August 10, 2021
Mr. Bill Favors
Ziolkowski Construction, Inc.
4050 Ralph Jones Dr.
South Bend, IN 46628
kkromer@zbuild.com
RE: Change Order No. 2 – Seitz Park Reconstruction - Phase I – Project No. 117-093A
Dear Mr. Favors:
At its August 10, 2021 meeting, the Board of Public Works approved the above
referenced Change Order for an increase of $31,820, bringing the revised contract amount to
$7,147,249.78.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Anne Fuchs
Anne Fuchs, Clerk
Enclosures
AF/lh
7/7/21
Jul 7, 2021
Jul 9, 2021
Jul 12, 2021
Use this account for this change order increase:
201-11-206-273-444000 PROJ00000079
August 10, 2021
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 6/23/2021
Name Sue Ellen Doudrick Department DPW
BPW Date 7/21/2021 Phone Extension 5922
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer Officer Name
BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title
Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. __ PCA
Chg. Order, No. 2 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Ziolkowski Construction V:1875
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Seitz Park Reconstruction – Phase I
Project Number 117-093A
Funding Source REDA TIF, Park Bond ****Use Account: 201-11-206-273-444000****
Account No. PR-00004857; PO 6342
Amount $31,820
Terms of Contract Line items
Purpose/Description Change Order #2: Replace existing failing CMP storm sewer located
beneath Riverwalk in Division B. Cost includes sewer televising to
determine the repair required and replacement.
For Change Orders Only
Amount of Increase
Decrease
$ 31,820
($)
Previous Amount $ 7,115,429.78
Current Percent of Change:
Increase
Decrease
0.4472%
(%)
New Amount $ 7,147,249.78
Total Percent of Change:
Increase
Decrease
0.1254%
(%)
Time Extension Amount: 0
New Completion Date: -
8/10/21