1. REVIEW OF MINUTES
A. Approve Regular Meeting Minutes of July 13, 2021
2. OPENING OF QUOTATIONS
A. Central Fire Station Pavement Repairs – Project No. 121-051
1. Funding: PR-00010623
3. AWARD BIDS AND APPROVE CONTRACTS
A. Three (3) More or Less, 2021 or Newer, Utility Crew Trucks – Spec C
1. Company: Jordan Ford
2. Total Amount: $236,942
a) One (1) with Alternate #1: $80,956 – Sewer Department
b) Two (2) with No Alternates: $155,986 – Street Department
3. Funding: PR-00009067
B. 2021 Brick Pavement Spot Repair – Project No. 121-019
1. Company: Acorn Landscaping & Excavation LLC
2. Amount: NTE $134,694
3. Funding: PR-00009400
C. Southeast Neighborhood Center (United Way) – Project No. 119-093R
1. Company: The Robert Henry Corporation
2. Amount: $1,168,005; Second-Lowest Bid
3. Funding: PR-00008109
4. AWARD QUOTATIONS AND APPROVE CONTRACTS
A. River Crossing 7 – Notre Dame, Access Path Improvements
1. Company: Foegley Landscape, Inc.
2. Amount: $22,205
3. Funding: PR-00010290
5. REJECT QUOTATION
A. Laurel Woods Drainage Improvements – Project No. 121-007
1. Company: Selge Construction Co., Inc.
2. Description: Quotes Rejected as Non-Responsive due to Incorrect MWBE
Utilization Form MWBE -1.0
3. Funding: PR-00010221
6. CHANGE ORDERS
A. Olive Street Reconstruction, Phase I – Project No. 114-064
1. Company: INDOT & Milestone Contractors North, Inc.
a) Change Order No.: 6
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING AGENDA
July 27, 2021 – 9:30 a.m.
Virtual Meeting Link https://tinyurl.com/2021BPWHybrid
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
Page 2
(1) Increase Amount: $3,890 City Amount; $19,450 INDOT Amount
(20/80 Split)
(2) Percent of Increase: 2.23%
b) Change Order No.: 7
(1) Increase Amount: $134,069 City Amount
(2) Percent of Increase: 6.25%
c) Change Order No.: 8
(1) Increase Amount: $2,303.92 City Amount; $11,519.58 INDOT
Amount (20/80 Split)
(2) Percent of Increase: 6.59%
(3) Total Percent of Increase for All Change Orders: 6.59%
(4) Revised Contract Amount for All Change Orders: $140,263.42 City
Amount; $165,039.08 INDOT Amount (20/80 Split); New Total of All
Change Orders: $3,503,578.49
2. Funding: PO-0009357
B. Sewer & Manhole Rehabilitation – Project No. 118-093
1. Company: Inland Water Pollution Control, Inc.
2. Change Order No.: 4
3. Decrease Amount: ($47,474)
4. Percent of Decrease: (1.51%)
5. Total Percent of Change: (0.59%)
6. Revised Contract Amount: $3,105,965.60
7. Funding: PO-000097
C. O’Brien Recreational Center Renovations – Project No. 118-091
1. Company: R. Yoder Construction, Inc.
2. Change Order No.: 3
3. Increase Amount: $17,178; Additional Eighteen (18) Days
4. Percent of Increase: 3.59%
5. Total Percent of Change: 14.3%
6. Revised Contract Amount/Completion Date: $496,163; June 18, 2021
7. Funding: PO-0005039
7. REQUEST TO ADVERTISE FOR THE RECEIPT OF BIDS
A. 2021 Drainage Improvements – Project No. 121-006A
1. Title Sheet
2. Description: Kaley St. and Marion St.
3. Funding: PR-00010684
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING AGENDA
July 27, 2021 – 9:30 a.m.
Virtual Meeting Link https://tinyurl.com/2021BPWHybrid
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
Page 3
8. RESOLUTIONS
A. Resolution No. 22-2021
A Resolution Establishing the Policy by which Members of the City of South
Bend Board of Public Works May Participate by Electronic Means of
Communication
1. Description: Adopting a Written Policy Establishing the Procedures for Board
Member’s Participation in Meetings and Electronic Communications
B. Resolution No. 23-2021
A Resolution of the City of South Bend, Indiana Board of Public Works on the
Disposal of Unfit and/or Obsolete Property
1. Description: Retirement of Firefighter Robert A. Krizmanich’s Helmet and
Boots
C. Resolution No. 24-2021
A Resolution of the City of South Bend, Indiana Board of Public Works for the
Disposal of Surplus Property
1. Description: Retirement of Sergeant Eric Downey’s Firearm
D. Resolution No. 25-2021
A Resolution of the City of South Bend, Indiana Board of Public Works on the
Disposal of Unfit and/or Obsolete Property
1. Description: One (1) FATS (FireArms Training Simulator) Machine
9. AGREEMENTS/CONTRACTS/PROPOSALS/ADDENDA
A. Joint Use and Maintenance Agreement – Indiana Department of Transportation
1. Description: Install Decorative Lettering Spelling “SOUTH BEND” on the
US 31 Bypass over Michigan Street, Project No. 120-008
2. Amount: $23,552
3. Funding: PR-00010358
B. Amendment No. 1 to Professional Services Agreement – Alliance Architects
1. Description: Additional Services to Produce Bid Documents for Former
Salvation Army Building Roof Repairs – Project No. 119-084B
2. Amount: $1,500; Total Amount: $10,800
3. Funding: PO-0004341
C. Amendment No. 1 to Owner-Engineer Agreement – VS Engineering, Inc.
1. Description: Redesign of Dubail Avenue Streetscape, Project No. 120-009
Revisions Due to Budget Constraints
2. Amount: $68,268.72
3. Funding: PO-0000821
D. Award Contract – Milestone Contractors North, Inc.
1. Description: Installation of 2” Copper Line Stops for Olive St., Phase I,
Project No. 114-064
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING AGENDA
July 27, 2021 – 9:30 a.m.
Virtual Meeting Link https://tinyurl.com/2021BPWHybrid
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
Page 4
2. Amount: $21,700, City Only
3. Funding: PR-00010655
E. Sewer and Water Service Agreement – Adams Road Development II Corporation
1. Description: Public Sewer & Water Extension to Serve Phase II of the
Bradford Shores Development
2. Title Sheet
F. Amendment No. 4 to Owner-Engineer Agreement – SmithGroup Inc.
1. Description: Additional Design Services for Seitz Park Reconstruction Phase
II, Project No. 117-093B
2. Amount: NTE $36,360 (Hourly); Adjusted Agreement Total $1,064,760
3. Funding: PO-0006606
10. LICENSES AND PERMITS
A. Street Closures for Special Events
1. Event: 21st Annual Kid’s Triathlon
a) Date/Times: July 31, 2021; 5:00 a.m. to 12:00 p.m.
b) Location: S. Greenlawn Ave., RR tracks to Wall St, Southwood
Ave./Twyckenham Dr. to Greenlawn Ave.; Belmont Ave./Twyckenham
Dr. to Greenlawn Ave. and Wall St., Greenlawn Ave. to Ironwood Dr.
2. Event: 2021 Urban Adventure Games
a) Date/Times: July 31, 2021; 6:00 a.m. to 10:00 a.m.
b) Location: St. Louis Blvd. from the South Side of E. Jefferson Blvd. to St.
Peter St.
3. Event: Payne’s Birthday Block Party
a) Date/Times: August 6, 2021; 5:00 p.m. to 12:00 a.m.
b) Location: College St. from Humbolt St. to Elwood Ave.
4. Event: South Bend Farmer’s Market Classic Car Show
a) Date/Times: August 28, 2021; 8:00 a.m. to 2:00 p.m.
b) Location: Eddy St. on North Side of Market to Dead End in front of the
Armory
5. Event: Trax Music Bash - Rescheduled
a) Date/Times: May 14, 2022; 7:00 a.m. to 12:00 a.m.
b) Location: Ignition Dr. from W. Sample St. to W. Cotter St.
B. Encroachments/Revocable Permits
1. Applicant: KRG Eddy St. Land III, LLC
a) Description: New Proposed Location for Directional Sign D6
b) Location: Robinson Community Learning Center Entrance; East Side of
Eddy Street North of Entrance Drive
c) Favorable Recommendations
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING AGENDA
July 27, 2021 – 9:30 a.m.
Virtual Meeting Link https://tinyurl.com/2021BPWHybrid
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
Page 5
11. STREET/ALLEY VACATIONS
A. Applicant: Kathleen A. Kershner
1. Location: 2234 Highland Ave.
2. Purpose: Street/Alley Maintenance
3. Unfavorable Recommendations from Engineering & Community Investment;
Does Not Meet Three (3) of the Four (4) I.C. 36-7-3-13 Criteria (1, 2, and 4)
12. RATIFY BONDS
A. Contractor Bonds
1. Cabbit Concrete, Approved effective July 15, 2021
2. Octavio Luna, Released effective August 13, 2021
B. Occupancy Bonds
1. Arborcare, Inc., Approved effective July 13, 2021
2. Cabbit Concrete, Approved effective July 15, 2021
3. Octavio Luna, Released effective August 13, 2021
4. Milestone Contractors North, Inc., Approved effective July 20, 2021
13. CLAIMS
A. Ratification of Preapproved City of South Bend Claims Payments
1. Claim No.: GBLN-19199
a) Date: 07/14/2021
b) Amount: $1,126,922.33
2. Claim Nos.: GBLN-19003, GBLN-19078
a) Date: 07/14/2021
b) Amount: $2,408,393.61
3. Claim Nos.: GBLN-19261, GBLN-19306
a) Date: 07/15/2021
b) Amount: $385,739.84
4. Claim Nos.: GBLN-19200, GBLN-19301
a) Date: 07/15/2021
b) Amount: $662,966.62
5. Claim Nos.: GBLN-19802, GBLN-18644
a) Date: 07/20/2021
b) Amount: $3,320,259.68
14. PRIVILEGE OF THE FLOOR
15. ADJOURNMENT
NOTICE FOR HEARING AND SIGHT IMPAIRED PERSONS
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
MEETING AGENDA
July 27, 2021 – 9:30 a.m.
Virtual Meeting Link https://tinyurl.com/2021BPWHybrid
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
Page 6
Auxiliary Aid or Other Services are Available upon Request at No Charge.
Please Give Reasonable Advance Request when Possible.