HomeMy WebLinkAboutChange Order No 1 - Wastewater Treatment Plant Final Clarifiers 4-5 - Bowen Engineering Corp.
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
May 20, 2021
Mr. John Dettman
Bowen Engineering Corporation
8802 N. Meridian St.
Indianapolis, IN 46260
Johnd@BowenEngineering.com
RE: Change Order No. 1 – Wastewater Treatment Plant Final Clarifiers 4-5, Aeration Tanks
1-4, Disinfection Improvements – Project No. 119-069A
Dear Mr. Dettman:
It has come to my attention that a signature was included in error on your documentation
from the May 11, 2021 Board of Public Works meeting. I have updated the attached
documentation to remove Board Member Jordan Gather’s signature. Mr. Gathers was not present
at the time this item was voted on; therefore, his signature should not have been included.
I apologize for this administrative oversight. Please update your records accordingly and
feel free to call me with any questions at (574) 235-9251.
Sincerely,
/s/ Anne Fuchs
Anne Fuchs, Clerk
Enclosures
AF/lh
ELIZABETH A. MARADIK GARY A. GILOT JORDAN V. GATHERS JOSEPH R. MOLNAR MURRAY L. MILLER
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
May 11, 2021
Mr. John Dettman
Bowen Engineering Corporation
8802 N. Meridian St.
Indianapolis, IN 46260
Johnd@BowenEngineering.com
RE: Change Order No. 1 – Wastewater Treatment Plant Final Clarifiers 4-5, Aeration Tanks
1-4, Disinfection Improvements – Project No. 119-069A
Dear Mr. Dettman:
At its May 11, 2021 meeting, the Board of Public Works approved the above referenced
Change Order for an increase of $50,136.93, bringing the revised contract amount to
$4,323,135.93.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-9251.
Sincerely,
/s/ Anne Fuchs
Anne Fuchs, Clerk
Enclosures
AF/lh
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:4/26/2021
PROJECT NO:119-069A
PROJECT NAME:WWTP Final Clarifier Nos. 4-5, Aeration Tank Nos. 1-4 and
Disinfection Improvements (119-069A)
CONTRACT DATE:11/13/2020 Notice to Proceed
CHANGE ORDER NO.001
SUBJECT OF CHANGE ORDER:Provide epoxy coating of the existing steel embedded plates at
Final Clarifier Nos. 4 & 5. Ovivo will redesign and fabricate new
equipment column and sludge duct around existing RAS
Opening for Final Clarifier No. 4.
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns.
The original contract sum $ 4,272,999.00
Net change by previously authorized change orders $0.00
The contract sum prior to this change order $ 4,272,999.00
By this Change Order, the project amount is Increased
Decreased $ 50,136.93
The new contract sum including this change order $ 4,323,135.93
This Change Order represents a total change of 1.17 %
Total change for entire project 1.17 %
Original contracted completion date/time 05/17/2022
Extension of date/time by previous change orders 0 days
Date/time extension by this change order 0 days
New completion date/time 05/17/2022
RECOMMENDED FOR APPROVAL
CONTRACTOR Construction Manager
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Date: ______________ Contractor Signature
Printed Name and Title
Bowen Engineering Corporation
Elizabeth A. Maradik, President
Company name
8802 North Meridian Street
Gary A. Gilot, Member
Address
Indianapolis, IN 46260
Jordan V. Gathers, Member
City, State, Zip Joseph R. Molnar, Member
Nick Isenhower, Project Engineer
Nick Isenhower
Murray L. Miller, Member
04-28-2021
May 11, 2021
EJCDC® C-941, Change Order.
Prepared and published 2013 by the Engineers Joint Contract Documents Committee.
