HomeMy WebLinkAboutChange Order No 1 - City of SB Wayfinding Signage Program - Phase II Proj No. 120-020 - Geograph Industries, Inc.
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
August 10, 2021
Mr. Greg Freudiger
Geograph Industries, Inc.
475 Industrial Dr.
Harrison, OH 45030
gregfreudiger@geograph-ind.com
RE: Change Order No. 1 – City of South Bend Wayfinding Signage Program - Phase II
Project No. 120-020
Dear Mr. Freudiger:
At its August 10, 2021 meeting, the Board of Public Works approved the above
referenced Change Order for an increase of $2,745 with a additional nineteen (19) days, bringing
the revised contract amount to $149,311 with a new completion date of June 16, 2021.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Anne Fuchs
Anne Fuchs, Clerk
Enclosures
AF/lh
August 10, 2021