HomeMy WebLinkAboutAmendment No. 1 to PSA - Additional Srvcs Time & Effort Required Public Bid Expenses for Former Salvation – Alliance Architects
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
July 27, 2021
Mr. Christopher Hartz, RA
Alliance Architects
929 Lincolnway East, Suite 200
South Bend, IN 46601
chartz@alliarch.com
RE: Amendment No. 1 to Professional Services Agreement
Dear Mr. Hartz:
At its July 27, 2021 meeting, the Board of Public Works approved the above referenced
amendment for additional services to produce bid documents for the Former Salvation Army
Building roof repairs – Project No. 119-084B in the amount of $1,500 with a total amount of
$10,800.
Enclosed please find a copy of the amendment for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Laura Hensley/Acting
Anne Fuchs, Clerk
Enclosures
AF/lh
Page 1 of 1
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Anne Fuchs, Clerk
Board of Public Works
FROM: Zach Hurst, Project Engineer
SUBJECT: PSA Amendment No. 1 - Project No. 119-084B
Former Salvation Army Building Roof Repairs
DATE: July 1, 2021
This amendment to the Professional Services Agreement with Alliance Architects adds fee back
to the contract to account for the unforeseen expense of needing to put the project out for public
bid after quotes came back over the $150,000 threshold as outlined in the Indiana State Code.
Quotes were solicited in late 2020, and both quotes received exceeded the allowable threshold
for quoted projects. The architect was directed to modify the quote documents into bid documents.
This amendment adds in the time and effort required for the architect to produce documents for
public bid, and addresses reimbursable expenses incurred thus far.
929 Lincolnway East, Suite 200 | South Bend, Indiana 46601 | Tel 574.288.2052 | www.alliarch.com
June 30, 2021
Mr. Zach Hurst, PE VIA E-MAIL
Project Engineer
Public Works | Division of Engineering
1316 County-City Building
227 West Jefferson Boulevard
South Bend, IN 46601
RE: Contract Amendment No. 1
Roof Restoration and Replacement at the Former Salvation Army Building
Dear Zach:
Thank you for the opportunity to submit this contract amendment for additional services related to the
bidding of the roof restoration and replacement project.
Per your email request on 12/21/20, the project changed scope from soliciting contractor quotes to being
a bid package. The additional fee requested for performing this change amounts to $1,500, bringing the
total project fee to $10,800.
Aside from the aforementioned bid scope, there were no additional scope changes to the proposed work.
The bidding documents were created in a timely manner, with bids received in early February. Construction
is under way with completion expected this summer.
Thank you again for giving us the opportunity to work with you and present this amendment. If you have
any questions or concerns, please feel free to contact us.
Sincerely,
ALLIANCE ARCHITECTS
Christopher Hartz, RA
From:Chris Hartz
To:Zach Hurst
Cc:Bill Lamie
Subject:RE: Former Salvation Army Roof - quote update
Date:Monday, December 21, 2020 4:33:11 PM
Zach,
We estimate that our design fee would be no greater than $1500 using the hourly rates for
additional services. This assumes modifying the front end documents to be bid in lieu of quote,
defining the alternate in the specifications and drawings, participating in a pre-bid
conference/meeting, addressing bidder questions, reviewing bids, and providing our
recommendation. Construction Administration services would remain unchanged from the previous
proposal. Completing the documents for February bidding should not be an issue.
Please let me know if this is acceptable, and we can begin working on these changes shortly. Thanks.
Christopher Hartz
Alliance Architects
From: Zach Hurst <zhurst@southbendin.gov>
Sent: Monday, December 21, 2020 10:17 AM
To: Chris Hartz <chartz@alliarch.com>
Cc: Bill Lamie <blamie@alliarch.com>
Subject: RE: Former Salvation Army Roof - quote update
Chris-
I was able to secure some more funds for the roof and have some direction. What I’d like to do is
prepare some bid documents, instead of quote documents, with the main change being the lower
roof coating being an alternate bid item. This way we can hopefully award the more critical upper
roof portion if nothing else. Being realistic about bidding timelines, we’d probably be looking to open
bids sometime in February, with work taking place over the summer. When we opened quotes and
were over the allotted limit, our Board approved a request to advertise for public bids for the
project, so I just need the completed plans and manual to move forward.
So what I would need from Alliance would be an estimate of your design fee to revise the drawings
and project manual, and your timeline for being able to perform the revisions. I have attached our
blank front end bid documents so you can see what will need to be revised on the City side of things.
Our agreement for this project included hourly rates for additional services, so an email outlining the
added fee would suffice in lieu of an amendment to the agreement. Please let me know what
questions or concerns you have – thank you.
Zach Hurst, P.E.
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 07/01/2021
Name Zach Hurst Department DPW
BPW Date 07/27/2021 Phone Extension 3057
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer Officer Name
BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Alliance Architects
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Salvation Army Roof Repairs
Project Number 119-084B
Funding Source RWDA TIF
Account No. PO-0004341
Amount $1,500.00
Terms of Contract
Purpose/Description Amendment covers added fee to produce bid documents after quotes were
rejected as excessive.
For Change Orders Only
Amount of Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: