. NO.
DATE:
SHEET OF
DRAWING NO.
TITLE:CHRISTOPHER B. BURKE
220 West Colfax Avenue, Suite 500
South Bend, Indiana 46601
(574) 282-8001
ENGINEERING, LLC
FILE NAME
NO DATE NATURE OF REVISION
DSGN.
DWN.
CHKD.
SCALE:
PLOT DATE:
CAD USER:
MODEL:
3/5/2021
19-0550.00000
03/05/2021
11
1
EXHIBIT -
SR 331 (CAPITAL AVENUE)
TRAIL EXPANSION
227 WEST JEFFERSON BOULEVARD, RM. 732
SOUTH BEND, IN 46601
PHONE: (574) 235-7800
FAX: (574) 235-9813
ST. JOSEPH COUNTY AKG
AKG
1" = XX'
JEFFERSON BOULEVARD STREETSCAPE
CONSTRUCTION INSPECTION
South Bend, IN
CAPITOL AVENUE TRAIL EXTENSION
St. Joseph County, IN
PROJECT HIGHLIGHTS
• Topographic survey
• Preliminary engineering
• Geotechnical investigation
• Final design
• Bidding assistance
• Trail system connections to
eliminate gaps and improve
connectivity
• PermaTrak concrete
boardwalk system
CLIENT
St. Joseph County
Bill Schalliol
574.235.9812
TIME PERIOD
2019 - Present
PROJECT TEAM
Jason Durr
Mike Carey
PROJECT HIGHLIGHTS
• Streetscape project
incorporating complete street
concept
• Blog and Google Docs for
easy distribution of daily
updates
• Part-time construction
observation
• Field reports, record keeping
and daily logs of progress
• Payment application
processing
• Project management and
close-out
CLIENT
City of South Bend
Division of
Engineering
TIME PERIOD
2014
PROJECT TEAM
Jason Durr
Jeremy Morris
City of South Bend
Coal Line Trail Phase II
October 26, 2021
Page 10
PROJECT APPROACH
While our roots are in water resources, Burke has earned the reputation as an
industry leader in the construction engineering field. Our commitment to highly
responsive and effective planning, design and construction has led to the growth of
our field operation services to include construction management observation and
inspection. Burke’s construction engineering strengths began with our knowledge of
civil infrastructure but transcends into the disciplines of transportation engineering,
environmental planning and permitting, and public outreach. Burke team members
are all INDOT-certified technicians with extensive field experience. We are confident
the proposed team of seasoned professionals, led by Jason Durr and Mike Carey,
will work seamlessly with South Bend, INDOT, community leaders, and residents
to coordinate the construction of the Coal Line Trail Phase II from Riverside Drive
and Angela Boulevard to the connection to the East Bank Trail just west of Michigan
Street.
Our team is aware of the importance of the Coal Line Trail and its connectivity to
the East Bank Trail and Riverside Trail. The second phase of the Coal Line Trail will
provide direct access for the Northshore Triangle and Harter Heights neighborhoods.
The new trail will also provide connection to other trail and bike path routes to
surrounding parks, downtown South Bend, and the Notre Dame Campus. Our team
has explored the proposed project area and identified unique challenges for this project
that include a conversion of an old railroad bridge to a pedestrian bridge, potential
wetlands and environmental impacts, ADA grade concerns and general construction
access challenges. Also, adjacent to the project area are a combination of residential
and commercial properties that will require diligent coordination and communication
efforts to help navigate this project to a successful completion. While the railroad
corridor provides some isolation from the traveling public, mindful construction
sequencing and traffic safety during construction of trail sections adjacent to Angela
Boulevard will be critical.
The immediate planning and field verification of grades and rights of way and a
pre-construction safety review of the old railroad bridge with the contractor prior
to starting construction is crucial. Potential issues can be identified and addressed
before they become costly field changes. Our team knows that each project area and
each property is unique and will require constant care to deliver a final product that
meets the need of the public while also meeting expectations of the directly impacted
residents and neighborhoods.
PROJECT FAMILIARITY
City of South Bend
Coal Line Trail Phase II
October 26, 2021
Page 11
PROJECT APPROACH
PRE-CONSTRUCTION CONFERENCE
• Review of contract documents
• Gather names of key contact persons
• Coordinate with contractor to develop a schedule for contractor’s submittals
• Conduct field visits prior to construction
• Video project site prior to construction
• Coordinate kick-off meeting with Burke project team and the city of South Bend
staff
PROJECT INITIATION
• Organize and set agenda for conference
• Notify representatives of the city, contractor, utilities and INDOT
• Develop and distribute meeting minutes and sign-in sheet
• Phone non-attendees and verify pertinent information
FIELD OFFICE FILING SYSTEM
• Develop and maintain a filing system as outlined in the INDOT GIFE
• Integrate electronic management, as required
SHOP DRAWING / SUBMITTAL REVIEW
• Inform contractor as soon as possible of observed deficiency in contractor’s
work
• Conduct regular project progress meetings. Keep and distribute project progress
meeting minutes.
• Complete a daily report and diary form for each day’s work in the format desired
by the City and INDOT’s SiteManager
• Maintain a daily progressive record of the quantities and locations of materials
placed in INDOT’s SiteManager
• Submit weekly or monthly progress reports to the project manager, as required
• Review the contractor’s schedule on a weekly basis and compare actual progress
to the approved schedule with consideration of weather and field conditions
• Review and approve certified payrolls per INDOT standards
FULL-TIME CONSTRUCTION INSPECTION
• Coordinate shop drawings and submittal reviews with the design engineer and
the City
SURVEY / LAYOUT QUALITY ASSURANCE
• Provide periodic checks of the contractor’s general layout for quality assurance
City of South Bend
Coal Line Trail Phase II
October 26, 2021
Page 12
PROJECT APPROACH
CONTRACTOR APPLICATION FOR PAYMENT
• Perform as needed on-site and at-plant inspection of materials at the direction of
the City and in accordance with the INDOT GIFE manual
TESTING
• Review and agree to pay item quantities with contractor prior to submitting
applications for payment
• Review contractor’s applications for payment, sign and transmit payment
applications to the City’s project manager and INDOT
CHANGE ORDERS
• Implement change order procedures as outlined in the INDOT GIFE manual
• Issue a certificate of substantial completion
• Prepare a pre-final punch list
• Conduct a final project walk-through with the city’s project manager and INDOT
• Prepare and transmit a final project punch list
• Verify completion of punch list items
• Determine final quantities and complete daily progressive record
• Assemble final project files and documents
• Coordinate redline markup record drawings with the contractor throughout
construction
• Review and approve final application for payment and prepare final change order
• Complete a final construction record
PROJECT CLOSEOUT
Standard RFP Form Ver. 3-01-2021
6
(Rev. 06/27/18)
Des. #: 1401811
Affirmative Action Certification (AAC) for Disadvantaged Business Enterprises (DBE)
I hereby certify that my company intends to affirmatively seek out and consider Disadvantaged Business Enterprises (DBEs) certified
by the State of Indiana’s DBE Program and the Kentucky Transportation Cabinet (KYTC) DBE Program to participate as part of this
proposal. An Agreement between INDOT and KYTC established reciprocal acceptance of certification of DBE firms in their
respective states under the Unified Certification Program (UCP) pursuant to 49 CFR §26.81(e) and (f).
I acknowledge that this certification is to be made an integral part of this proposal. I understand and agree that the submission of a
blank certification may cause the proposal to be rejected. I certify that I have consulted the following DBE websites to confirm that
the firms listed below are currently certified DBEs:
INDOT: https://entapps.indot.in.gov/DBELocator/
KYTC: https://transportation.ky.gov/Civil-Rights-and-Small-Business-Development/Pages/Certified-DBE-Directory.aspx
I certify that I have contacted the certified DBE’s listed below, and if my company becomes the CONSULTANT, these DBEs have
tentatively agreed to perform the services as indicated. I understand that neither my company nor I will be penalized for DBE
utilization that exceeds the goal. After contract award, any change to the firms listed in this Affirmative Action Certification to be
applied toward the DBE goal must have prior approval by INDOT’s Economic Opportunity Division.
I.DBE Subconsultants to be applied toward DBE goal for the RFP item:
Certified DBE Name Service Planned Estimated Percentage to
be Paid*
%
%
%
%
II.DBE Subconsultants to be utilized beyond the advertised DBE goal for the RFP item:
Certified DBE Name Service Planned Estimated Percentage to
be Paid*
%
%
%
%
Estimated Total Percentage Credited toward DBE Goal:___________
Estimated Percentage of Voluntary DBE Work Anticipated over DBE Goal:__________
Company Name: ____________________________________________________________________
Signature: ___________________________________________ Date: ________________________
∗ It is understood that these individual firm percentages are estimates only and that percentages paid may be greater or less as a result
of negotiation of contract scope of work. My firm will use good faith efforts to meet the overall DBE goal through the use of these
or other certified and approved DBE firms.
Advanced Engineering Services Material Testing/Geotechnical 3
Advanced Engineering Services Material Testing/Geotechnical 2
3%
2%
Christopher B. Burke Engineering, LLC
October 26, 2021