HomeMy WebLinkAboutAmendment No. 4 to PSA - Beck’s Lake NPL Site LaSalle Park Area, Proj No. 120-053 – Jones Petrie Rafinski Corp.
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
August 10, 2021
Mr. R. Joseph Trojan
Jones Petrie Rafinski Corporation
200 Nibco Pkwy., Suite 200
Elkhart, IN 46516
RE: Amendment No. 4 to Professional Services Agreement
Dear Mr. Trojan:
At its August 10, 2021 meeting, the Board of Public Works approved the above
referenced amendment for time-critical removal actions related to Beck’s Lake NPL Site/LaSalle
Park Area, Project No. 120-053, and general consulting costs from July 2021 through December
2021 in an amount not to exceed $153,723.
Enclosed please find the original of the amendment for your signature. Please sign and
return the original amendment to lhensley@southbendin.gov. Please retain a copy for your
records.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Anne Fuchs
Anne Fuchs, Clerk
Enclosures
AF/lh
FOURTH AMENDMENT TO AGREEMENT FOR PROFESSIONAL SERVICES
This Fourth Amendment to the Agreement for Professional Service (this “Fourth
Amendment”) is made on July 13, 2021 (the “Effective Date”), by and between the City of South
Bend, Indiana, acting by and through its Board of Public Works (the “City”), and Jones Petrie
Rafinski Corp., an Indiana corporation with its principal office at 200 Nibco Parkway, Suite 200,
Elkhart, Indiana 46516 (the “Provider”) (each a “Party” and together, the “Parties”).
RECITALS
A. The City and the Provider entered into that certain Agreement for Professional
Services dated August 14, 2018 (the “Services Agreement”), for Beck’s Lake Project offsite
waste delineation and groundwater investigation (as defined in the Services Agreement).
B. The City and the Provider entered into the First Amendment to the Services
Agreement on November 13, 2018, incorporating Scope of Work Changes and Cost Adjustments
as set forth in the First Amendment.
C. The City and the Provider entered into the Second Amendment to the Services
Agreement on August 13, 2019, incorporating Scope of Work Changes and Cost Adjustments as
set forth in the Second Amendment.
D. The City and the Provider entered into the Third Amendment to the Services
Agreement on November 12, 2019, incorporating Scope of Work Changes and Cost Adjustments
as se
E. The City and the Provider now wish to further amend the Services Agreement as
set forth in this Fourth Amendment.
NOW, THEREFORE, in consideration of the mutual promises and obligations in this
Fourth Amendment, the Third Amendment, the Second Amendment, the First Amendment, and
the Services Agreement, the adequacy of which consideration is hereby acknowledged, the
Parties agree as follows:
1. Services. Add Exhibit D-1 to the Services Agreement, Scope of Work Changes and Cost
Adjustments, Beck’s Lake NPL Site/LaSalle Park Area, South Bend, Indiana (Project 2018 –
0225).
2. The entirety of Section 2 of the Services Agreement is deleted and replaced by the
following:
A. Compensation. In exchange for the Provider’s satisfactory performance of the
Services, and subject to the terms and conditions of this Agreement, the City will pay the
Provider a total sum not to exceed Five Hundred Forty Thousand Eight Hundred Twenty
Three Dollars ($540,823), of which a sum not to exceed One Hundred Fifty-Three Thousand
Seven Hundred Twenty Three Dollars ($153,723) (the “Remaining Contract Amount”) is to
paid in accordance with the cost proposal stated in the Scope of Work (Exhibit D-1). The
Provider shall prepare detailed, itemized invoices and submit them monthly to the City of
South Bend Department of Law. Invoices shall be presented as set forth in the Scope of
Work and payment shall be made to the Provider within a reasonable time thereafter. The
Provider acknowledges and agrees that invoices will be reviewed and approved by the City
prior to payment. The City will not be required to pay any invoice if the City is not satisfied
with the Provider’s Performance under this Agreement or any default or breach of this
Agreement by Provider exists, as the City may determine in its sole discretion. The Provider
will not incur or seek reimbursement for any expenses exceeding the Contract Amount
without a signed contract change or similar instrument as outlined in Section 16.
3.Each and every other provision of the Services Agreement and attachments thereto are hereby
ratified, approved and reaffirmed by the Parties and all other matters previously agreed to and set
forth in the Services Agreement and not affected by this Third Amendment shall remain in full
force and effect.
4.This Fourth Amendment may be executed in multiple counterparts, each of
which shall be deemed an original.
5.The undersigned person(s) executing and delivering this Fourth Amendment on
Behalf of the Parties represent and certify that s/he has been full empowered to execute and
deliver this Second Amendment.
IN WITNESS WHEREOF, the Parties hereto have made and executed this Fourth
Amendment to the Services Agreement as of the date first written above.
JONES PETRIE RAFINSKI CORP.,
an Indiana corporation
_________________________________
Signature
_R. Joseph Trojan___________________
Printed Name
_Environmental Project Manager_______
Title
_________________________________
Date Date Signed: August 10, 2021
Scope of Work and Cost Proposal for Beck’s Lake NPL/LaSalle Park Area
April 22, 2021
Page 1 of 3
April 22, 2021
City of South Bend
Legal Department
227 West Jefferson Boulevard #1200
South Bend, Indiana 46601
Attn: Stephanie Steele,
Corporation Counsel
RE: SCOPE OF WORK CHANGES AND COST ADJUSTMENTS, BECK’S LAKE NPL
SITE/LASALLE PARK AREA, SOUTH BEND, INDIANA
(PROJECT 2018-0225)
Dear Ms. Steele:
Jones Petrie Rafinski Corp. (JPR) is pleased to submit this Scope of Work Changes and Cost
Adjustments as a fourth amendment to the original professional services agreement (PSA) dated August
14, 2018 for work associated with additional offsite waste delineation (Task 1), groundwater investigation
(Task 2), soil management plan (SMP) implementation (Task 3), general consulting services (Task 4)
and soil sampling to define Areas of Concern (Task 5) for the Beck’s Lake NPL Site/LaSalle Park Area
project.
