Loading...
HomeMy WebLinkAboutAward Quote - Edison Filtration Fan Replacement Proj No. 121-069 - Ideal Consolidated Inc.  ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER 1316 COUNTY-CITY BUILDING 227 W. JEFFERSON BOULEVARD SOUTH BEND, INDIANA 46601-1830 PHONE 574/ 235-9251 FAX 574/ 235-9171 CITY OF SOUTH BEND JAMES MUELLER, MAYOR BOARD OF PUBLIC WORKS October 12, 2021 Mr. Fred Mohler Ideal Consolidated Inc. 1125 S. Walnut St. South Bend, IN 46619 fmohler@idealconsolidated.com RE: Quotation Award – Edison Filtration Fan Replacement – Project No. 121-069 Dear Mr. Mohler: At its October 12, 2021 meeting, the Board of Public Works awarded the above referenced quotation to you in the amount of $4,020. Please forward the following documents in one submittal by October 26, 2021 to my attention for Board of Public Works approval at lhensley@southbendin.gov : 1) One (1) signed original of the Contract (enclosed); and 2) Certificate of Insurance naming the City of South Bend as an additional insured. If you have any further questions regarding this matter, please call this office at (574) 235- 9251. Sincerely, /s/ Anne Fuchs Anne Fuchs, Clerk Enclosures AF/lh INTER-OFFICE MEMORANDUM DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING TO: Anne Fuchs, Clerk Board of Public Works FROM: Scott Kreeger, Project Engineer SUBJECT: Award Project No. 121-069 Edison Filtration Fan Replacement DATE: October 11, 2021 On October 11, 2021, Engineering received a single quote from Ideal Consolidated Inc. for the replacement of the two fan motors at the Edison Filtration facility. Engineering noted a scrivener’s error on the line item quantity breakdown between the unit price and total amount. Engineering was able to confirm with the Contractor the total amount is the listed $4,020. The quoters ranked as follows: Quoter Total Quote Amount 1. Ideal Consolidated Inc. $4,020 Engineering recommends award of a contract for Edison Filtration Fan Replacement to the lowest responsive / responsible quoter, Ideal Consolidated, Inc. in the amount of $4,020. Sufficient funds have been appropriated from Water Works Operations & Maintenance (620-06- 604-602-436005) Please call with your questions (5998). Enc. Quote Tabulation QUOTE TABULATIONEdison Filtration Fan ReplacementProject No: 121-069For Quotes Due: October 11, 2021Item No. Description Quantity UnitUnit PriceItem TotalUnit PriceItem Total1Supply and replace two 3-Phase induction motors at Edison Filtration Facility1 LS 2,000.00$ 2,000.00$ 4,020.00$ 4,020.00$ Total2,000.00$ 4,020.00$ I hereby certify that the above truly and accurately represents quotes received for this project on October 11, 2021Scott Kreeger, Project EngineerEngineer's Estimate Ideal Consolidated Inc.Non-Collusion AffadavitXPage 1 of 1 October 12, 2021 BOARD OF PUBLIC WORKS CITY OF SOUTH BEND, INDIANA PUBLIC WORKS CONTRACT This Agreement is made and entered into this 12th Day of October, 2021, by and between Ideal Consolidated Inc., 1125 S. Walnut St., South Bend, IN 46619 (the “Contractor”), and the Board of Public Works (the "Board"). The Contractor covenants and agrees to make the following improvement, as fully set out in the Request for Quotations, Standard Specifications, Special Provisions, Plans, and Bid Proposals, all of which are set forth as a part of this Contract, for: PROJECT NO. 121-069 DESCRIPTION: EDISON FILTRATION FAN REPLACEMENT COMPLETION DATE: SEE SPECIFICATIONS AMOUNT: $4,020 FUNDING: PR-00012291 The unit prices for this improvement were those prices as received and accepted by the Board on the 11th Day of October, 2021. The Contractor further agrees to notify the assigned Engineer when this improvement is completed. This notification shall be in the form of a Project Completion Affidavit, signed by the Contractor. Upon final acceptance of the improvement by the Engineer, the Contractor’s final estimate will be presented to the Board for final Payment with one (1) copy of the Project Completion Affidavit and one (1) copy of a Waiver of Lien. Each of the Parties, by signing below, represents and warrants to the other Party that he/she/it has the authority to bind the named person or entity to this Agreement. BOARD OF PUBLIC WORKS IDEAL CONSOLIDATED INC. President Member Printed Name Member Member Signature Member Attest: Anne Fuchs, Clerk October 12, 2021 BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date September 29, 2021 Name Scott Kreeger Department Public Works BPW Date October 12, 2021 Phone Extension 9245 Required Prior to Submittal to Board BPW Attorney Attorney Name Clara McDaniels Dept. Attorney Attorney Name Purchasing Michael Schmidt Check the Appropriate Item Type –Required for All Submissions Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA Chg. Order, No. Traffic Control Resolution Other: Ease./Encroach Required Information Company or Vendor Name Ideal Consolidated Inc. New Vendor Yes If Yes, Approved by Purchasing No MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name Edison Filtration Fan Replacement Project Number 121-069 Funding Source Water Works Operations Account No. 620-06-604-602-436005 Amount $4,020 Terms of Contract LS Purpose/Description ___Award of the simple quotations pending budget. The City will be receiving quotations on October 11th for the project.__________________ For Change Orders Only Amount of Increase Decrease $ ($ ) Previous Amount $ Current Percent of Change: Increase Decrease % (%) New Amount $ Total Percent of Change: Increase Decrease % (%) Time Extension Amount: New Completion Date: