Memorandum
Monday, December 10, 2012
TO: Redevelopment Commission
FROM: Jitin Kain .-
SUBJECT: Proposal by Cardno JFNew to address drainage issues on Fellows Street.
Attached with this memo is a proposal from Cardno JFNew for design services related to the
drainage issues on Fellows St.
Drainage issues on Fellows St. were brought to light by residents as well as by Christopher Burke
Engineering,the City's consultant that is currently working on the design of the Fellows & Ireland
intersection. Staff has been committed to finding a green solution to the drainage issues that does
not adversely impact the residents of Fellows St.
Cardno JFNew is an ecological consulting and restoration firm with more than 20 years of experience
providing innovative and successful solutions to challenging environmental issues. The following 4
tasks as part of the attached proposal:
Task 1: Project Coordination
Task 2: Hydrologic/Hydraulic Modeling
Task 3: Drainage Design
Task 4: Construction Documents
Staff requests approval of the attached proposal by Cardno JFNew in the amount not to exceed
$35,500 from the SSDA TIF.
227 W. JEFFERSON BLVD. SOUTH BEND, IN 46601 I P: 574-235-9371 I FAX: 574-235-9021 I SOUTHBENDIN.GOV
Cardno
w
JFNe
Shaping the Future
December 10, 2012
Jitin Kain Cardno JFNew
Director, Planning
Department of Community Investment 708 Roosevelt Road
City of South Bend Walkerton,IN 46574
227 W. Jefferson Blvd., Suite 1200 USA
South Bend, IN 46601 Phone 574 586 3400
Fax 574 586 3446
Subject: Fellows Street Project www.cardno corn
www.cardnojfnew.com
Dear Jitin:
Cardno JFNew appreciates the opportunity to provide you with the enclosed proposal
for assisting Christopher Burke Engineering (CBE) with drainage design for the Fellows
Street— Ireland Road intersection and drainage design in areas outside of the Fellows-
Ireland intersection that contribute to drainage problems on Fellows Street.
The drainage problem areas as we understand them include 1) the intersection of
Fellows Street and Walter Street, 2) on Fellows Street just south of the intersection of
its intersection with Barbie Street and 3) at the intersection of Fellows and Chippewa
Avenue.
We look forward to working with you on this project. Please contact me should you
have any questions.
Sin erely,
an Allison
Operations Manager
for Cardno JFNew
Cell: 574 229 5078
Email: ryan.allison @cardno.com
Ryan Allison
Australia • Belgium • Canada • Ecuador • Indonesia • Kenya • New Zealand • Papua New Guinea
Peru • United Arab Emirates • United Kingdom • United States • Operations in 70 countries
Fellows Street Drainage Design ( CArcina
December 10,2012 V JFNew
WORK SCOPE
We have divided our proposed scope into two parts — Part 1: assisting Christopher Burke Engineering (CBE)with
drainage design for the Fellows Street—Ireland Road intersection and Part 2: drainage design in areas outside of
the Fellows-Ireland intersection that contribute to drainage problems on Fellows Street.The drainage problem
areas as we understand them include 1)the intersection of Fellows Street and Walter Street, 2)on Fellows Street
just south of the intersection of its intersection with Barbie Street and 3)at the intersection of Fellows and
Chippewa Avenue.
For Part 1, we have assumed that we will work like a sub-consultant to CBE (though contracted through the City of
South Bend), helping them develop a drainage solution for the Fellows-Ireland intersection design that is
acceptable both to the City of South Bend (the City)and neighborhood residents. We will provide assistance with
conceptual drainage design and details and specifications as needed, but the final construction documents remain
CBE's responsibility. For Part 2 we have assumed that we will work as the primary design engineer;that is, the
design will be prepared and stamped by Cardno JFNew. But we will prepare our drawings and specifications so
they can be efficiently incorporated into the overall CBE bid package for the larger project.
TASK 1: PROJECT COORDINATION
This task covers our effort to coordinate with the City and with CBE.This includes correspondence on an on-going
basis and face to face meetings.We have assumed at least one more meeting with the City and CBE and at least
one meeting with stakeholders in the Fellows Street neighborhood.
Subtasks include:
a. Coordination with CBE and City of South Bend
b. Stakeholder Meeting(s)
Deliverables:
1. Project slides for stakeholder meeting(s)
TASK 2: HYDROLOGIC/HYDRAULIC MODELING
We will develop an explicit model of runoff and conveyance existing conditions for the entire drainage area that
contributes runoff to the Fellows Street problem areas.The model will include runoff from the Fellows-Ireland
intersection, the runoff contributions from Walters, Barbie and Chippewa Streets as well as all the runoff generated
in and along Fellows Street. Model results will feed into the design process(TASK 3 below). We will also develop a
proposed conditions model that incorporates the various design elements, so that the runoff control provided by
each design element is accounted for in the design of"downstream" runoff controls.
Subtasks include:
a. Compile GIS/CAD coverages
b. Delineate drainage areas
c. Prepare existing conditions model
d. Prepare proposed conditions model(following Task 3.d. below)
Deliverables:
1. Existing and proposed conditions model input and output files
2. Brief technical memorandum on model results
File#0811208.00 www.cardnojfnew.com
Fellows Street Drainage Design
December 10,2012 JFNow f0
FNew
TASK 3: DRAINAGE DESIGN
As noted in the modeling scope description, the runoff-conveyance model will help us develop an integrated
solution to the drainage issues on Fellows Street. Currently, CBA has done runoff calculations to estimate runoff for
the Fellows-Ireland intersection and to size inlets along the intersection. Our modeling will link all contributing areas
—street runoff from Fellows, Ireland, Walter, Barbie and Chippewa and any other areas that ultimately contribute
drainage to these streets into one model.The modeling will help us select and properly size the Best Management
Practices (BMPs)for each problem area.
Although we have not pre-selected the BMPs per se,we are prepared to recommend and/or design vegetated
swales, bioretention basins, rain gardens, permeable paving systems, drywells, and so on, as needed. Our
proposed design sequence will be to develop/help develop concept designs for Part 1 and 2 of design; establish
buy-in and/or revise as needed.Test designs with our proposed conditions model and revise again as needed. Our
drainage designs will meet or exceed City standards for runoff control and conveyance.
Subtasks include:
a. Part 1:Assist CBA with Fellows/Ireland intersection drainage design
b. Part 2: Drainage design outside of Fellows/Ireland intersection
c. Proposed conditions model
d. Concept Designs
Deliverables:
1. Part 1 Concept Design sketches
2. Part 2 Concept Design sketches
TASK 4: CONSTRUCTION DOCUMENTS
For Part 1, advising on the CBE intersection design, we have assumed CBE will develop the construction
documents and that we will provide drainage design advice.This scope and budget includes our submittal of
sketches, some limited details in CAD and sample specifications for Part 1 to CBE.
For Part 2, we have assumed that as the design engineer, we will deliver the entire design documentation for the
Fellows Street problem areas outside of the Fellows-Ireland intersection.We have also assumed that we will deliver
the Part 2 design deliverables both in hardcopy and electronic format(CAD and WORD documents).The electronic
format will allow CBE to efficiently incorporate our design into their complete construction documents.We will also
include an engineer's estimate of costs for our Part 2 design. Lastly, we will provide a maintenance plan to the City
for the BMPs that we design on this project.
Subtasks include:
a. 50%design drawings
b. 95%design drawings
c. Final construction documents
d. Maintenance Plan
Deliverables:
1. Part 1—concept drawings, example details and specifications
2. Part 2—50%design drawings, hardcopy and CAD files
3. Part 2—95%design drawings, hardcopy and CAD files
4. Part 2— 100% design drawings, hardcopy and CAD files
5. Part 2—specifications
6. Part 2—Engineer's estimate of costs
7. Part 1 and Part 2— Maintenance plans
8.
File#0811208.00 www.cardnojfnew,com
Fellows Street Drainage Design
December 10,2012 JFNewno
IVew
Project Component Cost Basis Estimated Cost
Project Coordination, Hydrologic/Hydraulic Modeling, Time and Materials not
$35,484.00
Drainage Design, Construction Documents to Exceed
Respectfully su mitted by:
iyan Allison
Cardno JFNew