July 27, 2021
Mr. Dustin Hilary
Milestone Contractors North, Inc.
24358 State Road 23
South Bend, IN 46614
akrueger@milestonelp.com
RE: Award Contract
Dear Mr. Hilary:
At its July 27, 2021 meeting, the Board of Public Works approved the above referenced
contract for the installation of 2” copper line stops for Olive St., Phase I, Project No. 114-064,
in the amount of $21,700.
Enclosed please find a copy of the contract for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Laura Hensley/Acting
Anne Fuchs, Clerk
Enclosures
AF/lh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENVIRONMENTAL SERVICES
TO: Board of Public Works
Anne Fuchs, Clerk
FROM: Leslie Biek, P.E., Assistant City Engineer
SUBJECT: Award Contract: Olive Ph 1 Water Service Relocation with
Milestone Contractors North
DATE: 7/15/2021
It is requested the Board of Public Works award a contract to Milestone Contractors North for
the relocation of two water service lines as a part of the Olive St Phase 1 project for a price of
$21,700.
For LPA projects, INDOT handles the construction contract. INDOT performed the public solicitation
of bids for the Olive St Phase 1 project and selected Milestone Contractors North as the lowest
responsive and responsible bidder. INDOT then works directly with the City on the local participation
costs and bills the City directly.
During construction, Milestone could not get an INDOT certified subcontractor to perform the 2”
copper line stop, so the work was not able to be completed under the INDOT contract. Therefore, the
City agreed to pay Milestone directly for the portion of work for the 2" copper line stop installation.
From:Leslie Biek
To:Chris Holth; Toy Villa; Relias, Nick
Cc:Jonathan Day; mwhitten@usiconsultants.com; Hauersperger, Steven; Kara Boyles
Subject:RE: 2" Copper and 6" Fire protection
Date:Thursday, April 22, 2021 12:09:11 PM
Nick and Chris,
We have gotten the go-ahead from Eric. Please proceed with the work. The City will work directly
with Milestone to get the work accomplished this Saturday.
Thanks!
Leslie Biek, P.E.
Assistant City EngineerDivision of Engineering
City of South Bend
lbiek@southbendin.gov
From: Chris Holth <cholth@hwcengineering.com>
Sent: Wednesday, April 21, 2021 11:10 AM
To: Leslie Biek <lbiek@southbendin.gov>; Toy Villa <tvilla@southbendin.gov>; Hauersperger, Steven
<SHauersperger@indot.IN.gov>
Cc: Jonathan Day <jday@hwcengineering.com>; mwhitten@usiconsultants.com; Relias, Nick
<nrelias@milestonelp.com>
Subject: FW: 2" Copper and 6" Fire protection
All,
Looking for a quick verbal on this pricing and work so that Milestone can get this accomplished this
Saturday. I have been going through the INDOT CO price range summary to determine if Milestones
prices are within past approved projects. Based on this information I think that they are well within
and lower on both these items from other approved CO for this type of work.
For the 2” re-route a line stop alone has been priced at $9000.00 not including the pipe re-routing
and labor to install the rest of the 2” copper. So I would recommend this price for sure.
For the 6” ductile Iron re-connect for fire protection there is no specific price for this found, but a
standard 6” re-connect is priced about average at $500.00 a lft or a basic reconnection listed at
$5500.00 which is just tying on to an existing service, which at approx. 30’ that would be well above
the price requested without the add’l fire protection manpower and Saturday work.
This one is critical to get a verbal on so Milestone can get them here Saturday. I won’t write a formal
CO until I get a verbal back from South Bend and INDOT, but at least with an agreement to the price
we can proceed and not hold up storm placement heading North. Let us know your thoughts.
Thanks,
Chris Holth
HWC Engineering
From: Relias, Nick <nrelias@milestonelp.com>
Sent: Wednesday, April 21, 2021 9:35 AM
To: Chris Holth <cholth@hwcengineering.com>
Subject: 2" Copper and 6" Fire protection
Chris,
Here are the prices to reroute the 6” Fire protection and the 2” Copper. This work has to be done
on a Saturday as we need to shutoff water to the business. It is a daycare and they are not open on
Saturdays. The Price for the 6” includes a Fire Protection company to shut off the system, watch the
building during our work and return the system to operation. The 2” requires a line stop as no one
will freeze this size line. I have reached out to 10 different companies and finally found one from
Illinois that will do the work.
From: scansb@walshkelly.com <scansb@walshkelly.com>
Sent: Wednesday, April 21, 2021 9:55 AM
To: Relias, Nick <nrelias@milestonelp.com>
Subject: Message from KM_C658
Nick Relias
General Superintendent
24358 SR 23
South Bend, IN 46614
Office:+1-574-544-5520
Mobile:+1-574-532-9056
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 7/15/2021
Name Leslie Biek, PE Department PW
BPW Date 7/27/2021 Phone Extension 9323
Review and Approval Required Prior to Submittal to Board Diversity Compliance
and Inclusion Officer Officer Name BPW Attorney Attorney Name
Dept. Attorney Attorney Name Clara McDaniels
Purchasing Amanda Pietsch
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Milestone Contractors North, Inc
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Olive Ph 1 Water Service Relocation
Project Number 114-064; PROJ 59
Funding Source RW TIF
Account No. PR-10655
Amount $21,700.00
Terms of Contract
Purpose/Description Contract with Milestone to relocate water services as a part of the Olive Ph 1
LPA project, but outside of INDOT LPA contract.
For Change Orders Only
Amount of
Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: