HomeMy WebLinkAboutChange Order No 1 - Martin Luther King Jr. Center Exterior Lighting Improvement - Martell Electric, LLC
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
June 22, 2021
Ms. Jennifer Martell
Martell Electric, LLC
4601 Cleveland Rd.
South Bend, IN 46628
jmmartell@martellelectric.com; awest@martellelectric.com
RE: Change Order No. 1 – Martin Luther King Jr. Center Exterior Lighting Improvements
Dear Ms. Jennifer Martell:
At its June 22, 2021 meeting, the Board of Public Works approved the above referenced
Change Order for an increase of $3,940 with an additional forty-four (44) days, bringing the
revised contract amount to $34,390 with a new completion date of August 31, 2021.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574)
235-9251.
Sincerely,
/s/ Anne Fuchs
Anne Fuchs, Clerk
Enclosures
AF/lh
DATE:
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS PROJECT CHANGE ORDER
6/22/2021
PROJECT NO: PROJ00000246
PROJECT NAME: MLK 2021 Exterior Improvements
CONTRACT DATE: April 27th, 2021
CHANGE ORDER NO: C0#1
SUBJECT OF CHANGE ORDER: Addition of pedestrian light pole and lead time adjustement
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time Extension of date/time by previous change orders Date/time extension by this change order New completion date/time
CONTRACTOR r/l(:((i2t!f'ir
Jenr.tfec �¾/dell 1 :Pce.skht Printed Name and itle
�o..r-\-e\l E\ed:ric, LLG
Company Name '
4�o\ weve\ ood Rd
Address
SD0+v-i. �°' lN %(o 22:>
City, State, Zip
$ ___ 3 ...... 0,_4s_o_.o_o
$ _____ o_.o_o
[K)lncreased □Decreased
$ ___ 3_0-'--,4_5_0._0_0
$ 3,940.00 ----'----$ 34,390.00 ----�--
J� 16th, 2021N
44 da�sgus 31st, 2021
12.90 %
12.90 %
RECOMMENDED FOR AP PROVAL
PROJECT MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS Approved Date: -------
Elizabeth A. Maradik, President
Jordan V. Gathers, Member
Joseph R. Molnar, Member
Gary A. Gilot, Member
Murray L. Miller, Member
Au
June 22, 2021
Date:5/21/2021
Project:MLK Exterior Lighting Upgrade
Customer:City Of South Bend
Proposal # CO #1
Description of Work:Add 1 Pole
Summary of Costs:Hours Rate Total Cost
Superintendant Labor Hours:0 $0.00 $0.00
Foreman Labor Hours: (documentation and coordination)16 $75.00 $1,200.00
Journeyman Labor Hours:0 $0.00
Apprentice Labor Hours:0 $0.00
Total Labor Cost:16 $1,200.00
Take-Off Material Cost:$2,101.09
Tax $0.00
Total Material Cost:$2,101.09
Equipment (Estimated Rental):$125.00
Other Job Expenses:$0.00
Overhead and Profit (15%):$513.91
Total Martell Electric Cost:$3,940.00
Change Order Proposal Summary
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 06/09/2021
Name: Patrick Sherman Department of Venues Parks & Arts
BPW Date: 06/22/2021 Phone Extension: 5601
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Clara McDaniels
Dept. Attorney Attorney Name Clara McDaniels
Purchasing Michael Schmidt
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 1 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Martell Electric, LLC
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Martin Luther King Jr Center Exterior Lighting Improvements
Project Number PROJ00000246
Funding Source PC-00000246
Account No. PO # 0009210
Amount $34,390.00
Terms of Contract Lump Sum
Purpose/Description This is for the addition of an additional pedestrian lighting for additional
security as identified on site walk and for time extension due to steel lead
time.
For Change Orders Only
Amount of Increase
Decrease
$ 3,940.00
($ )
Previous Amount $ 30,450.00
Current Percent of Change:
Increase
Decrease
0%
( %)
New Amount $ 34,390.00
Total Percent of Change:
Increase
Decrease
12.9%
( %)
Time Extension Amount: 44 days
New Completion Date: August 31st, 2021