Page 1 of 1
Change Order No.001
Date of Issuance:April 26, 2021 Effective Date: April 26, 2021
Owner:City of South Bend Owner's Contract No.:119-069A
Contractor:Bowen Engineering Contractor’s Project No.:
Engineer:Arcadis US Engineer's Project No.:30029091
Project:WWTP Final Clarifier Nos. 4-5, Aeration Tank Nos. 1-4
and Disinfection Improvements (119-069A)
Contract Name:
The Contract is modified as follows upon execution of this Change Order:
Description:
1. Provide epoxy coating of the existing steel embedded plates at Final Clarifier Nos. 4 & 5. This proposal
pertains to the 19 areas around each tank for a total of 38 locations in Final Clarifier Nos. 4 & 5.
2. Ovivo will redesign and fabricate new equipment column and sludge duct around existing RAS
opening
Attachments: Contractor’s Change Order Proposals
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIMES
Original Contract Price:Original Contract Times:
Substantial Completion: April 17,2022
$ 4,272,999 Ready for Final Payment: May 17,2022 dates
No Change from previously approved Change Orders:No Change from previously approved Change Orders:
Substantial Completion: 0
$0.00 Ready for Final Payment: 0 days
Contract Price prior to this Change Order:Contract Times prior to this Change Order:
Substantial Completion: April 17,2022
$4,272,999 Ready for Final Payment: May 17,2022 dates
Increase of this Change Order:Increase of this Change Order:
Substantial Completion: 0
$50,136.93 Ready for Final Payment: 0 days
Contract Price incorporating this Change Order:Contract Times with all approved Change Orders:
Substantial Completion: April 17,2022
$4,323,135.93 Ready for Final Payment: May 17,2022 dates
RECOMMENDED:ACCEPTED:ACCEPTED:
By: By: By:
Engineer Owner (Authorized Signature) Contractor (Authorized Signature)
Title: Title
:
Title
:Date: Date
:
Date
:
Project Engineer
4/26/2021
Nick Isenhower
Project Engineer
4/27/202104-28-2021
Assistant City Engineer
Page 1 of 2
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
March 30, 2021
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project #15-21-008
RE: RFQ-002E – Clarifier 4 & 5 Steel Embed Plate Coating
Dear Mr. Burroughs:
Bowen Engineering Corporation (BEC) is pleased to provide you with pricing on the requested epoxy coating of
the existing steel embedded plates at clarifiers 4 & 5. This proposal pertains only to the 19 areas around each tank
for a total of 38 locations in clarifiers 4 & 5. This pricing is inclusive of all subcontractor, Labor, Equipment, and
Materials to complete the work as outlined in the RFQ.
Labor/Equipment: $10,702.96
Material/Sub: $28,990.00
15% Markup: $1,851.44
5% Markup Sub: $1,367.50
Bonds/Insurance: $472.03
Total Price: $43,383.9 3
Forty Three Thousand Three Hundred Eighty Three Dollars and Ninety Three Cents
Clarifications/Scope of Work
- Embedded plate surface will be abrasive blasted in accordance with SSPC-SP10 (near white metal)
- Two (2) full coats of Sikagard-62 will be applied only to plate outside surface
- No concrete modifications around plate in any kind are included
- Removal of embedded plates is not included
- Removal of embedded anchors/studs is not included
- Any lead based paint and asbestos is not included
- No overtime has been included
- Appropriate time extension shall be provided to Bowen
- Any modifications/removal of embedded plate shall be T&M
- Blasting/Epoxy of embedded plates around drop box is included
- This proposal assumes conditions and quantities of Clarifier 5 are similar to that of Clarifier 4
Page 2 of 2
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
We look forward to the opportunity to review this proposal with you. If you have any questions regarding this
proposal, feel free to contact me at 317-518-9721.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
Bowen Labor
Classification Rate/HR Hours Cost
Carpenter 72.66$ 64 4,650.24$
Carpenter Foreman 80.17$ 16 1,282.72$
Supervision LS 24 2,520.00$
Bowen Equipment
Classification Rate/Day Days Cost
Manlift 225 10 2,250.00$
Total Labor/Equipment Cost 10,702.96$
Bowen Material
Classification Rate/Unit Units Needed Cost
Sikadur 32 410 4 1,640.00$
Delta Subcontractor
Classification Rate/Unit Units Needed Cost
Labor LS 23490 23,490.00$
Equipment LS 2960 2,960.00$
Material LS 900 900.00$
Total Material/Sub Cost 28,990.00$
Page 1 of 2
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
April 12, 2021
(E-Mail)
Benjamin Burroughs
Water Resource Engineer
Arcadis U.S., Inc.
150 West Market Street Suite 278
Indianapolis, IN 46204
RE: South Bend WWTP Upgrades
Bowen Project #15-21-008
RE: -CR-003 Clarifier Column Redesign and Fabrication
Dear Mr. Burroughs:
Bowen Engineering Corporation (BEC) is pleased to provide you with pricing for Ovivo to redesign and fabricate
an alternate column and sludge duct to encompass the existing RAS opening inside Final Clarifiers 4 and 5. This
alternate solution will maintain the entire existing RAS opening and eliminate any saw cutting of the clarifier
slab. BEC will make all additional field welds of the extended sludge duct to the center column for both clarifiers.
Pricing for this change request is direct from the clarifier equipment manufacturer (Ovivo). BEC will provide all
additional installation labor/material for the new design at no cost to the Owner. This pricing is inclusive of all
Subcontractor, Labor, Equipment, and Materials to complete the work as outlined in the RFQ.
BEC Install Labor/Equipment: Included
Ovivo Design Engineering: $4,000.00
Ovivo Material/Fabrication: $2,753.00
Bowen Markup: None
Total Price: $6,753.00
Six Thousand Seven Hundred Fifty Three Dollars and Zero Cents
Clarifications/Scope of Work
- Ovivo will redesign and fabricate new equipment column and sludge duct around existing RAS
opening
- This change proposal eliminates structural concrete concerns of saw cutting the clarifier slab
- BEC will install and make all additional field connections/welding
- Design and fabrication will require an estimated 4 weeks of additional time for Ovivo.
- Substantial project competition shall be extended each day past equipment delivery from 6/21/21
- Formal design will be provided by Ovivo approximately 2 weeks after acceptance of change proposal
- Final design will require review and approval by Arcadis U.S., Inc.
Page 2 of 2
8802 North Meridian Street • Indianapolis, IN 46260 • 317.842.2616 phone • www.BowenEngineering.com
We look forward to the opportunity to review this proposal with you. If you have any questions regarding this
proposal, feel free to contact me at 317-518-9721.
Sincerely,
BOWEN ENGINEERING CORPORATION
Nick Isenhower
Project Engineer
Ovivo Design
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 04-28-2021
Name: Jacob M. Klosinski Department of Public Works – Engineering Division
BPW Date: 05-11-2021 Phone Extension:
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Clara McDaniels
Dept. Attorney Attorney Name Clara McDaniels
Purchasing Michael Schmidt
Check the Appropriate Item Type –Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 1 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Bowen Engineering Corporation
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name WWTP Final Clarifiers 4-5, Aeration Tanks 1-4, Disinfection Improvemetnts
Project Number 119-069A (PROJ-00000078)
Funding Source 642-06-605-514-442005
Account No. PR-00002751/PO-0005021
Amount See change order description below
Terms of Contract Lump Sum (Schedule of Values)
Purpose/Description The Division of Engineering and Division of Utilities request the approval of
Change Order No. 1 (increase of $50,136.93) to address Final Clarifier 4-5
tank and mechanism modifications, unforeseen conditions (see attached).
For Change Orders Only
Amount of Increase
Decrease
$ 50,136.93
($ )
Previous Amount $ 4,272,999.00
Current Percent of Change:
Increase
Decrease
1.17%
(%)
New Amount $ 4,323,135.93
Total Percent of Change:
Increase
Decrease
1.17%
(%)
Time Extension Amount:
0 Days *Adjustment to time extension will be made when equipment
delivery date is confirmed
New Completion Date: 05-17-2022