SCOPE OF WORK CHANGES BY TASK WITH COST ADJUSTMENTS
Task 1: Waste Delineation Outside of the LaSalle Park Area (LPA) - North of Linden Avenue
Net Task Change: None.
Task 2: Monitor Well Installation, Development, and Groundwater Sampling
Net Task Change: None.
Task 3: Soil Management Plan Implementation and Oversight of Waste Soil Disposal
Net Task Change: $97,723.00 increase.
The City of South Bend has recently approved the “Contract Documents and Specifications for Beck’s
Lake/LaSalle Park” (Project No. 120-053) which is the bid package for implementing the Time-Critical
Removal Actions (TCRA) related to multiple areas of the Beck’s Lake/Lasalle Park NPL Site as
required by the EPA. The planned activities will include sod, soil and tree removal as well as the
placement of additional fill sand and topsoil. As per the EPA-approved Soil Management Plan (SMP),
the air must be monitored for particulate contaminants of concern (COCs) during any soil disturbance
at the site. Any soil excavated must be removed from the site and transported directly to an EPA-
approved landfill for proper disposal. In addition, all soil brought to the site must be determined to be
free of COCs via laboratory analytical testing (at concentrations above regulatory limits) prior to
placement on the site.
EXHIBIT D-1
Scope of Work and Cost Proposal for Beck’s Lake NPL/LaSalle Park Area
April 22, 2021
Page 2 of 3
The associated additional costs for Task 3 are as follows:
Field Labor for Soil Removal/Placement Oversight
With estimated field activities duration of six weeks
Env. Project Manager ($140/hr @ 240 hours)………………………………………….$33,600.00
Field Technician ($95/hr @ 60 hours)…………………………………………………..$ 5,700.00
Laboratory Analysis of Backfill Soil Samples for TAL Metals,
VOCs, SVOCs+PNA SIM, Pesticides, PCBs for 44 samples
@ $766.70/sample………………………………………………………………………..$33,734.80
Level IV QA/QC Package………………………………………………………………..$ 5,060.20
Third Party Data Validation………………………………………………………………$ 6,030.00
Air Monitoring Equipment Rental ($383/wk for 6 weeks)……………………………..$ 2,298.00
Survey of Excavation and Backfill Extents as well as location of
Underground Sprinkling Infrastructure………………………………………………….$ 5,000.00
Project Documentation and Soil Management Plan Modifications…………………..$ 6,300.00
Task 3 Subtotal………………………………………..$97,723.00
Task 4: General Consulting - Provide Assistance to Project Coordinator for On-Going
Deliverables
Net Task Change: $56,000 increase
The existing PSA dated November 12, 2019 included costs for general consulting through June 2020.
Since the project is ongoing, general consulting is necessary to assist the City of South Bend with
EPA requirements.
Therefore, the following cost adjustment includes anticipated general consulting costs from July 2020
through December 2021:
• Environmental Project Manager @$140/hour – estimated 400 hours for July 2020
through December 2021 at direction of the EPA-assigned Project Coordinator.
Task 5: Soil sampling to Define Areas of Concern
Net Task Change: None.
The following is a summary of the overall cost adjustments:
Current Approved Costs……….……………………………………………. $387,100
New Total Estimated Costs………….………………………………………. $540,823
Net Contract Change (increase)…………..…….……………..……………. $153,723
EXHIBIT D-1
Scope of Work and Cost Proposal for Beck’s Lake NPL/LaSalle Park Area
April 22, 2021
Page 3 of 3
Please note that the costs presented herein are our best estimate of the time and materials involved
in the project which Jones Petrie Rafinski will not exceed without prior approval. Should the scope
of services require modification (i.e., additional/less borings, analyses, etc.) based upon field
conditions and/or circumstances that would not have otherwise been anticipated, JPR will notify the
client of such “changed conditions” and resultant cost implications to the project.
Assuming a portion of the project is ongoing, our services will be billed monthly. Payment will be
subject to the terms of the PSA. Should you have any questions or comments concerning our
services or charges during the course of the work, please bring them to our attention immediately for
quick resolution.
Sincerely,
R. Joseph Trojan
Environmental Project Manager
EXHIBIT D-1
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date August 2, 2021
Name Aladean DeRose Department Legal
BPW Date August 10, 2021 Phone Extension 5866
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name BPW Attorney Attorney Name Clara McDaniels
Dept. Attorney Attorney Name Clara McDaniels
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Jones, Petrie & Rafinski
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Beck’s Lake NPL Site/LaSalle Park Area
Project Number 2018-0225
Funding Source Professional Services - EPA
Account No. 226-0412-672-39-02
Amount NTE $153,723
Terms of Contract
Purpose/Description Fourth Amendment to August 14, 2018 Professional Services Agreement.
The City of South Bend has recently approved the “Contract Documents
and Specifications for Beck’s Lake/LaSalle Park” (Project No. 120-053)
which is the bid package for implementing the Time-Critical Removal
Actions (TCRA) related to multiple areas of the Beck’s Lake/Lasalle Park
NPL Site as required by the EPA. The planned activities will include sod,
soil and tree removal as well as the placement of additional fill sand and
topsoil, as well as general consulting costs from July 2021 through
December 2021.
For Change Orders Only
Amount of
Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $