HomeMy WebLinkAboutAward Bid - City of SB 2021 Drainage Improvements - Kaley St. & Marion St. Proj No. 121-006A - Selge Construction Co., Inc.
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
September 28, 2021
Mr. Robert Kuhns
Selge Construction Co., Inc.
2833 South 11TH St.
Niles, MI 49120
aswinehart@selgeconstruction.com
RE: Award Bid – City of South Bend 2021 Drainage Improvements-Kaley St. & Marion St.
Project No. 121-006A
Dear Mr. Kuhns:
At its September 28, 2021 meeting, the Board of Public Works awarded the above
referenced bid to you in the amount of $94,371.50 for Division #1 and $158,632.75 for Division
#2. Enclosed please find a signed Bid/Proposal form.
Please forward the following documents in one submittal by October 12, 2021 to my
attention for Board of Public Works approval at lhensley@southbendin.gov :
1) One (1) signed original of the Public Works Contract (enclosed)
2) Labor & Material Payment Bond
3) Performance Bond (125% of Bid Amount)
4) Certificate of Insurance naming the City of South Bend as an additional insured
5) Item #4 for all subcontractors that you use
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Anne Fuchs
Anne Fuchs, Clerk
Enclosures
AF/lh
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
September 28, 2021
Mr. Matthew D. Cain
HRP Construction Inc.
5777 Cleveland Rd., PO Box 266
South Bend, IN 46624
mattc@hrpconstruction.com
RE: Award Bid – City of South Bend 2021 Drainage Improvements-Kaley St. & Marion St.
Project No. 121-006A
Dear Mr. Cain:
At its September 28, 2021, 2021 meeting, the Board of Public Works awarded the above
referenced bid to Selge Construction Co., Inc. in the amount of $94,371.50 for Division #1 and
$158,632.75 for Division #2.
Thank you for bidding, and we hope you bid with us in the future.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Anne Fuchs
Anne Fuchs, Clerk
Enclosures
AF/lh
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
September 28, 2021
Mr. Dustin Hilary
Milestone Contractors North, Inc.
24358 State Road 23
South Bend, IN 46614
akrueger@milestonelp.com
RE: Award Bid – City of South Bend 2021 Drainage Improvements-Kaley St. & Marion St.
Project No. 121-006A
Dear Mr. Hilary:
At its September 28, 2021, 2021 meeting, the Board of Public Works awarded the above
referenced bid to Selge Construction Co., Inc. in the amount of $94,371.50 for Division #1 and
$158,632.75 for Division #2.
Thank you for bidding, and we hope you bid with us in the future.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Anne Fuchs
Anne Fuchs, Clerk
Enclosures
AF/lh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Anne Fuchs, Clerk
Board of Public Works
FROM: Rebecca Plantz, Project Engineer
SUBJECT: Award Project No. 121-006A
South Bend 2021 Drainage Improvements – Kaley & Marion
DATE: September 20, 2021
On August 24, 2021, the Board of Public Works opened and read bids for the above project.
The bids are summarized as follows:
Bidder Division 1
Base Bid
Division 1
Alternate Division 2
Total of Div 1,
Div 1 Alt, &
Div 2
Selge Construction
Co., Inc. $84,211.50 $10,160.00 $158,632.75 $253,004.25
HRP Construction
Inc. $82,425.00 $9,250.00 $175,465.00 $267,140.00
Milestone
Contractors North,
Inc.
$94,280.00 $9,170.00 $173,920.00 $277,370.00
Division 1
MBE Goal: 3.2%
WBE Goal: 5.4%
Division 2
MBE Goal: 2.7%
WBE Goal: 5.1%
The project is funded by Stormwater Infrastructure – Sewers in the interest of drainage
improvements to Kaley Street and Marion Street including curb, stormwater swales, pavement,
storm structures, and storm pipe. Sufficient funding is available for the following
recommendations:
Division 1 – Kaley St, I recommend rejection of the lowest bid from HRP Construction, Inc.
based on the conclusions of Legal and the Office of Diversity and Inclusion that HRP failed to
meet the MBE participation goal of 3.2% and did not meet the good faith efforts standards to
obtain MBE participation.
On Form MBE – 1.0 MBE Utilization Plan, HRP listed an MBE participation percentage of 0.9%.
which does not meet the 3.2% MBE goal. In light of HRP’s inability to meet the MBE goal on
Division 1, a good faith efforts evaluation took place. There were follow-up discussions with the
bidder and subcontractors that the bidder listed. That review indicates that good faith efforts
were not met as to the MBE goal for Division 1 of the project.
Specifically, deficiencies were found in establishing compliance with at least two of the good
faith effort affirmations contained in Form MBE-2.0. The first good faith effort affirmation not met
is, “I affirm that I have made good faith efforts to select portions of the contract work to be
performed by MBEs, including, where appropriate, breaking out contract work items into
economically feasible units to facilitate MBE participation.”
The City of South Bend’s Minority and Women Business Enterprise Inclusion Program Plan
states when determining whether a bidder has made good faith efforts, the performance of other
bidders in meeting the contract goal may be considered. All other bids received for Division 1
were able to meet the MBE goal. Therefore, it may be reasonably questioned whether with
additional reasonable efforts, the contract goal could have been met by HRP. In addition, the
pricing for trucking related activities received by HRP was equal to or higher than other bidders,
which gives rise to a concern the bidder did not properly select portions of the work to be
performed by an MBE.
A second good faith effort affirmation was not met – i.e., “I affirm that I negotiated with
interested MBEs in good faith, including providing such MBEs with adequate information about
the plans, specifications and other requirements of the subcontract.” Initial outreach was made
by the bidder to a list of MBEs. However, the bidder failed to perform the necessary follow-up to
affirm MBE receipt and retrieval of such information/documentation.
For the above reasons, I recommend the award of the base bid plus alternate of Division 1 –
Kaley St to the next lowest and responsive bidder, Selge Construction Co., Inc., in the amount
of $94,371.50. Selge Construction Co., Inc. met both MBE & WBE contract goals for Division 1.
I recommend the award of the base bid of Division 2 – Marion St to the lowest, responsive
bidder, Selge Construction Co., Inc., in the amount of $158,632.75. Selge Construction Co.,
Inc., met both MBE & WBE contract goals for Division 2.
Please do not hesitate to contact me with any questions you may have (ext. 5998).
Enc. Bid Tabulation
September 28, 2021
BOARD OF PUBLIC WORKS
CITY OF SOUTH BEND, INDIANA
PUBLIC WORKS CONTRACT
This Agreement is made and entered into this 28th Day of September, 2021, by and between Selge
Construction Co., Inc., 2833 S. 11th. St., Niles, MI 49120 (the “Contractor”), and the Board of
Public Works (the "Board”).
The Contractor covenants and agrees to make the following improvement, as fully set out in the
Request for Quotations, Standard Specifications, Special Provisions, Plans, and Bid Proposals, all
of which are set forth as a part of this Contract, for:
PROJECT NO. 121-006A
DESCRIPTION: CITY OF SOUTH BEND 2021 DRAINAGE IMPROVEMENTS -
KALEY ST. & MARION ST.
COMPLETION DATE: SEE SPECIFICATIONS
AMOUNT: DIVISION #1 $94,371,50; DIVISION #2 $158,632.75
FUNDING: PR-00010684
The unit prices for this improvement were those prices as received and accepted by the Board on
the 24th Day of August, 2021.
The Contractor further agrees to notify the assigned Engineer when this improvement is
completed. This notification shall be in the form of a Project Completion Affidavit, signed by the
Contractor. Upon final acceptance of the improvement by the Engineer, the Contractor’s final
estimate will be presented to the Board for final Payment with one (1) copy of the Project
Completion Affidavit and one (1) copy of a Waiver of Lien.
Each of the Parties, by signing below, represents and warrants to the other Party that he/she/it has
the authority to bind the named person or entity to this Agreement.
BOARD OF PUBLIC WORKS SELGE CONSTRUCTION CO.,
INC.
President Member Printed Name
Member Member Signature
Member Attest: Anne Fuchs, Clerk
September 28, 2021
BID TABULATION
SOUTH BEND 2021 DRAINAGE IMPROVEMENTS - KALEY ST MARION ST
Project No: 121-006A
KALEY ST & MARION ST DRAINAGE IMPROVEMENTS 2021
DIVISION 1 - KALEY STREET IMPROVEMENTS
Item No. Line Item Quantity Unit Unit Price Cost Unit Price Cost Unit Price Cost Unit Price Cost
1 CONSTRUCTION ENGINEERING 1 LSUM $1,500.00 $1,500.00 $3,495.00 $3,495.00 $5,000.00 $5,000.00 $3,000.00 $3,000.00
2 MOBILIZATION AND DEMOBILIZATION 1 LSUM $2,774.60 $2,774.60 $10,300.00 $10,300.00 $3,850.00 $3,850.00 $15,600.00 $15,600.00
3 MAINTENANCE OF TRAFFIC 1 LSUM $3,500.00 $3,500.00 $7,600.00 $7,600.00 $2,020.00 $2,020.00 $3,500.00 $3,500.00
4 VIDEO RECORD 1 LSUM $1,500.00 $1,500.00 $600.00 $600.00 $500.00 $500.00 $1,000.00 $1,000.00
5 CLEARING OF RIGHT-OF-WAY 1 LSUM $5,000.00 $5,000.00 $7,500.00 $7,500.00 $27,600.00 $27,600.00 $2,500.00 $2,500.00
6 CONCRETE, PAVEMENT REMOVE 3 SYS $40.00 $120.00 $140.00 $420.00 $25.00 $75.00 $540.00 $1,620.00
7 SURFACE MILLING, ASPHALT 1.5 IN 2700 SFT $3.00 $8,100.00 $1.75 $4,725.00 $1.60 $4,320.00 $1.25 $3,375.00
8 CLEAR AND GRUB 400 SFT $2.00 $800.00 $10.00 $4,000.00 $5.00 $2,000.00 $2.00 $800.00
9 COMMON EXCAVATION, ASPHALT REMOVE 20 CYS $50.00 $1,000.00 $150.00 $3,000.00 $66.00 $1,320.00 $315.00 $6,300.00
10 HMA SURFACE, TYPE B 30 TON $130.00 $3,900.00 $180.00 $5,400.00 $200.00 $6,000.00 $200.00 $6,000.00
11 COMPACTED AGGREGATE , No. 53 5 CYS $75.00 $375.00 $60.00 $300.00 $150.00 $750.00 $210.00 $1,050.00
12 PCCP FOR APPROACH, REINFORCED 12 SYS $100.00 $1,200.00 $220.00 $2,640.00 $192.00 $2,304.00 $300.00 $3,600.00
13 SIDEWALK, CONCRETE, 4 IN 4 SYS $63.00 $252.00 $200.00 $800.00 $175.00 $700.00 $700.00 $2,800.00
14 STEPS, CONCRETE 1 LSUM $5,000.00 $5,000.00 $5,800.00 $5,800.00 $4,750.00 $4,750.00 $7,310.00 $7,310.00
15 CONCRETE CURB 250 LFT $35.00 $8,750.00 $55.00 $13,750.00 $37.50 $9,375.00 $31.00 $7,750.00
16 CURB TURNOUT 1 EACH $800.00 $800.00 $5,200.00 $5,200.00 $2,450.00 $2,450.00 $1,645.00 $1,645.00
17 RIPRAP PROTECTION 1 CYS $75.00 $75.00 $7,000.00 $7,000.00 $850.00 $850.00 $1,000.00 $1,000.00
18 TURF SOD, AND TOPSOIL 135 SYS $12.00 $1,620.00 $70.00 $9,450.00 $42.50 $5,737.50 $95.00 $12,825.00
19 TEMPORARY EROSION CONTROL 1 LSUM $12,000.00 $12,000.00 $2,300.00 $2,300.00 $4,610.00 $4,610.00 $750.00 $750.00
$58,266.60 $94,280.00 $84,211.50 $82,425.00
KALEY ST & MARION ST DRAINAGE IMPROVEMENTS 2021
DIVISION 1 - KALEY STREET ALTERNATES
Alt No. Alternate #1 Line Item Quantity Unit Unit Price Cost Unit Price Cost Unit Price Cost Unit Price Cost
7A SURFACE MILLING, ASPHALT 1.5 IN 2600 SFT $3.00 $7,800.00 $1.45 $3,770.00 $1.60 $4,160.00 $1.25 $3,250.00
10A CONCRETE SEAT WALL 30 TON $125.00 $3,750.00 $180.00 $5,400.00 $200.00 $6,000.00 $200.00 $6,000.00
$11,550.00 $9,170.00 $10,160.00 $9,250.00
Engineer's Estimate Milestone Contractors North
Division 1 Total
HRP Construction
Alternate #1 Total
Selge Construction
Engineer's Estimate Milestone Contractors North Selge Construction HRP Construction
H:\2021 Projects\2021-0028\Bidding\2021-08-24 Bid Tabulation.xlsx
BID TABULATION
SOUTH BEND 2021 DRAINAGE IMPROVEMENTS - KALEY ST MARION ST
Project No: 121-006AKALEY ST & MARION ST DRAINAGE IMPROVEMENTS 2021
DIVISION 2 - MARION STREET IMPROVEMENTS
Item No. Line Item Quantity Unit Unit Price Cost Unit Price Cost Unit Price Cost Unit Price Cost
22 CONSTRUCTION ENGINEERING 1 LSUM $1,500.00 $1,500.00 $3,445.25 $3,445.25 $6,500.00 $6,500.00 $3,000.00 $3,000.00
23 MOBILIZATION AND DEMOBILIZATION 1 LSUM $6,769.35 $6,769.35 $16,400.00 $16,400.00 $6,820.00 $6,820.00 $22,900.00 $22,900.00
24 MAINTENANCE OF TRAFFIC 1 LSUM $7,500.00 $7,500.00 $8,300.00 $8,300.00 $7,160.00 $7,160.00 $9,500.00 $9,500.00
25 VIDEO RECORD 1 LSUM $1,500.00 $1,500.00 $600.00 $600.00 $500.00 $500.00 $1,000.00 $1,000.00
26 CLEARING OF RIGHT-OF-WAY 1 LSUM $3,000.00 $3,000.00 $9,500.00 $9,500.00 $28,600.00 $28,600.00 $1,500.00 $1,500.00
27 TREE REMOVE 3 EACH $2,000.00 $6,000.00 $850.00 $2,550.00 $1,500.00 $4,500.00 $900.00 $2,700.00
28 CONCRETE, PAVEMENT REMOVE 40 SYS $40.00 $1,600.00 $36.00 $1,440.00 $25.00 $1,000.00 $35.00 $1,400.00
29 CONCRETE CURB REMOVE 176 LFT $16.00 $2,816.00 $14.00 $2,464.00 $10.00 $1,760.00 $10.00 $1,760.00
30 SURFACE MILLING, ASPHALT 1.5 IN 4900 SFT $3.00 $14,700.00 $1.90 $9,310.00 $1.60 $7,840.00 $1.25 $6,125.00
31 CLEAR AND GRUB 360 SFT $2.00 $720.00 $13.00 $4,680.00 $5.00 $1,800.00 $2.00 $720.00
32 COMMON EXCAVATION, ASPHALT REMOVE 170 CYS $50.00 $8,500.00 $64.00 $10,880.00 $17.00 $2,890.00 $55.00 $9,350.00
33 STRUCTURAL BACKFILL 75 CYS $45.00 $3,375.00 $0.01 $0.75 $16.00 $1,200.00 $15.00 $1,125.00
34 HMA BASE, TYPE B, 8"75 TON $125.00 $9,375.00 $150.00 $11,250.00 $143.00 $10,725.00 $143.00 $10,725.00
35 HMA INTERMEDIATE, TYPE B, 2.5"25 TON $100.00 $2,500.00 $210.00 $5,250.00 $256.00 $6,400.00 $256.00 $6,400.00
36 HMA SURFACE, TYPE B, 1.5"60 TON $130.00 $7,800.00 $175.00 $10,500.00 $200.00 $12,000.00 $200.00 $12,000.00
37 COMPACTED AGGREGATE , No. 53 25 CYS $75.00 $1,875.00 $60.00 $1,500.00 $100.00 $2,500.00 $225.00 $5,625.00
38 PCCP FOR APPROACH, REINFORCED 40 SYS $100.00 $4,000.00 $255.00 $10,200.00 $192.00 $7,680.00 $300.00 $12,000.00
39 SIDEWALK, CONCRETE, 4 IN 2 SYS $63.00 $126.00 $700.00 $1,400.00 $175.00 $350.00 $870.00 $1,740.00
40 CURB RAMP, CONCRETE 6 SYS $100.00 $600.00 $400.00 $2,400.00 $420.00 $2,520.00 $310.00 $1,860.00
41 CONCRETE CURB 190 LFT $75.00 $14,250.00 $70.00 $13,300.00 $48.00 $9,120.00 $31.00 $5,890.00
42 CURB INLET 4 EACH $3,000.00 $12,000.00 $4,700.00 $18,800.00 $2,480.00 $9,920.00 $4,200.00 $16,800.00
43 CORE & BOOT EXIST STORM STRUCTURE 1 EACH $2,000.00 $2,000.00 $4,700.00 $4,700.00 $1,175.00 $1,175.00 $3,000.00 $3,000.00
44 PVC STORM SEWER PIPE, 12IN 180 LFT $75.00 $13,500.00 $52.00 $9,360.00 $66.00 $11,880.00 $85.00 $15,300.00
45 RCP STORM SEWER PIPE, 12IN 95 LFT $75.00 $7,125.00 $59.00 $5,605.00 $66.00 $6,270.00 $95.00 $9,025.00
46 HYDROMULCH, SEEDING AND TOPSOIL 50 SYS $12.00 $600.00 $100.00 $5,000.00 $45.75 $2,287.50 $75.00 $3,750.00
47 OVERSTORY TREE, 2-1/2" CAL 2 EACH $600.00 $1,200.00 $1,155.00 $2,310.00 $1,343.00 $2,686.00 $1,155.00 $2,310.00
48 TREE WATER BAG 2 EACH $200.00 $400.00 $80.00 $160.00 $80.00 $160.00 $80.00 $160.00
49 THERMOPLASTIC LINE, SOLID, WHITE, 4 IN 185 LFT $2.00 $370.00 $3.00 $555.00 $1.25 $231.25 $10.00 $1,850.00
50 THERMOPLASTIC LINE, SOLID, YELLOW, 4 IN 420 LFT $2.00 $840.00 $3.00 $1,260.00 $1.25 $525.00 $10.00 $4,200.00
51 THERMOPLASTIC LINE, SOLID, WHITE, 8 IN 40 LFT $3.00 $120.00 $5.00 $200.00 $1.85 $74.00 $15.00 $600.00
52 THERMOPLASTIC LINE, SOLID, WHITE 24 IN 20 LFT $6.00 $120.00 $15.00 $300.00 $7.95 $159.00 $20.00 $400.00
53 TEMPORARY EROSION CONTROL MEASURES 1 LSUM $5,000.00 $5,000.00 $300.00 $300.00 $1,400.00 $1,400.00 $750.00 $750.00
$141,781.35 $173,920.00 $158,632.75 $175,465.00
I hereby certify that the above truly and accurately represents bids received for this project on August 25, 2021
Chris Chockley, PLA
Name, Title
YESYESNon-Collusion Affadavit -YES
Division 2 Total
Engineer's Estimate Milestone Contractors North Selge Construction HRP Construction
H:\2021 Projects\2021-0028\Bidding\2021-08-24 Bid Tabulation.xlsx
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 08/12/2021
Name Becca Plantz Department Public Works
BPW Date 08/24/2021 Phone Extension 5998
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name Michael Patton BPW Attorney Attorney Name Clara McDaniels
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name 2021 Drainage Improvements – Kaley St & Marion St
Project Number 121-006A
Funding Source Stormwater Infrastructure-Sewers
Account No. PR-000010684
Amount
Terms of Contract Unit Prices & Lump Sums
Purpose/Description Small drainage improvements to Kaley Street and Marion Street including
site preparation and sewer line improvements.
For Change Orders Only
Amount of
Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date:
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 09/08/2021
Name Becca Plantz Department Public Works
BPW Date 09/28/2021 Phone Extension 5998
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name Michael Patton BPW Attorney Attorney Name Clara McDaniels
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Selge Construction Co., Inc.
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name 2021 Drainage Improvements – Kaley St & Marion St
Project Number 121-006A
Funding Source Stormwater Infrastructure-Sewers
Account No. PR-000010684
Amount Division 1 - $94,371.50 & Division 2 - $158,632.75
Terms of Contract Unit Prices & Lump Sums
Purpose/Description Small drainage improvements to Kaley Street and Marion Street including
site preparation and sewer line improvements.
For Change Orders Only
Amount of
Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: